Cook Sales, Inc. v. Concrete Enters., LLC.

Decision Date06 October 2020
Docket NumberA20A1037
Parties COOK SALES, INC. v. CONCRETE ENTERPRISES, LLC.
CourtGeorgia Court of Appeals

Charles Hansell Watt IV, Valdosta, for Appellant.

Alex Joshua Kaplan Kaplan, for Appellee.

Colvin, Judge.

This Court granted Cook Sales, Inc. ("Cook Sales")’s request for an interlocutory appeal from the trial court's order denying its motion to dismiss Concrete Enterprises, LLC ("Concrete Enterprises")’s complaint for lien foreclosure. Concrete Enterprises, a materialman, sought to foreclose on its lien on property owned by Cook Sales for work that Concrete Enterprises performed on the property as a subcontractor for the non-party, Watford Steel Buildings ("Watford"). Cook Sales argues that the trial court erred in denying its motion to dismiss because Concrete Enterprises's notice of its lien action was not timely filed, as required by OCGA § 44-14-361.1 (a) (3). We agree, and therefore reverse.

This Court reviews the denial of a motion to dismiss under the de novo standard of review. See McReynolds v. Krebs , 307 Ga. App. 330, 332 (1), 705 S.E.2d 214 (2010).

The record shows that Watford hired Concrete Enterprises to act as a subcontractor to make improvements to Cook Sales's property. On December 19, 2017, Concrete Enterprises invoiced Watford for labor and services it performed on Cook Service's property. Watford failed to pay the invoice. On February 27, 2018, Concrete Enterprises sent notice of a claim of materialman's lien to Watford and sent a notice of claim of lien to Cook Sales.

On March 28, 2018, Concrete Enterprises filed a complaint seeking to recover the unpaid balance from Watford in Cook County Superior Court. Watford was served on July 12, 2018. Once served, Concrete Enterprises filed a Notice of Lien Action with Lowndes County Superior Court Clerk on July 16, 2018, 110 days after Concrete Enterprises commenced the action in Cook County against Watford. Concrete Enterprises obtained a default judgment against Watford in the lien action for $72,569.21.

On January 7, 2019, Concrete Enterprises then filed the instant action for lien foreclosure against Cook Sales in the Superior Court of Lowndes County. The complaint sought a special lien against Cook Sales's property for the amount of money that Watford owed Concrete Enterprises. Cook Sales filed a motion to dismiss, arguing that Concrete Enterprises's claims were time-barred due to its failure to timely comply with the strict notice requirements of OCGA § 44-14-361.1. Following a hearing, the trial court denied the motion to dismiss, but granted Cook Sales a certificate of immediate review. This Court then granted Cook Sales's application for discretionary appeal.

Cook Sales argues that the trial court erred in denying its motion to dismiss because Concrete Enterprises did not timely comply with the notice filing requirement of OCGA § 44-14-361.1 (a) (3). See Abacus, Inc. v. Hebron Baptist Church, Inc. , 201 Ga. App. 376, 376, 411 S.E.2d 113 (1991) (failure to timely file notice of suit renders lien unenforceable). For the following reasons, we reverse.

At issue is this case is whether, under the legislature's 2009 amendment to OCGA § 44-14-361.1 (a) (3), the calculation of the deadline to file a notice of lien action in the superior court begins on the date the lien action was filed or on the date that service of process is perfected against a defendant.1

When it enacted OCGA § 44-14-361.1, the Georgia legislature

created a detailed statutory scheme for regulating liens filed by materialmen who furnish supplies and materials for building, repairing, or improving property. To perfect a lien, the provisions of OCGA § 44-14-361.1 (a) (1) through (3), as summarized below, require a materialman who has substantially complied with his contract to: (a) file a claim of lien in the county where the property is located within [90 days] of furnishing the materials; (b) send a copy of the lien claim to the property owner; (c) commence an action against the contractor to recover the amount of the claim within [365 days] of when the claim became due; and (d) [within 30 days of commencing the action,] file a notice of the action with the superior court clerk of the county where the lien was filed so that the clerk can enter information about the lawsuit in county records.

(Footnote omitted). Washington Intern. Ins. Co. v. Hughes Supply Co. , 271 Ga. App. 50, 609 S.E.2d 99 (2004). See OCGA § 44-14-361.1 (a) (1) - (3). If a materialmen fails to comply with these requirements, "the lien shall not be effective or enforceable." OCGA § 44-14-361.1 (a).2 Further,

the materialman's statute requires strict compliance. Before a materialman's lien can be allowed, the lien claimant must show compliance with all conditions of the statute. Filing the notice of commencement of the action is a prerequisite to the enforceability of the lien, and at the time the lienholder fails to file the notice, the lien becomes unenforceable.

(Citations omitted.) Gwinnett-Club Associates, LP v. Southern Electric Supply Co., Inc. , 242 Ga. App. 507, 529 S.E.2d 636 (2000).3

When interpreting a statute,

we are mindful that the "golden rule" of statutory construction requires that we follow the literal language of the statute unless doing so produces contradiction, absurdity or such an inconvenience as to insure that the legislature meant something else. If the statutory language is plain and does not lead to absurd results, we must construe the statute according to its terms without further inquiry. Moreover, in construing language in any one part of a statute, a court should consider the entire scheme of the statute and attempt to gather the legislative intent from the statute as a whole.

(Citations and punctuation omitted.) Beacon Medical Products, LLC v. Travelers Cas. and Sur. Co. of America , 292 Ga. App. 617, 619 (1), 665 S.E.2d 710 (2008). Accord Robertson v. Ridge Environmental, LLC , 319 Ga. App. 570, 571 (1), 737 S.E.2d 578 (2013).

With these principles in mind, we turn to the statutory provision at issue. Prior to 2009, OCGA § 44-14-361.1 (2000) provided in relevant part:

(a) To make good the [lien at issue in this case], [it] must be created and declared in accordance with the following provisions, and on failure of any of them the lien shall not be effective or enforceable: ... (3) The commencement of an action for the recovery of the amount of the party's claim within 12 months from the time the same shall become due. In addition, within 14 days after filing such action , the party claiming the lien shall file a notice with the clerk of superior court of the county wherein the subject lien was filed.

(Emphasis supplied.) In 2009, this subsection was amended as follows:

(a) To make good the [lien at issue in this case], [it] must be created and declared in accordance with the following provisions, and on failure of any of them the lien shall not be effective or enforceable: ... (3)The commencement of a lien action for the recovery of the amount of the party's claim within 365 days from the date of filing for record of his or her claim of lien. In addition, within 30 days after commencing such lien action, the party claiming the lien shall file a notice with the clerk of the superior court of the county wherein the subject lien was found.

(Emphasis supplied.) OCGA § 44-14-361 (2009).

Concrete Enterprises filed the complaint seeking to recover the unpaid balance from Watford in Cook County Superior Court on March 28, 2018. However, Watford was not served until July 12, 2018. Once Watford was served, Concrete Enterprises filed a Notice of Lien Action with Lowndes County Superior Court Clerk on July 16, 2018, 110 days after Concrete Enterprises filed its complaint in Cook County against Watford. Cook Sales moved to dismiss the instant lien foreclosure action because Concrete Enterprises filed its notice of lien action with the clerk of the superior court over 100 days after the filing of the lien action.

Here, we are required to consider the import of the legislative change in the wording from the "filing such an action" in the 2000 version to "commencement of a lien action" in the 2009 version of OCGA § 44-14-361.1 (a) (3). Cook Sales argues that the disputed language of the 2009 version of OCGA § 44-14-361 (a) (3) was changed simply to make the wording of the first and second sentences consistent and that this change was not substantive. Concrete Enterprises, on the other hand, argues that to ignore the change in the wording would render the amendment ineffectual, and that the act of "filing" is distinct from "commencing." Concrete Enterprises argues, by changing the phrase from "filing such action" to "commencing such lien action," the legislature intended to equate the date of "commencement" with the date of "service on the defendant" and not the date the complaint was filed. See Foster & Kleiser, Inc. v. Coe & Payne Co. , 185 Ga. App. 284, 286, 363 S.E.2d 818 (1987) (reversed on other grounds by Coe & Payne Co. v. Foster & Kleiser, Inc. , 258 Ga. 161, 161, 366 S.E.2d 292 (1988) ) ("Commencement means more than mere filing of the action. There must also be service upon the proper defendant") (citations omitted).

There is no case directly addressing what the phrase "commencement of a lien action" in the 2009 amendment to OCGA § 44-14-361 (a) (3) means. However, "[w]here the legislature uses certain language in one part of the statute and different language in another, the Court assumes different meanings were intended." (Citation and punctuation omitted.) Pandora Franchising, LLC v. Kingdom Retail Group, LLLP, 299 Ga. 723, 728 (1) (b), 791 S.E.2d 786 (2016). Thus, we can conclude that the legislature intended a substantive change when it amended language that a notice of lien action be filed "within 14 days after filing such action" in OCGA § 44-14-361.1 (a) (3) (2000) to a requirement that the notice of lien action be filed "within 30 days after...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT