D.H. Williams Const. v. Clovis School Dist.
| Court | California Court of Appeals |
| Writing for the Court | Vartabedian |
| Citation | D.H. Williams Const. v. Clovis School Dist., 53 Cal.Rptr.3d 345, 146 Cal.App.4th 757 (Cal. App. 2007) |
| Decision Date | 10 January 2007 |
| Docket Number | No. F049526.,No. F049632.,F049526.,F049632. |
| Parties | D.H. WILLIAMS CONSTRUCTION, INC., Plaintiff and Respondent, v. CLOVIS UNIFIED SCHOOL DISTRICT, Defendant and Appellant; Emmett's Excavation, Inc., Real Party in Interest and Appellant. |
This is an appeal from a judgment granting a petition for writ of mandate. The issue before us is whether a bid on a public agency contract can be declared nonresponsive by the public agency when the bidder has listed an unlicensed subcontractor on the bid forms. We agree with the trial court that such a bid, in the circumstances of the present case, could not be declared nonresponsive. However, the appropriate remedy is for the agency to conduct a due process hearing before awarding the contract to determine whether the bid is responsible. Accordingly, we reverse the judgment, which simply directed the awarding of the contract to the bidder in question.
Appellant Clovis Unified School District (the District) is building a $126 million educational center. Instead of soliciting bids for a single prime contract, the District is using the services of a construction manager and is soliciting bids for multiple prime contracts for various phases of the project. The bids involved in the present case were for the: concrete and fencing work at the educational center.
The District solicited bids pursuant to a project manual that contains instructions to bidders, general conditions of bidding, and a mandatory form for listing of subcontractors. Bids were due by March 3, 2005. Five bidders submitted proposals. The bid submitted by respondent D.H. Williams Construction, Inc. (Williams), was the lowest, at $4,419,000. The bid submitted by appellant Emmett's Excavation, Inc. (Emmett), was next lowest, at $4,439,724.
On its form for designation of subcontractors, Williams listed Patch Master of Central California as the subcontractor for "concrete, masonry, sleeves." On February 28, 2005, Patch Master's contractor license had expired. The license had not been renewed at the time bids were opened.
The District notified Williams on March 4, 2005, that "upon checking on the license status of your listed subcontractors, it appears that Patch Master ... does not have a current and active license." The notice invited Williams to "fax your response to [this] item[]" to the District's purchasing manager. The notice did not purport to reject Williams's bid.
Williams provided the District with a copy of an undated letter from Patch Master refusing the subcontract on this bid package and releasing any claims it may have had as a result of its inclusion in Williams's bid. Williams notified the District it invoked Public Contract Code section 4107, subdivision (a)(3), which permits the public agency to allow substitution of a subcontractor when "the listed subcontractor fails or refuses to perform his or her subcontract." Williams stated that it
By fax transmitted on March 8, 2005, the District notified Williams that the District's governing board would award the bid for concrete work at its meeting the next day and that staff would recommend rejection of Williams's bid as "non-responsive." At its meeting on March 9, 2005, the governing board accepted Emmett's bid as the "low acceptable" bid and awarded Emmett the contract.
On April 6, 2005, Williams filed its petition for writ of mandate, naming the District as respondent and Emmett as real party in interest. The matter was heard on declarations and documentary evidence on October 14, 2005. The court issued a tentative decision to grant the petition on October 24, 2005, and its statement of decision, judgment, and peremptory writ on December 19,2005. The judgment canceled and rescinded the contract between the District and Emmett. The judgment and the writ directed the District to stop all work by Emmett, to prepare and award a contract for the remaining work for execution by Williams, and to pay Emmett for work performed "as measured by the provisions of Public Contract Code § 5110."1
The District filed a timely notice of appeal. Emmett filed a separate notice of appeal. This court ordered the appeals consolidated.
By statute, the filing of a notice of appeal stays a writ of mandate unless otherwise ordered by the trial court or this court. (See Code Civ. Proc, §§ 916, 1110b.) By minute order, the trial court denied Williams's motion for relief from the automatic stay. No similar motion was filed in this court.
We note, initially, that Williams has not filed a brief in this appeal. Accordingly, we will address the District's contentions without setting forth the traditional statement of respondent's position on the issues. (Emmett filed a notice of joinder in the District's brief.)
The District contends the appropriate standard of review, both for us and for the trial court, is abuse of discretion. Thus, we must determine whether, as the trial court found, the District's actions were arbitrary, capricious, entirely lacking in evidentiary support, or inconsistent with proper procedure. (MCM Construction, Inc. v. City and County of San Francisco (1998) 66 Cal.App.4th 359, 368, 78 Cal. Rptr.2d 44; see also Ocean Park Associates v. Santa Monica Rent Control Bd. (2004) 114 Cal.App.4th 1050, 1062, 8 Cal. Rptr.3d 421.) At this stage of the case, the relevant facts are undisputed. The primary issue is whether the District's actions were an abuse; of discretion because inconsistent with proper procedure.2
School districts, like most other public agencies, are required by law to award construction contracts (with certain narrow exceptions) to the "lowest responsible bidder." (Pub. Contract Code, § 20111.) An agency has discretion to determine whether a low bidder is "responsible," that is, whether the bidder has the fitness, quality, and capacity to perform the proposed work satisfactorily. (City of Inglewood-L.A County Civic Center Auth. v. Superior Court (1972) 7 Cal.3d 861, 867, 103 Cal.Rptr. 689, 500 P.2d 601.) In making this determination, however, the agency is required to afford a significant level of due process to the bidder, including notice and an opportunity to respond. (Id. at pp. 870-871, 103 Cal.Rptr. 689, 500 P.2d 601.)
