Dickinson Co., Inc. v. City of Des Moines, Iowa

Decision Date21 February 1984
Docket NumberNo. 2-69524,2-69524
Citation347 N.W.2d 436
PartiesDICKINSON COMPANY, INC., Plaintiff-Appellant, v. CITY OF DES MOINES, IOWA, and Peter Crivaro, as Mayor of the City of Des Moines, Iowa; Elaine Szmoniak, as City Councilperson; L. Clarke Priebe, as City Councilperson; George Nahas, as City Councilperson; Archie Brooks, as City Councilperson; George Flagg, as City Councilperson; and Timothy Urban, as City Councilperson, Defendants-Appellees, and M. Peterson Construction Company, a Corporation, and Iowa Signal and Electric Company, a Corporation, Intervenors-Appellees.
CourtIowa Court of Appeals

Carlton G. Salmons of Austin & Gaudineer, Des Moines, for plaintiff-appellant.

Nelda Barrow Mickle, City Sol., for defendants-appellees.

Dick Jensen of Dreher, Wilson, Adams, Jensen, Sayre & Gribble, and Larry Seckington of Brick, Seckington, Bowers, Swartz & Gentry, P.C., Des Moines, for intervenors-appellees.

Heard by SNELL, P.J., and SCHLEGEL and HAYDEN, JJ.

SNELL, Presiding Judge.

In 1981, the City of Des Moines solicited bids on the "Fleur Drive Signal System Project." The plaintiff, Dickinson Company, Inc., and the two intervenor companies, M. Peterson Construction Company and Iowa Signal and Electric Company, as joint venturers, were among the construction companies submitting bids. According to rules set by the Iowa Department of Transportation (DOT), any bid made by a contractor was to be accompanied by a bid bond as a proposal guarantee. In the case of a joint venture bid, all contractors were required to sign a bid bond. In the instant case, only one contractor of the intervenors' joint venture, M. Peterson Construction Company, submitted a bid bond with the bid. According to DOT rules, if a bid bond failed to meet the requirements, the bid bond was to be declared invalid and the respective bid proposal was not to be considered. Nevertheless, the intervenors' bid was opened and considered with the other contractors' bids.

The intervenors' bid of $397,210.00 was the lowest bid received. Dickinson's bid of $455,991.50 was second lowest. The city council met and accepted the intervenors' bid subject to approval by the DOT, which was supplying 95 percent of the funding for the project. At the same meeting, the city also received an additional bid bond to cure the defect in intervenors' original bid.

The Iowa Attorney General's office, on behalf of the DOT, informed the city that the intervenors' bid did not conform to the bid proposal requirements; therefore, the contract could not be awarded to the intervenors. The Attorney General's office further informed the city:

We find your bid document forms acceptable and could concur in the award of the contract to Dickinson Co., Inc., as the lowest responsib[l]e bidder. Documents submitted on behalf of Dickinson Co. are in compliance with the bidding procedure. You should also be aware that were the City of Des Moines to relet the project by rejecting all bids, our participation would be limited to $455,991.56; the amount of the lowest acceptable bid.

The city thus had a choice of accepting Dickinson's next lowest bid or rejecting all bids and opening up the project for bidding again. The city chose to reject all bids and readvertise. In the rebidding, Dickinson's bid was $451,991.50 and intervenors' bid was $394,210. Intervenors' bid was lowest; the contract was awarded to them.

Dickinson filed this action in district court asking for a writ of certiorari to the city council to require them to award the contract to Dickinson. The petition also contained a request for a declaratory judgment awarding the contract to Dickinson and a claim for damages on theories of deprivation of civil rights and tort.

The case was submitted on stipulated facts. The court concluded that it did not have subject matter jurisdiction to proceed in granting certiorari relief on any of Dickinson's claims arising from the city's acceptance of intervenors' bid subject to DOT approval. The court viewed the city's acceptance as full and complete as of July 27 1981, and thus, any alleged illegality was complete then. Dickinson did not file its petition until September 15, 1981. According to Rule 319, Iowa Rules of Civil Procedure: "No writ of certiorari shall issue or be sustained unless the petition is filed within thirty days from the time the inferior tribunal, board or officer exceeded its jurisdiction or otherwise acted illegally." Iowa R.Civ.P. 319 (1983). Thus, because Dickinson's petition was not filed within thirty days of the city's conditional acceptance of intervenors' bid, the court found the petition untimely as to the city's acceptance of intervenors' bid.

The court evidently found it had jurisdiction to consider Dickinson's claims directed to the city's rejection of all bids and readvertising the project. As to these issues, the court held that, by Iowa case law and by Iowa Code section 384.100, the city was entitled to reject all bids. The court further held that no private cause of action exists in favor of a private bidder, as no absolute right to a public improvement contract exists, and that Dickinson's participation in the rebidding of the contract estopped it from now claiming its invalidity.

Dickinson raises many arguments on appeal: that its application for certiorari was timely; that the trial court had jurisdiction of the case as an ordinary law action; that the judgment was not supported by substantial evidence; that the city's actions were unreasonable, arbitrary and capricious and therefore illegal; that Dickinson had a common law cause of action to assert its right to the contract; that it has a claim for damages because its right to the contract was denied; that it also has a claim for damages for deprivation of due process rights; and that the district court improperly based its decision in part on an equitable doctrine, not applicable in this action at law.

Regarding the jurisdictional argument, we find that plaintiff's cause of action did not arise until the city finally chose its course of action. Its initial acceptance of intervenors' low bid was conditioned upon its being legally sufficient. When advised that it was not, the city then chose to readvertise for bids. That decision on August 17, 1981, commenced the time period for any certiorari action. Plaintiff's petition filed on September 15, 1981, came within the thirty-day period to satisfy the jurisdictional requirements. The supreme court has stated:

Certiorari is appropriate where an inferior board, exercising judicial functions, acts illegally. Iowa R.Civ.P. 306. An illegality is established if a board has not acted in accordance with the statute. The burden to prove such an illegality rests with the plaintiff.

Istari Construction, Inc. v. City of Muscatine, 330 N.W.2d 798, 799 (Iowa 1983).

Certiorari is an action at law; therefore, "our review ordinarily is not de novo and we do not review fact findings of the lower tribunal further than to ascertain if they are sustained by competent and substantial evidence." State v. Cullison, 227 N.W.2d 121, 126 (Iowa 1975). Where there is no factual dispute, we review trial court's conclusions as a matter of law; in reviewing law issues, we are not bound by trial court's ruling. See id. An exception to this review occurs when issues of violation of basic constitutional safeguards are raised. Such issues require us to make our own evaluation of the totality of the circumstances under which the ruling on those constitutional rights was made. See id.

In the instant case, the district court did not make a conclusion regarding either the illegality of the city's action in opening and considering intervenors' bid or Dickinson's claims of violation of his due process rights....

To continue reading

Request your trial
10 cases
  • SEA AIR SHUTTLE v. Virgin Islands Port Authority
    • United States
    • U.S. District Court — Virgin Islands
    • 13 Marzo 1992
    ...Asphalt And Concrete, Inc. v. Dept. of Transportation, 475 So.2d 1284 (Fla.Dist. Ct.App.1985); Dickinson Company, Inc. v. City of Des Moines, Iowa, 347 N.W.2d 436 (Iowa Ct.App.1984); Inman's Inc. v. City of Greenfield, 412 N.E.2d 126 (Ind.Ct.App. 1980). These cases provide further support f......
  • Elview Const. Co., Inc. v. North Scott Community School Dist.
    • United States
    • Iowa Supreme Court
    • 21 Agosto 1985
    ...accord with this general rule. Mortland v. Poweshiek County, 156 Iowa 720, 723, 137 N.W. 1009, 1010 (1912); Dickinson v. City of Des Moines, 347 N.W.2d 436, 440-41 (Iowa Ct.App.1984). Further, as this court, in Istari Construction, Inc. v. City of Muscatine, 330 N.W.2d 798, 800 (Iowa 1983),......
  • Bogue v. Ames Civil Service Com'n, 84-1205
    • United States
    • Iowa Supreme Court
    • 22 Mayo 1985
    ...N.W.2d 798, 799 (Iowa 1983); Norland v. Worth County Compensation Board, 323 N.W.2d 251, 253 (Iowa 1982); Dickinson Co. v. City of Des Moines, 347 N.W.2d 436, 439 (Iowa Ct.App.1984); Iowa R.Civ.P. 306. Bogue and Schendel alleged in their certiorari petition that the commission contravened s......
  • State v. Malloy
    • United States
    • Iowa Court of Appeals
    • 28 Mayo 1987
    ...of the totality of the circumstances under which the ruling on those constitutional rights was made. Dickinson Co., Inc. v. City of Des Moines, 347 N.W.2d 436, 439 (Iowa App.1984). The fourth amendment to the Constitution of the United States provides that no warrants shall be issued absent......
  • Request a trial to view additional results
1 books & journal articles
  • Creative Collateral Claims Against Public Entities and Their Agents
    • United States
    • ABA General Library The Construction Lawyer No. 40-1, January 2020
    • 1 Enero 2020
    ...67. All-Star Constr. & Excavating, Inc. v. Bd. of Pub. Works, 640 N.E.2d 369, 371 (Ind. 1994). 68. Dickinson Co. v. City of Des Moines, 347 N.W.2d 436, 441 (Iowa Ct. App. 1984). 69. Interior Contractors, Inc. v. Bd. of Trustees of Newman Mem’l Cty. Hosp . , 185 F. Supp. 2d 1216, 1229 (D. Ka......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT