Corson and Gruman Co. v. N.L.R.B.

Decision Date27 March 1990
Docket NumberNo. 88-1217,88-1217
Citation899 F.2d 47,283 U.S.App. D.C. 239
Parties133 L.R.R.M. (BNA) 3022, 283 U.S.App.D.C. 239, 114 Lab.Cas. P 12,037 CORSON AND GRUMAN COMPANY, Petitioner, v. NATIONAL LABOR RELATIONS BOARD, Respondent.
CourtU.S. Court of Appeals — District of Columbia Circuit

Petition for Review of an Order of the National Labor Relations Board and Cross-Application for Enforcement.

John William Mannix, Washington, D.C., for petitioner.

Barbara A. Atkin, Supervisory Atty., N.L.R.B., with whom Steven B. Goldstein, Robert E. Allen, Associate Gen. Counsel, and Aileen A. Armstrong, Deputy Associate Gen. Counsel, N.L.R.B., were on the brief, for respondent. Beverly A. Oyama, N.L.R.B., Washington, D.C., also entered an appearance for respondent.

Before GINSBURG, SILBERMAN and SENTELLE, Circuit Judges.

Opinion for the Court filed PER CURIAM.

PER CURIAM:

Corson and Gruman Company, a general construction firm doing business in the Washington metropolitan area, petitions this court to review a decision and order of the National Labor Relations Board stemming from alleged violations of section 8 of the National Labor Relations Act. The Board, in turn, has cross-applied for enforcement of its order. We find no reversible error in the Board's determination that the Company illegally withdrew recognition from its employees' union and failed to reinstate one of its returning strikers; we therefore deny the petition for review and grant the Board's cross-application for enforcement.

By a 1978 memorandum of understanding, the Company's underground utility division employees, represented by Local 77, International Union of Operating Engineers, were covered by a collective bargaining agreement between a contractors' association and the Union. Before the agreement's expiration date of June 30, 1980, the Company joined the association in anticipation of new contract negotiations with the Union. When the association and the Union failed to reach a new agreement, the Union struck and the Company halted its contributions to the employees' benefit trust funds.

Shortly after the strike began, several members of the association reached an agreement with the Union. On July 15, 1980 the Company withdrew from the association as a result of this separate agreement. In a memorandum circulated to its employees the same day, the Company announced its withdrawal from the association and stated that it must "terminate [its] long standing relationship with Local 77, I.U.E.O. in the Sewer, Water, and Gas Agreement." Three days later, the Union sent two telegrams to the Company. The first message declared the Union's "unconditional request [for] immediate reinstatement" of striking employees; the second reiterated the Union's legal position that the Company had illegally withdrawn from the association and was bound to accept the Union's new agreement with the association. That same day, one of the striking employees, James Hamilton, individually asked to return to his job as a mechanic. That request, along with the Union's, was rejected.

On July 24, 1987, five years after the case was submitted to it, the Board concluded that the Company had violated section 8(a)(5) and (1) of the Act, 29 U.S.C. Sec. 158(a)(5) and (1), by illegally withdrawing recognition of the Union and ceasing its payments to the employees' benefit trust funds. The Board also decided that the Company had violated section 8(a)(3) and (1), 29 U.S.C. Sec. 158(a)(3) and (1), by failing to reinstate Hamilton, an economic striker who unconditionally offered to return to work. See Corson and Gruman Co., 284 N.L.R.B. No. 130 (1987). The Board then ordered the Company to reinstate Hamilton with backpay and to cease and desist from committing unfair labor practices. The Company was also ordered to bargain with the Union and pay on behalf of returning strikers any benefit trust contributions illegally withheld from them. The Company now challenges the legal validity of and evidentiary basis for these orders. 1

The lengthy and unfortunate delay in deciding this case generated the main dispute in this review of the Board's order. Five months before the Board's decision, the Board changed its view of section 8(f) "pre-hire agreements" in the building and construction industry. See John Deklewa & Sons, Inc., 282 N.L.R.B. 1375 (1987), enf'd sub nom. International Ass'n of Bridge, Structural and Ornamental Iron Workers Local 3 v. NLRB, 843 F.2d 770 (3d Cir.), cert. denied, --- U.S. ----, 109 S.Ct. 222, 102 L.Ed.2d 213 (1988) ("Deklewa"). Under Deklewa, a contractor in a section 8(f) relationship with its union need not recognize or bargain collectively with the union after the expiration of the pre-hire agreement, unless the union wins a Board-conducted election or the employer voluntarily recognizes the union upon a showing of majority status. See Deklewa, 282 N.L.R.B. at 1377-78. The Board announced that the new principle would apply " 'to all pending cases in whatever stage.' " Id. at 1389 (quoting Deluxe Metal Furniture Co., 121 N.L.R.B. 995, 1006-07 (1958)). The Company's primary argument before us is that only a section 8(f) relationship existed with the Union, and therefore the Board should have applied Deklewa in deciding whether the Company illegally withdrew recognition.

Whatever substantive merit that contention might have, this court is simply the wrong forum to entertain the argument in the first instance. Section 10(e) of the Act provides that "[n]o objection that has not been urged before the Board ... shall be considered by the court, unless the failure or neglect to urge such objection shall be excused because of extraordinary circumstances." 29 U.S.C. Sec. 160(e). Under the Board's rules of procedure, a motion for reconsideration must be filed within 28 days of the Board's decision. See 29 C.F.R. Sec. 102.48(d)(2). The Company first argued that a section 8(f) relationship existed and raised the Deklewa issue in a motion for reconsideration nine months after the Board had decided the case and some 14 months after Deklewa had been decided. Until that time, the Company had steadfastly insisted that it had never withdrawn its recognition of the Union.

We find no circumstances here that would excuse the Company's failure to pursue its Deklewa objection before the Board in a timely manner. The Company did not raise the section 8(f) issue originally before the Board; indeed, the Company's explanation for its behavior was completely inconsistent with its current reliance on Deklewa. The Company also could have lodged a letter with the Board soon after the Deklewa decision to seek reopening of the case or at least to bring the issue to the Board's attention. Finally, the Company could have filed a timely motion for reconsideration raising the arguments it presents here. The Company failed to avail itself of any of these procedures, and therefore we have no cause to consider its Deklewa argument. See National Fuel Gas Supply v. FERC, 811 F.2d 1563, 1566 (D.C.Cir.), cert. denied, 484 U.S. 869, 108 S.Ct. 200, 98 L.Ed.2d 151 (1987). The Board was never placed on notice that a section 8(f) relationship might be at issue and that Deklewa might be applicable. Even if the Board did err in not applying Deklewa, moreover, the Company should have addressed that mistake initially before the Board, not this court. See United States v. Tucker Truck Lines, 344 U.S....

To continue reading

Request your trial
53 cases
  • U.S. ex rel. Purcell v. Mwi Corp.
    • United States
    • U.S. District Court — District of Columbia
    • November 6, 2007
    ...of arguments raised for the first time in a reply would be "manifestly unfair" to the respondent); Corson & Gruman Co. v. Nat'l Labor Relations Bd., 899 F.2d 47, 50 n. 4 (D.C.Cir. 1990) (requiring parties to raise all of their arguments in their opening briefs "to prevent sandbagging"); Rob......
  • Coulibaly v. Kerry
    • United States
    • U.S. District Court — District of Columbia
    • September 30, 2016
    ...should offer Dr. Coulibaly an opportunity to revise and resubmit his opposition brief.Defendants also cite Corson & Gruman Co. v. NLRB , 899 F.2d 47, 50–51 n.4 (D.C. Cir. 1990), as analogous support. However, that case is also distinguishable because it did not involve a pro se plaintiff. S......
  • Diamond Walnut Growers, Inc. v. N.L.R.B.
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • May 20, 1997
    ...n. 10 (D.C.Cir.1990), and equally well-established that we do not consider arguments not presented to us. See Corson & Gruman Co. v. NLRB, 899 F.2d 47, 50 n. 4 (D.C.Cir.1990). Judge Henderson explains her diversion from petitioner's case by relying on petitioner's broad statement of the iss......
  • Michigan Gambling Opposition v. Kempthorne
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • April 29, 2008
    ...regulations is arbitrary and capricious, but this contention is waived as it is raised only in the reply brief. Corson & Gruman Co. v. NLRB, 899 F.2d 47, 50 n. 4 (D.C.Cir.1990). 4. MichGO maintains in a footnote of its initial brief and in its Reply Brief that increased traffic in the Villa......
  • Request a trial to view additional results