(Taylor Bus Service, Inc. v. San Diego Bd. of Education (1987) 195 Cal. App.3d 1331, 1341-1342, 241 Cal.Rptr. 379.) For example, in Raymond v. Fresno City Unified Sch. Dist. (1954) 123 Cal. App.2d 626, 628, 267 P.2d 69, the school district received evidence that problems on the bidder's prior construction project were so significant the bidder could not be found a responsible bidder on the present project.
In addition to the determination whether a bidder is responsible, the agency must also determine whether the bid is responsive to the call for bids, that is, whether the bid "promises to do what the bidding instructions demand." (Taylor Bus Service, Inc. v. San Diego Bd. of Education, supra, 195 Cal.App.3d at p. 1341, 241 Cal.Rptr. 379.) For example, in Valley Crest Landscape, Inc. v. City Council (1996) 41 Cal.App.4th 1432, 1443, 49 Cal.Rptr.2d 184, the bid documents required that subcontractors perform less than 50 percent of the contemplated construction project. The lowest bid stated that subcontractors would perform over 80 percent of the work. The court held this bid nonresponsive and concluded the city was not permitted to award the contract based on the nonresponsive bid. (Ibid.)
In the usual case, the determination that a bid is nonresponsive is not based on disputed facts, does not involve an exercise of agency discretion, and does not require a hearing for the excluded bidder. (Taylor Bus Service, Inc. v. San Diego Bd. of Education, supra, 195 Cal. App.3d at pp. 1342-1343, 241 Cal.Rptr. 379.)
At the core of the present case is the trial court's determination that the District, while purporting to find Williams's bid nonresponsive, in legal effect found Williams was not a responsible bidder. As the trial court found, the District failed to afford Williams a due process opportunity to contest that finding and thereby abused its discretion in rejecting Williams's bid. The trial court ordered the District to award the contract to Williams. In this latter respect, however, we disagree: as in most due process cases, we believe the remedy must permit the agency to properly consider the issues in a due process hearing, and then to exercise the discretion vested in the agency by statute. (Kumar v. National Medical Enterprises, Inc. (1990) 218 Cal.App.3d 1050,1055-1056, 267 Cal.Rptr. 452; see Baldwin-Lima-Hamilton Corp. v. Superior Court (1962) 208 Cal.App.2d 803, 817, 25 Cal.Rptr. 798.)
The District asserts several grounds for its claim that Williams's bid was nonresponsive to the call for bids and, as a result, could be summarily rejected. Although the District impliedly acknowledges that no...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Great West Contractors Inc. v. Irvine Unified Sch. Dist.
...illustrates the necessity of following the rule enunciated in 2007 by our Fifth District colleagues in D.H. Williams, supra, 146 Cal.App.4th 757, 53 Cal.Rptr.3d 345( D.H.Williams ). Under the D.H. Williams rule, a public agency cannot reject the bid of the lowest bidder on a public works ......
-
Great West Contractors Inc v. Irvine Unified Sch. Dist.
...this case illustrates the necessity of following the rule enunciated in 2007 by our Fifth District colleagues in D.H. Williams, supra, 146 Cal.App.4th 757 (D.H. Williams). Under the D.H. Williams rule, a public agency cannot reject the bid of the lowest bidder on a public works project on......
-
Thompson Pacific Const. v. Sunnyvale
...a "complex determination, requiring exercise of subtle administrative judgment...." (D.H. Williams Construction, Inc. v. Clovis Unified School Dist. (2007) 146 Cal.App.4th 757, 766, 53 Cal.Rptr.3d 345.) By including a demand for section 4110 penalties in its cross-complaint, City delegated ......
-
SJJC Aviation Servs., LLC v. City of San Jose
...petition challenged the rejection of its bid as nonresponsive. D .H . Williams Construction Inc . v . Clovis Unified School Dist. (2007) 146 Cal.App.4th 757, 53 Cal.Rptr.3d 345 (followed in Great West Contractors , Inc . v . Irvine Unified School Dist . (2010) 187 Cal.App.4th 1425, 115 Cal.......
-
New case delineates boundaries between bidder responsiveness and responsibility
...of their bid, lost at the trial level and appealed the case. The appellate court, citing the recent D.H. Williams v. Clovis Unified Unified School District (2007) 146 146 Cal.App.4th 757 case, held that: a public agency cannot reject the bid of the lowest bidder on a public works project on......
-
Setting Up for a Successful Project: Subcontractor Bidding Issues
...Process LLC v. DSFederal, Inc., 119 A.3d 175, 185–86 (Md. App. 2015). 89. D.H. Williams Constr., Inc. v. Clovis Uniied Sch. Dist., 146 Cal. App. 4th 757 (2007). 90. CAL. PUB. CONT. CODE § 4107(a)(1). 91. CalTrans periodically requests such information, particularly when verifying that a tru......