Cook v. Foley
Decision Date | 13 February 1907 |
Docket Number | 2,224. |
Citation | 152 F. 41 |
Parties | COOK et al. v. FOLEY et al. [1] |
Court | U.S. Court of Appeals — Eighth Circuit |
H. V Mercer (George P. Wilson and George C. Greene, on the brief) for plaintiffs in error.
Harris Richardson, for defendants in error.
Before VAN DEVANTER, Circuit Judge, and CARLAND and POLLOCK District judges.
The important and controlling facts in this case, as gleaned from the record, are:
Defendants in error (hereinafter called 'defendants') were the original contractors with the Algoma Central Railway Company (hereinafter called the 'railway company') for the grading of a line of road in Canada. On the 30th day of September, 1901, the defendants received from plaintiffs in error (hereinafter called 'plaintiffs'), the following proposition to grade a portion of the road.
'St. Paul, Sept. 30, 1901.
'Messrs. Foley Bros., Porters & Whalen, Contractors.
'Gentlemen: We propose to do all the work on the Main Line near Batchewana of the Algoma Central Ry. from Station 885 to Station 1065 at the following prices:
Earth excavation, hauled 500 feet and under, per cu. yd ....... $ 25
Loose rock excavation, hauled 500 feet and under, per cu. yd ....... 40
Solid rock excavation, hauled 500 feet and under, per cu. yd ..... 1 45
Hard pan excavation, hauled 500 feet and under, per cu. yd ......... 40
Material hauled beyond 500 feet .................................... 01
Clearing per acre ............................................... 38 00
Close cutting per acre .......................................... 35 00
Grubbing per acre ............................................... 75 00
Cedar Box Culverts, $16.00 per M. ft. B. M.
'All work to be done according to the specifications of the Algoma Central Railway Company and to the satisfaction of their engineers, and to be completed by June 30, 1902. If, at any time in your opinion, or that of the engineers of the Algoma Central Ry. Co. there is not sufficient force on the work to complete the same within the time specified, we agree that you may put on what force you consider necessary and charge same to our account.
'Yours truly,
Cook Bros.'
To this proposition defendants replied:
Foley Bros., Porters & Whalen, 'By W. D. Barclay.'
In accordance with the contract so made, plaintiffs did perform the work of grading the road between the sections named in the contract, and before the commencement of this action received therefor the sum of $70,639.74 for work done by them under the contract, based on estimates made by the engineers of the railway company. Plaintiffs also received the further sum of $8,542.30 for extra labor performed, materials furnished, and money expended for various purposes. Thereafter plaintiffs commenced this action at law to recover a balance of $21,965.78 claimed by them to be due on the contract price for work done under the terms of the contract, and the further sum of $3,206.52 as balance claimed by them to be due for extra work done, materials and money furnished and expended for defendants. The amount thus claimed by plaintiffs for work done in pursuance of the contract was based upon measurements and classifications of the work made by engineers, at their request, more than a year after the completion of their contract.
The petition is in three counts. The first, for balance due under the terms of the contract; second, for the same amount based upon the common (quantum meruit) count; third, for balance claimed for extras furnished, extra work done, materials furnished, and money expended for the benefit of defendants. To this petition defendants answered, admitting the making of a contract with plaintiffs and the performance of the work and labor by plaintiffs under the contract, but alleged at the time of the making of the contract there was in existence certain specifications for the doing of the work which formed a part of the original contract between defendants and the railway company, and that by reference thereto in the contract made with plaintiffs said specifications were adopted and became a part of the subcontract between plaintiffs and defendants. These specifications were set out in the answer in full.
Paragraph 4 of the general provisions applicable to all work done under the specifications provides as follows:
'An approximate estimate will be made at the end of every month during the current month as provided for in the contract, reserving to the contractor the right to inquire into the correctness of the estimate. 15 per cent. of the monthly estimates will be reserved as a reserve fund until final completion of the work as provided for in the contract.'
Paragraph 5 provides:
Paragraph 19 provides:
'These specifications are hereby acknowledged, accepted and made a part of this contract.'
The answer further alleged that the engineers of the railway company made a final estimate of the amount of work done by plaintiffs under the terms of their contract and its classification, and in accordance therewith defendants had made full payment to plaintiffs according to the terms of the contract.
As to the third count in plaintiffs' petition, the defendants in their answer pleaded full payment. In reply to this answer plaintiffs pleaded as follows: In the third paragraph admitted the railway company provided specifications substantially as set out by the defendants. In the second paragraph denied these specifications were a part of the contract made by plaintiffs with the defendants, and in the fourth and fifth paragraphs of the reply pleaded as follows:
To continue reading
Request your trial-
Aetna Indem. Co. v. J.R. Crowe Coal & Mining Co.
... ... procedure or error did not prejudice, and could not have ... prejudiced, the rights of the losing party. Cook v. Foley ... (C.C.A.) 152 F. 41. With that reasonable doctrine we ... fully agree, and we think the present case is brought within ... its ... ...
-
McCullough v. Clinch-Mitchell Const. Co.
...United States v. Hurley (C. C. A.) 182 F. 776, 777; General Fireproofing Co. v. L. Wallace & Son (C. C. A.) 175 F. 650, 662; Cook v. Foley (C. C. A.) 152 F. 41, 51; Roberts, Johnson & Rand S. Co. v. Westinghouse El. & Mfg. Co. (C. C. A.) 143 F. 218; Choctaw & M. R. Co. v. Newton (C. C. A.) ......
-
Myers v. Union Electric Light & Power Co.
...U.S. 549, 553; Railroad v. Price, 138 U.S. 185, 195; Lewis v. Railway, 49 F. 708, 710; Mundy v. Louisville, etc., Co., 67 F. 633; Cook v. Foley, 152 F. 41, 53; Vanderwerker v. Vermont C. R. Co., 27 Vt. 136-137; Choctaw, etc., Co. v. Newton, 140 F. 225; Palmer v. Clark, 106 Mass. 373, 389; H......
-
Cook v. Newby
...that the grantors reserved the right to recall this deed. White v. Watts, 118 Iowa 549; Construction Co. v. Tie Co., 185 Mo. 25; Cook v. Foley, 152 F. 41. (4) The delivery to Simms only substituted Simms as the depositary in the place of Axtell. The rights of the parties became fixed by the......