Doane Coll. v. Lanham

Decision Date16 May 1889
Citation42 N.W. 405,26 Neb. 421
PartiesDOANE COLLEGE v. LANHAM.
CourtNebraska Supreme Court

OPINION TEXT STARTS HERE

Syllabus by the Court.

1. J. L. contracted with Doane College to furnish the material and mechanical skill for doing the brick-work of one of the halls or buildings of said college, and agreed to complete the said brick-work, except topping the chimneys, on or before July 1st next thereafter, and to forfeit to said college of his compensation for such material and mechanical skill $100 for each week which he should overrun his time in the completion of said work. The work not having been done in time, and certain differences and disagreements having arisen between J. L. and the building committee of Doane College, including the amount of forfeiture under said agreement, and the parties having agreed to submit to arbitration “some points and items of difference existing between said parties as to work to be done, material to be furnished, damage for alleged delay,” etc., before entering upon the arbitration the following memorandum was entered upon the agreement to submit, as expressing the points and differences submitted: “Mem. The matters are stone for, freight upon, and setting stone steps, and damages for delay in completing contract beyond July 15.” The arbitrators made the following award: (1) Lanham to be relieved of the steps entirely, the college to do that work at their own expense. (2) No change to be made in estimate already made in brick-work done in basement around windows. (3) Lanham to pay Doane College the actual loss at rate of $1.87 1/2 per room per week for each of the thirty rooms mentioned in Mr. Doane's statement, counting from beginning to end of fall term, rent on all rooms not occupied. Total amount, $675. (4) Lanham to pay Doane College twelve weeks' service of T. W. Maloon, at $35.50,--$426. Loss, freezing cistern water, etc., $100. Total, $1,201. Deduct from penalty five days, at rate $100 per week,--$81.66. Total amount to be taken from contract price, $1,119.34.” An action being afterwards brought by J. L. against Doane College for mechanical skill, work, labor, and material furnished by him under the said contract for the erection of the said building, and for additional mechanical skill, work, and labor rendered necessary in the erection thereof by reason of changes in the height and plan of said building, and Doane College having answered in said action, setting up the submission of said points and matters of difference between the said parties to arbitration; the award of said arbitrators thereupon, which found that there was due to the said Doane College the sum of $1,119.34; that thereupon the said Doane College did tender to said J. L., “the balance his due, of which the said J. L. took all, except the sum of $120.21, and which the said Doane College now owes the said J. L., which they have often tendered him, * * * and amount he refuses to accept, and the said college now presents said amount of money in court,” etc.: held, that the said award be sustained as a counter-claim or set-off in favor of Doane College, and against the claim of J. L., to the extent and amount of $593.34, and no more.

2. The contract being for putting up the masonry of Ladies' Hall, and to furnish all the brick, sand, lime, cement, and water, and all the labor, necessary and of such quality as to put up the building in good workman-like manner in the shortest time possible consistent with good work, etc., with all the ordinary specifications as to the manner of doing the work, and providing the manner of measuring the same, and providing for paying for the same when completed and accepted at the rate of $10 per 1,000 of brick, where the walls have one side of repressed brick, which is to include chimneys, and $12 per 1,000 where the walls have two sides of repressed brick; also for paying, in addition to the price named, 75 cents per 1,000 of bricks for all brick masonry laid in mortar made in part with hydraulic cement, etc.,--there being no plan or drawing of said building showing the height thereof exhibited to the contractor or present at the time or previous to the entering into said contract, nor any specification or clause in said contract stating or indicating the height of which said building was to be, or the number of stories which it was to contain; and there being evidence on the trial tending to prove that the contractor, without inexcusable negligence on his part, entered into the said contract in the honest belief and expectation that the brick walls of said building were to be, and that he would be required to build them, only two stories high; and there being also evidence tending to prove that the mechanical skill and labor necessary to build and erect the brick-work of the third story of the three-story walls and building, which the contractor was required by the building committee of the defendant under the said contract and did actually build for the defendant, was actually worth at the rate of $3 per 1,000 brick for 189,401 brick more and in excess of the average of that required to build and erect the same building of two stories in height only; there also being evidence tending to prove that said contract was entered into by both of the parties in view of the said building being erected upon a foundation and foundation walls then being constructed under another and separate contract by the said J. L., without change in the shape or character of the walls thereof, but that before the erection of the brick-work of said building the plan and character of said foundation was changed from plain corners to buttressed corners; that said contractor was required and did build the walls and brick-work of said building to conform to said foundation, so changed, at an additional cost of skill, mechanical work, and labor to the contractor of the sum of $30; and there being evidence tending to prove the laying and placing in the walls of said building by the contractor of a number of thousands of brick, and a quality and kind of workmanship which, under the terms of the said contract, would amount to a sum which, added to the amount of compensation for the extra work as above set out and stated, and after deducting all moneys paid to the contractor under said contract, and the amount of defendant's counter-claim or set-off allowed as above stated, would still leave an amount due to the contractor above the amount of the verdict,--the verdict is sustained, and judgment affirmed.

Error from district court, Saline county; BROADY, Judge.Dawes & Foss, for plaintiff in error.

Abbott & Abbott, for defendant in error.

COBB, J.

This action was commenced in the district court of Saline county by John Lanham against Doane College. The plaintiff in his petition alleges that Doane College is a corporation under the laws of this state. That on or about April 10, 1884, he contracted with the college, through Thomas Doane, its legally authorized agent, to furnish the material and labor and to build and complete for Doane College the brick-work for a college building then being built for defendant on its grounds at Crete, Neb., and known as “Ladies' Hall.” That it was then and there agreed between the parties that the price of said labor and material should be, for brick laid in the wall, with mortar mixed partly with cement, and with both sides of wall faced with repressed brick, $12.75 per 1,000 brick. That chimneys should be computed as solid, and each cubic foot of such masonry, including door and window openings, should be computed to contain 224 1/2 bricks. That it was then and there verbally agreed by and between said parties that said work should be built on a foundation, the dimensions of which were then determined, and should be two stories high, with plain outer walls, similar to those of the college building then standing on said grounds, and should contain, as nearly as could then be estimated, a total of 275,000 brick. That subsequently, and after said work was commenced, the plan was so changed by defendant as to make the main part of said building three stories high, instead of two, as originally agreed upon, with outer walls buttressed instead of plain. That the plaintiff, without any agreed price therefor, did, at the request of defendant, proceed to furnish the labor and material, and build and complete the third story and the outer walls with buttresses instead of plain, according to said change of plan. That said third story contains the amount of 195,000 brick; that the first and second stories contain the total amount of 275,000 brick,--all of which is laid in mortar mixed with cement, according to contract. That of said 275,000 brick two-thirds are faced on both sides with repressed brick, and the plaintiff, according to said contract, is entitled, for building the same, to the sum of $12.75 per M. That the remainder or one-third part thereof were faced on one side with repressed brick, and the price of laying the same, according to the contract, is $10.75 per M. The plaintiff alleges that the extra expense of laying the third story over those of the first and second amounts to $3 per M., and that to furnish material and labor, and to build the third story of said building, was worth $15.75 per M. of brick for walls faced on both sides with repressed brick, and $13.75 per M. for walls with one face of repressed brick laid in mortar mixed with cement, as stated; and that of the 195,000 brick laid in the third story of said building 75,000 were faced with repressed brick on both sides, and 120,000 were so faced on one side; that all are laid with mortar properly mixed with cement; that the labor necessarily employed on the outer walls, buttressed instead of plain, is worth the sum of $15; and that the labor and material expended in the erection of the third story and the change in the outer walls amounts to $2,846.25. The plaintiff alleges that the total labor and...

To continue reading

Request your trial
4 cases
  • Wilkinson v. Pritchard
    • United States
    • Iowa Supreme Court
    • December 18, 1909
    ...14 N. H. 49;Graham v. Graham, 9 Pa. 254, 49 Am. Dec. 557;Nashua, etc., Ry. v. Boston, etc., Ry. 157 Mass. 268, 31 N. E. 1060;Doane College v. Lanham, 26 Neb. 421, 42 N. E. 405. See cases collected in 3 Cyc. 608. But the time within which the award must be filed is not one of the matters whi......
  • Wilkinson v. Prichard
    • United States
    • Iowa Supreme Court
    • December 18, 1909
    ... ... Dec ... 557); Nashua, etc., Ry. v. Boston, etc., Ry., 157 ... Mass. 268 (31 N.E. 1060); Doane College v. Lanham, ... 26 Neb. 421 (42 N. E. [145 Iowa 70] 405. See cases collected ... in 3 Cyc ... ...
  • Elliott v. Atkins
    • United States
    • Nebraska Supreme Court
    • May 16, 1889
  • Doane College v. Lanham
    • United States
    • Nebraska Supreme Court
    • May 16, 1889
    ...42 N.W. 405 26 Neb. 421 DOANE COLLEGE, PLAINTIFF IN ERROR, v. JOHN LANHAM, DEFENDANT IN ERROR Supreme Court of NebraskaMay 16, ERROR to the district court for Saline county. Tried below before BROADY, J. AFFIRMED. Total amount $ 675 00 Fourth, Lanham to pay Doane College twelve weeks' servi......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT