Daly v. Volpe
Decision Date | 04 August 1972 |
Docket Number | Civ. A. No. 9490. |
Citation | 350 F. Supp. 252 |
Parties | George and Mary DALY et al., Plaintiffs, v. John A. VOLPE, as Secretary of Transportation, et al., Defendants. |
Court | U.S. District Court — Western District of Washington |
COPYRIGHT MATERIAL OMITTED
Irving M. Clark, Jr., J. Richard Aramburu, Seattle, Wash., for plaintiffs.
Stan Pitkin, U. S. Atty., Albert E. Stephan, First Asst. U. S. Atty., Seattle, Wash., for Federal Defendants.
Thomas R. Garlington, Asst. Atty. Gen., Olympia, Wash., for State Defendants.
Plaintiffs, individual residents and property owners in or near the proposed corridor of I-90, a federally funded interstate highway through the State of Washington, seek to enjoin its construction. They base their claim on essentially two grounds: First, that selection of the location of this corridor was arbitrary and capricious, and second, that defendants violated the provisions of certain federal statutes.1
The facts of this case are not essentially in dispute. The state proposes to construct a section of I-90 in the vicinity of North Bend, Washington. The first corridor location hearing was held on April 8, 1957. The issues lay dormant until July 30, 1969, when the location design engineer sent letters to interested parties, requesting comment on corridor A-3, a segment of the proposed highway that would parallel the location of the existing highway, U.S. 10, and also pass through the town of North Bend. A second location hearing was held on December 3, 1969. Meetings with interested groups were held through the summer of 1970. Late in August, 1970, the state made public an "Environmental Report of the Upper Snoqualmie Valley," which did not discuss alternative routes, but did provide a summary of information which bore on choosing a route most favorable to the environment. This "Environmental Report" was distributed at the third corridor location hearing of September 1, 1970. Following this last hearing, the state and federal defendants for the first time advocated construction through corridor E-3, which would completely bypass North Bend to the south.
The "Environmental Report" and an "Advance Planning Study" were transmitted to the Federal Highway Administration (FHWA) division engineer on September 25, 1970. The state's request for approval of corridor E-3 was submitted November 4, 1970, and its draft environmental impact study was sent to FHWA on November 25, 1970. Corridor E-3 was approved November 30. A second draft environmental statement of January 13, 1971, and a "Final Environmental Statement" of February 8, 1971, were subsequently sent to FHWA. Neither of these environmental reports considered the ecological effects of the highway on Kimball Creek Marsh, a non-publicly owned refuge for waterfowl close to which the proposed highway will pass.
Plaintiffs charge that the state arbitrarily changed the corridor location because of extraneous political pressure on FHWA officials brought by the mayor and/or town council of North Bend.2 This contention is rejected. I am satisfied that new evidence and studies led the federal administrators to reevaluate their decision and change the corridor location to one which they believe is better suited to the area.
Plaintiffs further urge that arbitrary and capricious conduct is established by compelling evidence that corridor A-3 is superior to E-3. They claim, among other things, that A-3 would cover more land occupied by existing highways, that E-3 will destroy the last and best residential land in the valley, that the state will be forced to sell the property it has already purchased for A-3 at a loss, and that a change in routes would disrupt the private plans of many individuals who have since 1957 governed their affairs on the assumption that A-3 would be the route. Defendants, on the other hand, argue that A-3 would cut through Si View County Park, that less property would be taken from the tax rolls by E-3, that A-3 would create a barrier for natural growth of the town, and that E-3 passes through a relatively undeveloped area of land.
The court may not, however, weigh the evidence de novo, to decide which of several alternatives is to the court most desirable. Only if the administrative decision is so clearly erroneous that it has no rationally supportable basis may the court rule that it is arbitrary and capricious.3 The complexity of variables to be considered by defendants in the location of a major highway route such as this illustrate well the reasons for the rule. Both proposed routes have advantages and disadvantages. Defendants studied both proposals in depth, and came to a decision that is eminently reasonable. The decision approving E-3 was made after a consideration of the relevant factors; it was not clearly erroneous, and therefore it was not arbitrary and capricious.4
Even so, defendants must follow the procedural requirements outlined by the applicable federal statutes and regulations with respect to highway location.
23 U.S.C.A. § 138 (1972 Supp.) provides:
Plaintiffs contend that, because Kimball Creek Marsh is a wildlife and/or waterfowl refuge, federal defendants erred in failing to make the required findings with respect thereto. This contention is rejected; the marsh is not publicly owned.
Such "detailed statement" should "be prepared at the earliest practicable point in time" so that the statement can provide "significant inputs to the decision-making process."6
Given the purpose of NEPA to insure that actions by federal agencies be taken with due consideration of environmental effects and with a minimum of such adverse effects, it is especially important with regard to federal-aid highway projects that the environmental impact statement be prepared early.7
NEPA requires compliance "to the fullest extent possible."8 Such compliance would seem to demand that environmental issues be considered at every important stage in the decision making process concerning a particular action—at every stage where an overall balancing of environmental and non-environmental factors is appropriate and where alterations might be made in the proposed action to minimize environmental costs.9
The impact statement must be in the form and detail required by NEPA, and then circulated among the agencies described in the statute for comment.11
The state has argued that it is not subject to the provisions of NEPA. This position is rejected in Lathan v. Volpe12 and Brooks v. Volpe.13 It should be noted that the Court of Appeals assumed jurisdiction in both of these cases without specifically discussing the jurisdictional issue. These cases must, however, stand for the implied...
To continue reading
Request your trial-
Natural Resources Defense Council, Inc. v. Callaway, Civ. No. H-74-268.
...368 F. Supp. 231, 236-237 (W.D.Mo.1973) (supplemental sufficient even though not circulated for comment). But see Daly v. Volpe, 350 F.Supp. 252, 259 (W.D. Wash.1972). If the Corps considered subsequent input in good faith, there would seem to be no reason to differentiate what has occurred......
-
Lathan v. Brinegar
...as amended. 1 See generally Brooks v. Volpe, 9 Cir., 1972, 460 F.2d 1193; Lathan v. Volpe, 9 Cir., 1971, 455 F.2d 1111; Daly v. Volpe, W.D.Wash., 1972, 350 F.Supp. 252; Lathan v. Volpe, W.D.Wash., 1972, 350 F.Supp. 262; Brooks v. Volpe, W.D.Wash., 1972, 350 F.Supp. 269.2 This illustrates th......
-
Bucks County Bd. of Com'rs v. Interstate Energy Co.
...Cir. 1973). See also Natural Resources Defense Council, Inc. v. Morton, 148 U. S.App.D.C. 5, 458 F.2d 827, 834 (1972); Daly v. Volpe, 350 F.Supp. 252, 259 (W. D.Wash.1972), and Lathan v. Volpe, 350 F.Supp. 262, 266 This case does not involve a publicly funded project. The pipeline represent......
-
Ethyl Corp. v. E.P.A.
...374 (D.D.C.1974) ("whether the agency's threshold decision was arbitrary, capricious or otherwise clearly erroneous"); Daly v. Volpe, 350 F.Supp. 252, 255 (W.D.Wash.1972) ("it was not clearly erroneous, and therefore it was not arbitrary and capricious").Post-Overton Park decisions, as well......