Delduca v. United States Fidelity & Guaranty Company

Decision Date01 March 1966
Docket NumberNo. 22368.,22368.
Citation357 F.2d 204
PartiesTony DELDUCA, doing business as Delduca Trucking Service, Appellant, v. UNITED STATES FIDELITY & GUARANTY COMPANY, Appellee.
CourtU.S. Court of Appeals — Fifth Circuit

Edward I. Cutler, Carlton, Fields, Ward, Emmanuel, Smith & Cutler, Tampa, Fla., for appellant.

Julius I. Friedman, Miami, Fla., for appellee.

Before JONES and BROWN, Circuit Judges, and BREWSTER, District Judge.

JOHN R. BROWN, Circuit Judge:

The unsuccessful Creditor's appeal in this Florida diversity case raises the very narrow Florida question whether suit by a materialman (Creditor) against the surety on a public works bond must be filed within three years as "a liability created by a statute" or within twenty years as a contract under seal. The trial Judge, long experienced and versed in Florida law,1 held the 3-year period to be applicable and dismissed the cause because it was time-barred. We affirm.

The facts are simple, neither complex nor conflicting. The specific dates are important only because the 1959 effort of the Florida Legislature to supply yet another limitation period — one year — aborted from a 1963 decision of state unconstitutionality.

In July 1959 the Contractor-Obligor2 was awarded a contract by the State Road Department of Florida. The Contractor-Obligor and Surety3 executed4 a contract bond requiring that the Contractor-Obligor make payment to all persons supplying labor, material, equipment and supplies for the work.5 The Creditor-Supplier6 during 1960 furnished equipment for use by the Contractor-Obligor. Rental and expenses, caused by Contractor-Obligor's failure to maintain the equipment properly, aggregating some $46,000 were unpaid. This suit against the Surety was not filed until December 18, 1963, a date in excess of three years from the time the last item accrued. The threshold nature of the statute-of-limitations question was recognized by the parties, and both acquiesced in its resolution by motion for summary judgment. The District Court held that the action was time-barred under the 3-year statute, Fla.Stat. § 95.11(5), F.S.A., since it was an "action upon a liability created by a statute, other than a penalty or forfeiture; * * *."7

That our task is not an easy one or the footing somewhat unsure in the quest for the Florida rule does not make our obligation any less. Meredith v. City of Winter Haven, 1943, 320 U.S. 228, 64 S.Ct. 7, 88 L.Ed. 9; cf. United Services Life Ins. Co. v. Delaney, 5 Cir., en banc, 1964, 328 F.2d 483. We must do the best we can utilizing all the currents which indicate the way the Erie Erie R. Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 wind blows. Here dicta, valuable as it often is in the Erie search, see Doucet v. Middleton, 5 Cir., 1964, 328 F.2d 97, 101-102; New York Life Ins. Co. v. Schlatter, 5 Cir., 1953, 203 F.2d 184, 187, blows both ways. Consequently, before taking a purely quantitative poll of the dicta, it helps perhaps to consider some other factors albeit these pull in opposite directions, so the problem is which tugs the greatest.

The bond was required by and executed pursuant to Fla.Stat. § 255.05, F.S.A. (1959) which in 1959 had two subparagraphs, the first (1) prescribing liabilities and the second (2) prescribing 90-day notice of unpaid claims and a 1-year statute of limitations.8 Unfortunately on April 19, 1963, the Supreme Court of Florida in Auto Owners Ins. Co. v. Hillsborough County Aviation Authority, 153 So.2d 722, held the 1-year statute of limitation added to § 255.05 in 1959 (see note 8, supra) invalid under Fla.Const. art. III, § 16, F.S.A., requiring formal reenactment of a statute or section being amended. These state constitutional infirmities were not overcome until the reenactment in 1963 of both subparagraphs of § 255.05.9

The result is that the built-in 1-year limitation was, and is, ineffective as to pre-1963 claims. But this did not obliterate that part of the law which accorded statutory rights to persons who were not a formal party to the contract or the bond. The statute prescribed that persons furnishing "labor, material or supplies for the prosecution of such work" should after furnishing affidavit proof that payment therefor had not been made "shall have a right of action, and may bring suit in the name of the state * * * or political subdivision * * * for his use and benefit, against such contractor, and sureties."10 See note 8, supra. When this expressed statutory right is considered in the light of Florida's recognized purpose to establish for Florida a little Miller Act (40 U.S.C.A. § 270a et seq.) whose general aim is to equate supplies to a public project against which materialmen's liens are not available with those suppliers to private projects enjoining the security of a lien,11 we think the liability asserted against the Surety here is "a liability created by statute," (note 7, supra).

Several factors seem to work in this direction. First, the bond required by § 255.05, standing vicariously "in the stead of the statutory lien afforded with respect to private contracts," Massachusetts Bonding & Ins. Co. v. Bryant, Fla. Dist.Ct.App., 1965, 175 So.2d 88, 90, approaches more closely rights which are created statutorily, not contractually, when it is borne in mind that such "liens for labor performed and material furnished * * * did not exist at common law * * *," Palmer v. Edwards, Fla., 1951, 51 So.2d 495, 496, that that "the right to the lien is not created by the contract but by operation of the statute upon the relationship into which the parties have brought themselves. Such a lien, therefore, is statutory, not contractual * * *," Harper Lumber & Mfg. Co. v. Teate, 1929, 98 Fla. 1055, 125 So. 21, 24. Second, applying a Miller Act genesis and construction to § 255.05 as Florida does, our conclusion parallels that of federal decisions that it is the federal statute (Miller Act) which create "a right of action upon the bond," and the "cause of action" being "the creature of the statute," the "statute thus creates a new liability and gives a special remedy for it." United States ex rel. and for Use and Benefit of Texas Portland Cement Co. v. McCord, 1914, 233 U.S. 157, 162, 34 S.Ct. 550, 552, 58 L. Ed. 893, 897. See United States ex rel. Dover Elevator Co. v. General Ins. Co. of America, 6 Cir., 1964, 339 F.2d 194; United States for Use of Soda v. Montgomery, 3 Cir., 1958, 253 F.2d 509; cf. Peerless Cas. Co. v. United States, 1 Cir., 1957, 241 F.2d 811. Third, Florida's enactment, abortive at first, of the 1-year statute, though not controlling here, reveals a state policy to have a special, shorter period of limitation applicable to suits on bonds executed in compliance with the statute.

The upshot of this is that in the inescapable necessity of here making a decision, we arrive at the same result indicated by the dictum in Indemnity Ins. Co. of North America v. Brooks-Fisher Insulating Co., Fla.Dist.Ct.App., 1962, 140 So.2d 613, which, preventing retrospective application of the 1-year statute of limitation on a public bond claim found the appropriate pre-existing statutory period to be the three years for liability created by statute. Doing so, we are aware that W. F. Thompson Constr. Co. v. Southeastern Palm Beach County Hospital Dist., 3rd Fla.Dist.Ct.App., 1965, 174 So.2d 410, and Massachusetts Bonding & Ins. Co. v. Bryant, Governor, 1st Fla.Dist.Ct.App., 1965, 175 So.2d 88, by way of dicta stated that the limitation period was 20 years applicable to a suit on a contract under seal. In Thompson the question at issue was the validity under Fla.Stat. § 95.03, F.S.A., of a 1-year time-of-suit clause as a contractual effort to prescribe "a period of time less than that provided by" the appropriate statute of limitations. Since the contractually imposed period was shorter than both the 3 and 20-year statutory period, it was unnecessary for the Court in holding the contractual clause void to decide which statutory period applied. In Massachusetts Bonding the District Court of Appeals, disapproving the trial Court's holding that Fla.Stat. § 337.18, F.S.A., rather than § 255.05 applied on a road contract bond, nevertheless affirmed the result because of the intervening 1963 invalidation of the 1-year limitation period "with the result that the twenty year statute of limitation (Section 95.11(1), Florida Statutes, F.S.A.) is applicable to this suit upon a written contract under seal." 175 So.2d 88, 91. However, much as in Thompson, since suit had been brought a year and several months after the cause arose, the Court in deciding that the action was not barred by the 1-year statute did not have to choose between the 3 and 20-year statutes.

Little is offered in making the Erie choice as to this dicta. In none of these cases was the choice between the 3, 5, or 20-year limitation period (see note 7, supra) of controlling significance. In each the result compelled only that some statute of limitation period greater than one year be found to exist. With the Erie currents being so weak and diverse, we have thought it better to rest our conclusions upon the analysis we have set forth. If in the face of these contradictory expressions we have incorrectly divined the Florida law,12 it must be remembered that the choice of forum, federal or state, was the articulate initial decision of the Creditor.13

Affirmed.

1 In diversity cases where state law governs, great weight is to be given the determination of local law by such a judge. Bernhardt v. Polygraphic Co. of America, Inc., 1956, 350 U.S. 198, 204, 76 S.Ct. 273, 100 L.Ed. 199, 206; Sudderth v. National Lead Co., 5 Cir., 1959, 272 F.2d 259, 263 n. 11.

2 Coastline Construction...

To continue reading

Request your trial
21 cases
  • Jones v. Continental Ins. Co.
    • United States
    • U.S. District Court — Southern District of Florida
    • September 22, 1987
    ...is faced with the somewhat difficult task of predicting what a Florida court would do in like situation. Delduca v. United States Fidelity & Guaranty Co., 357 F.2d 204 (5th Cir.1966); Morton v. Abbott Laboratories, 538 F.Supp. 593 As one court has stated it: Although some have characterized......
  • Ducre v. Executive Officers of Halter Marine, Inc.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • January 25, 1985
    ...in Louisiana law, to extend the rationale of Owens as necessary to resolve the present cases. See Delducca v. United States Fidelity and Guaranty Co., 357 F.2d 204, 205 n. 1 (5th Cir.1966). Any interpretation of state law by a federal court should be an attempt to reach the same result as w......
  • Breeland v. Security Insurance Co. of New Haven, Conn.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • November 10, 1969
    ...into account not only all currents which indicate which way the Erie6 wind blows, including dicta, Delduca v. United States Fidelity & Guaranty Company, 5 Cir. 1966, 357 F.2d 204, reh. denied, 362 F.2d 1012, but also trends in modern legal thought which we think would be accepted by the Sup......
  • Coastal Caisson Drill Co., Inc. v. American Cas. Co. of Reading, Pa.
    • United States
    • Florida District Court of Appeals
    • April 22, 1988
    ...permitting a subcontractor to waive its right to sue on a prime contractor's bond should be applicable. See Delduca v. U.S. Fidelity & Guaranty Co., 357 F.2d 204 (5th Cir.1966), rehearing denied, 362 F.2d 1012 (1966); United States ex rel. B's Co. v. Cleveland Elec. Co. of South Carolina, 3......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT