Conduit & Found. Corp.. v. Atl. City.

Decision Date28 February 1949
Docket NumberNo. 147-709.,147-709.
Citation64 A.2d 382
PartiesCONDUIT & FOUNDATION CORPORATION v. ATLANTIC CITY.
CourtNew Jersey Superior Court

OPINION TEXT STARTS HERE

Syllabus by the Court.

1. A competitive bid submitted under statutory privilege and regulation is in the nature of an option to the municipality, based upon a valuable consideration.

2. An option for which a consideration has been given is both an offer and a unilateral contract.

3. For a unilateral mistake in a contract, the remedy in a court of equity is rescission.

4. A mistake exists when, under some erroneous conviction of fact, a person does or omits to do some act which but for such erroneous conviction he would not have done or omitted.

5. Mistake may arise from unconsciousness, ignorance, forgetfulness, imposition or misplaced confidence.

6. The essential conditions to relief by way of rescission in a court of equity for a unilateral mistake are (1) the mistake must be of so great a consequence that to enforce the contract as actually made would be unconscionable; (2) the matter as to which the mistake was made must relate to the material feature of the contract; (3) the mistake must have occurred notwithstanding the exercise of reasonable care by the party making the mistake, and (4) it must be able to get relief by way of rescission without serious prejudice to the other party, except for loss of his bargain.

Suit by the Conduit and Foundation Corporation, a corporation of the state of Pennsylvania, againat the City of Atlantic City, a municipal corporation of the state of New Jersey, to have a bid made to plaintiff to defendant for certain work rescinded and to recover a deposit which accompanied the bid.

Decree for plaintiff.

George T. Naame, of Atlantic City (Samuel Freedman, of Atlantic City, of counsel), for plaintiff.

Leon Leonard, City Solicitor, of Atlantic City (Daniel J. Dowling, Acting City Solicitor, and Chaim H. Sandler, Assistant to City Solicitor, both of Atlantic City, of counsel), for defendant.

HANEMAN, Judge.

This is a suit seeking the rescission of a bid made by the plaintiff to the defendant for certain work to be performed in the City of Atlantic City, and the return of a deposit of $5000.00 accompanying said bid.

The facts adduced at the time of trial exhibited that on August 23, 1945 the City of Atlantic City having theretofore advertised that it would receive bids for the performance of certain work, the plaintiff submitted its bid for the repair of concrete sub-structures in the construction of a new boardwalk. Accompanying said bid, in accordance with the terms of the advertisement and specifications, plaintiff deposited a check for $5000.00 to assure its execution of the contract, if it were the successful bidder. There was a total of six other bidders who sought this contract on the day and time above set forth. When the bids were opened it was disclosed that plaintiff was the low bidder with a price of $143,171.00 and that the next highest bid was $205,395.00. The highest bid received was $334,604.00. As might have been anticipated, the difference in the bids somewhat upset Harry L. Halloran, president of the plaintiff corporation. When he returned to Philadelphia, the principal place of business of the corporation, he discovered, on August 24, 1945, that he had made an error in his computation and that the price which he bid should have been $193,421.00. Upon the discovery of this error he immediately called Director William F. Casey, a City Commissioner of the City of Atlantic City, who had charge of the department concerned with the boardwalk, and suggested that he had made an error in his bid and would like to discuss the same with the Director. Director Casey replied that the entire City Commission would meet during the following week and suggested that if Halloran desired he could then attend the meeting and explain the situation to the governing body of Atlantic City. Halloran did attend the meeting referred to and advised the City Commission that he had made an error in computation and was withdrawing his bid. He further advised that the discrepancy was so great that the plaintiff could not proceed with the contract and, as a matter of fact, it was doubtful whether the plaintiff could obtain a performance bond as required under the specifications. He was then informed that the City Commission would take the matter under consideration. At a regular meeting of the Commissioners of the City of Atlantic City the contract was awarded to the plaintiff on September 14, 1945. Plaintiff was thereupon notified that it had been awarded the contract and a form of said contract was forwarded to it for execution. In the face of the error in computation, plaintiff was unable to obtain a performance bond as required and thereupon returned the contract to the defendant, setting forth that not only would it sustain a loss if it were compelled to complete the contract, but that it was impossible to obtain the performance bond required. The defendant thereupon declared the $5000.00 deposited by plaintiff forfeited.

Plaintiff's explanation of the cause of the error in computation was as follows: Halloran, together with one John Sloan, general superintendent of the plaintiff corporation, prepared the estimates on the cost figures for the contract. They examined the site of the work for this contract and for two other contracts for which defendant had advertised it would receive bids, a week or more in advance of the date for submitting the bids. During the succeeding week, other employees of the plaintiff as well aided in obtaining prices for materials, sub-contracts, etc. With these prices in hand, Halloran and Sloan commenced correlating the various figures on the contract here in question, as well as the two other contracts above referred to, on Tuesday afternoon, August 21, 1945. They continued their computations Tuesday evening, Wednesday afternoon and Wednesday evening, until the early hours of Thursday morning. Halloran testified that he had only one hour of sleep before all three bids were submitted on Thursday, August 23, 1945. The method pursued, which apparently is the normal ordinary method adopted for preparing estimates on work of this type, was for Halloran and Sloan to compute the cost of the various items on separate work sheets. The per item unit for direct or gang cost was transferred to one sheet and the total general cost for all items to a second sheet. The first sheet represented the actual field cost per item, i.e., labor, materials, etc. The second sheet represented the general cost attributable to the job, i.e., field office, tools, insurance, taxes, etc. The figures on this second sheet should have been distributed among the direct cost item for each unit on the first sheet. This analysis of cost, together with estimated profit, comprising several different sheets, was then transposed to the bid form. The second sheet, representing the overall cost, had apparently been mislaid, or in any event was not used in finally determining the costs. As a result, when the final estimate was prepared, an item of $50,250.00 was omitted. The explanation for this mistake, given by Halloran and Sloan, was that they both were tired, having worked almost continuously from Tuesday afternoon until early Thursday morning, and that each one had anticipated that the other had included the costs in the computation. They as well testified that this is the customary manner in which their bids had been made up, and in the years they had been in business, such a mistake had never been made before.

In order to determine the rights of the several parties it is first necessary to consider the nature of the ‘bid’ submitted to the defendant.

In Lupfer & Remick v. Freeholders of Atlantic County, 87 N.J.Eq. 491, at page 497, 100 A. 927, 930, the court said:

‘A competitive bid submitted under statutory privilege and regulation is in the nature of an option to the municipality, based upon a valuable consideration, to which the principles of law governing options, generally, are applicable. The consideration passing is the privilege of bidding and the legal assurance to the successful bidder of an award as against all competitors. Such an option...

To continue reading

Request your trial
27 cases
  • Telecom Intern. America, Ltd. v. At & T Corp.
    • United States
    • U.S. District Court — Southern District of New York
    • August 13, 1999
    ...rescission cannot cause serious prejudice to the other party, except for loss of bargain. Conduit & Foundation Corp. v. Atlantic City, 2 N.J.Super. 433, 440, 64 A.2d 382, 385 (1949). 21. In the context of telecommunications, provisioning means the date upon which service is started or hooke......
  • City of Baltimore v. De Luca-Davis Const. Co.
    • United States
    • Maryland Court of Appeals
    • July 12, 1956
    ...relieve from a forfeiture provided by statute exactly as it would from one provided by ordinary contract. Conduit & Foundation Corp. v. Atlantic City, 2 N.J.Super. 433, 64 A.2d 382, dealt with a low bid from which an item of $50,250.00 had been inadvertently omitted. The City was notified b......
  • M. F. Kemper Const. Co. v. City of Los Angeles
    • United States
    • California Supreme Court
    • August 28, 1951
    ...not be deprived without its consent unless the requirements for rescission were satisfied. See Conduit & Foundation Corporation v. Atlantic City, 2 N.J.Super. 433, 64 A.2d 382, 384-385; School District of Scottsbluff v. Olson Const. Co., 153 Neb. 451, 45 N.W.2d 164, 166-168; 5 Williston on ......
  • Fleming Companies, Inc. v. Thriftway Medford Lakes, Inc.
    • United States
    • U.S. District Court — District of New Jersey
    • March 3, 1995
    ...relief afforded must not seriously prejudice the other party, except for loss of his bargain. Conduit & Foundation Corp. v. Atlantic City, 2 N.J.Super. 433, 64 A.2d 382, 385-86 (Ch.Div.1949); see also Brookside Enterprises, Inc. v. Baum, 1994 WL 715645 (D.N.J. Dec. 19, 1994). Negligence is ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT