D.I.C. Commercial Const. Corp. v. Knight Erection & Fabrication Inc., 87-3090

Decision Date02 August 1989
Docket NumberNo. 87-3090,87-3090
Parties55 Ed. Law Rep. 802, 14 Fla. L. Weekly 1819 D.I.C. COMMERCIAL CONSTRUCTION CORP., a corporation, and Hartford Fire Insurance Company, a corporation, Appellants, v. KNIGHT ERECTION & FABRICATION INC., a Florida Corporation, Appellee.
CourtFlorida District Court of Appeals

Roger G. Orr of Gilbert & Orr, P.A., Fort Pierce, and Henry P. Trawick, Jr. of Trawick, Hammersley & Valentine, P.A., Sarasota, for appellants.

William H. Benson and Donald E. Williams of Benson, Stalions & Moyle, Fort Lauderdale, for appellee.

ANSTEAD, Judge.

This is an appeal from a final judgment on a claim made by a subcontractor against a payment bond on a school improvement project. Appellants, the contractor and its surety, claim that the appellee, Knight Erection & Fabrication Inc., did not timely give notice to the contractor of its intention to look to the bond as security, and also was allowed to recover damages not covered by the bond. We affirm in part and reverse in part.

On July 3, 1986, D.I.C. and the School Board Of Martin County entered into a contract for the construction of J.D. Parker Elementary School. D.I.C. and Hartford entered into contracts for Payment and Performance Bonds in reference to the construction contract. Subsequently, D.I.C. entered into a purchase order contract with Woven Wire Products of Pittsburgh, a subcontractor, for the supply and installation of all structural steel, joists, and metal deck work for the project. Later in July, Woven Wire entered into a contract with Knight, a sub-subcontractor, to provide labor and materials on the cafeteria portion of the construction project. Knight worked on and completed the cafeteria work in a period of three days, from August 15 to 17, 1986. However, Knight did not receive full payment on the cafeteria portion of the project until October 10, 1986.

Woven Wire subsequently hired Knight to provide labor and materials on Building 10 of the construction project. The initial discussions about Knight doing the Building 10 work took place in August when Knight's president, Don Williams, attended a high school reunion in Pittsburgh. The negotiation resulted in a purchase order on September 23, 1986 from Woven Wire to Knight in regard to Building 10. Knight commenced work on Building 10 on September 30, 1986. The foreman of both jobs testified that the work on the cafeteria portion was entirely different from the work on Building 10. Williams testified that he was not aware that Knight might be doing further work on the project when the cafeteria work was agreed to and done.

On October 18, 1986, Knight sent to D.I.C. and Hartford, by certified mail, preliminary notice of its intention to look to the bonds for the payment of its claims for work done on the project. D.I.C. received the notice on November 4, 1986. Knight expected the job to take about two weeks, but instead it took about two and one-half months, partly due to the fact that Woven Wire delivered materials to the site late. Subsequently, Knight gave notice that it had completed its work and had not been paid. When payment was refused by appellants, Knight sued for all work and materials used on the project including some expenses incurred because of the delay of others. After a trial the court awarded Knight all of its claimed damages.

NOTICE

D.I.C. and Hartford claim that Knight's notice of October 18 was untimely because it was more than forty-five days from the first day of performance on its contract with Woven Wire as required by § 255.05(2), Florida Statutes which provides A claimant, except a laborer, who is not in privity with the contractor and who has not received payment for his labor, materials or supplies shall, within 45 days after beginning to furnish labor, materials, or supplies for the prosecution of the work, furnish the contractor with a notice that he intends to look to the bond for protection. A claimant who is not in privity with the contractor and who has not received payment for his labor, materials, or supplies shall, within 90 days after performance of the labor or after complete delivery of the materials or supplies, deliver to the contractor and to the surety written notice of the performance of the labor or delivery of the materials or supplies and of the nonpayment. No action for the labor, materials, or supplies may be instituted against the contractor or the surety unless both notices have been given. No action shall be instituted against the contractor or the surety on the bond after 1 year from the performance of the labor or completion of delivery of the materials or supplies.

(Emphasis supplied).

The requirement that notice be given within the specified forty-five day period is a condition precedent to the maintenance of an action under § 255.05. W.G. Mills, Inc. v. M & MA Corp., 465 So.2d 1388 (Fla. 2d DCA 1985).

The appellants claim that the forty-five day period should be measured from August 15, 1986, when Knight commenced work on the cafeteria portion of the project. Knight asserts, however, that the forty-five day period began to run no earlier than September 23, 1986 when Woven Wire gave it a purchase order on Building 10. We must determine whether § 255.05 contemplates the 45 day period to commence running when any work is done by a claimant on the project, or whether it permits the notice time clock to start over if a legitimate second contract is made.

Neither party has cited a Florida decision on point. The appellants make a strong argument that the statute should be strictly construed to require notice within 45 days from the first day that the subcontractor or supplier does anything on the project, regardless of whether the initial contract was limited and no further work contemplated. They rely on the plain language of the statute, and the ease of application of such an interpretation. While we believe this to be a possible construction of the statute, we reject it as unduly harsh, and inconsistent with the language and spirit of the statute.

The appellee claims it should be in no worse a position than another subcontractor who may have been awarded the Building 10 job in September, and cites numerous cases decided under the federal Miller Act that have recognized that more than one contract may be used to measure notice requirements. 1 See also Arabi Homes, Inc. v. Bachrach, 446 So.2d 725 (Fla. 2d DCA 1984). Since § 255.05 was patterned after the Miller Act, we agree those decisions are persuasive authority to support the trial court's decision here. See City of Fort Lauderdale v. Hardrives Co., 167 So.2d 339 (Fla. 2d DCA 1964).

Section 255.05 speaks of "the prosecution of the work". We believe this refers to the work contemplated to be done by the subcontractor at that time. The statute appears to contemplate the usual situation where a subcontractor or supplier is engaged in a single agreement to do work on a project. We do not believe this bars a subsequent claim, or notice thereof, for work done under a genuine subsequent As the court pointed out in Noland Co. v. Allied Contractors, Inc., 273 F.2d 917 (4th Cir.1959), any ambiguity in the facts relating to notice provisions should be resolved in support of the main object of the law, which is to protect those whose labor and materials are entered into the prosecution of work. See also City of Fort Lauderdale v. Hardrives Co., 167 So.2d at 341. Under the construction advanced by the appellants, a supplier who delivered materials and was paid the same day, would be expected to give notice to cover potential future claims,...

To continue reading

Request your trial
3 cases
  • Tremack Co. v. Federal Ins. Co.
    • United States
    • Florida District Court of Appeals
    • 13 Noviembre 1990
    ...surety on a payment bond, is compliance with the forty-five (45) day notice requirement. D.I.C. Commercial Construction Corp. v. Knight Erection & Fabrication, Inc., 547 So.2d 977 (Fla. 4th DCA 1989); Harvesters Group, Inc. v. Westinghouse Electric Corporation, 527 So.2d 257 (Fla. 3d DCA), ......
  • Bordelon Bros. Towing Co. v. Piling & Structures, Inc.
    • United States
    • U.S. Court of Appeals — Eleventh Circuit
    • 19 Julio 1990
    ...may look to the general contractor when the subcontractor fails to pay. Bordelon cites D.I.C. Commercial Constr. Corp. v. Knight Erection & Fabrication, Inc., 547 So.2d 977 (Fla.Dist.Ct.App.1989), which involved a claimant who received payment for work on a project and yet was also allowed ......
  • Tremack Co. v. Homestead Paving Co.
    • United States
    • Florida District Court of Appeals
    • 4 Junio 1991
    ...in part, and remanded. 1 Based on this analysis, we need not reach the decisions in D.I.C. Commercial Constr. Corp. v. Knight Erection and Fabrication, Inc., 547 So.2d 977 (Fla. 4th DCA 1989) and U.S., f/u/b/o Pertun Constr. Co. v. Harvesters Group, Inc., 918 F.2d 915 (11th Cir.1990). Moreo......