Domino Group, Inc. v. Charlie Parker Memorial Foundation

Decision Date05 February 1993
Docket NumberNo. 91-3588,91-3588
Citation985 F.2d 417
PartiesDOMINO GROUP, INC., Plaintiff-Appellant, v. CHARLIE PARKER MEMORIAL FOUNDATION, Defendant-Appellee.
CourtU.S. Court of Appeals — Eighth Circuit

Wiliam C. Nulton, Kansas City, MO, argued (Thomas A. Sheehan, on the brief), for plaintiff-appellant.

Michael E. Dailey, North Kansas City, MO, argued, for defendant-appellee.

Before McMILLIAN, Circuit Judge, BRIGHT, Senior Circuit Judge, and LOKEN, Circuit Judge.

LOKEN, Circuit Judge.

Domino Group, Inc. ("Domino"), appeals a district court order vacating a confirmed arbitration award, denying Domino alternative damage relief, and setting the case for trial. Although we otherwise agree with the district court's analysis, we conclude that it erred in vacating its prior confirmation of the award. Accordingly, we modify the district court's order and remand the case for further proceedings.

I.

The Charlie Parker Memorial Foundation ("Foundation") owns the International Jazz Hall of Fame. On April 24, 1985, the Foundation entered into a written Production Contract with Domino relating to "International Jazz Hall of Fame induction ceremonies." Paragraph 3 of the contract provided that Domino "Agrees to produce the ceremonies, specifically on the evening of August 21, 1985." Article J of the contract's preamble provided that, "Acceptance of this contract gives [Domino] the sole option to produce the next ten (10) ceremonies."

Domino produced the 1985 awards ceremony, which was a money-losing failure. When the Foundation refused to allow Domino (or any other producer) to produce additional ceremonies, Domino filed a claim for arbitration under the arbitration clause in the contract, asking that it "be allowed to exercise [its] rights to produce the ceremonies under said contract, or to be compensated therefor." On August 15, 1986, following a hearing, the arbitrator issued a final award granting Domino's request for specific performance of the "on-going continuing and subsisting contract." The arbitrator denied Domino's alternative request for "substantial monetary damages" as moot.

The Foundation did not timely move to vacate, modify, or correct the arbitrator's award. See § 12 of the Federal Arbitration Act, 9 U.S.C. § 12. On August 11, 1987, Domino commenced this action by moving to confirm the award under § 9 of the Act. The district court initially denied Domino's motion for summary judgment because it was unable "to determine what it is the award directs the parties to do." Then, on May 15, 1989, the court granted Domino's motion to remand to the arbitrator for clarification of the award. The court explained:

The arbitrator is instructed to clarify what is meant by "Claimant's request ... for injunctive relief and specific performance is granted." Namely, the arbitrator should delineate all actions which the parties are to perform "specifically," including all duties found to be arising from the contract at issue. The object and extent of injunctive relief should be similarly identified.

On April 5, 1990, Domino sent a letter to the arbitrator constituting "claimant's position on clarification of the Award." Domino attached an exhibit enumerating "Producer's Rights" under the contract and urged the arbitrator to "specifically direct the Foundation to permit Domino Group to exercise these enumerated rights." Domino also argued that "[t]he Foundation's actions make necessary a consideration of alternative relief," and urged the arbitrator to award $450,000 damages "as alternative relief." Domino justified its request for damages by submitting six pages of transcript from the original arbitration hearing that recorded a discussion between Domino's counsel and the arbitrator concerning the appropriateness of a $450,000 damage award.

On June 6, 1990, without holding a further hearing, the arbitrator issued a Clarification of Award. In a cryptic, nearly unintelligible decision, the arbitrator adopted the list of specific Producer's Rights submitted by Domino, commenting that "[c]ooperation should and ought remove any doubt as to just how to undertake performance" of the contract. The arbitrator further agreed that Domino's suggested $450,000 damage award "does provide a good basis of alternative relief." The decision concluded, "All that need be added is that these suggested and proposed courses for relief are adopted as the resolution of this arbitration."

On September 28, 1990, the district court granted Domino's uncontested motion to confirm the clarified award. The court's order directed entry of judgment in favor of Domino for specific performance, incorporating the list of Producer's Rights adopted in the Clarification of Award. The order further stated that, if the Foundation refused to permit Domino to exercise these rights, "plaintiff may seek damages."

On July 8, 1991, Domino moved the court to enter judgment for $450,000 damages "in addition to the award for specific performance." Domino submitted a short affidavit by Domino's president stating that the Foundation had continued to refuse to permit Domino to perform under the contract. In response, the district court ruled that the award of damages in the Clarification of Award was "in manifest disregard of the law and evidential record in these proceedings." The court concluded that a further remand to the arbitrator would be futile. It therefore vacated the arbitrator's award and clarification and ordered that the case be "returned to the docket of this court for trial."

This appeal followed. We have jurisdiction to review a district court order vacating an award. 9 U.S.C. § 16(a)(1)(E). On appeal, Domino argues that the district court erred in vacating the arbitrator's award and that Domino is entitled to a judgment for $450,000 damages based upon the arbitrator's Clarification of Award. The Foundation argues that the district court properly vacated the arbitrator's awards but erred in setting the case for trial. The Foundation argues that the case be referred to a new arbitration panel for "full arbitration proceedings."

II.

We have recited the procedural history of this case in detail because in our view it is critical to a proper resolution of the issues raised on appeal. The answer to most of these issues becomes readily apparent when put in the context of the limited nature of judicial review of arbitration awards under the Federal Arbitration Act:

First, the Foundation's failure to file a motion to vacate, modify, or correct within three months of either the initial award or the Clarification of Award waived any defenses to confirmation that might be asserted in a timely motion to vacate. See, e.g., Local Union No. 36, Sheet Metal Workers' Int'l Assn. v. Atlas Air Conditioning Co., 926 F.2d 770, 772 (8th Cir.1991); Sanders-Midwest, Inc. v. Midwest Pipe Fabricators, Inc., 857 F.2d 1235, 1237-38 (8th Cir.1988); Piccolo v. Dain, Kalman & Quail, Inc., 641 F.2d 598, 600 (8th Cir.1981). Absent a timely motion to vacate, in most cases "the confirmation of an arbitration award is a summary proceeding that makes what is already a final arbitration award a judgment of the court." Florasynth, Inc. v. Pickholz, 750 F.2d 171, 176 (2d Cir.1984).

Second, when Domino filed its timely motion to confirm the arbitrator's initial award of specific performance, the district court properly remanded the case to the arbitrator for clarification of that award. "An ambiguous award should be remanded to the arbitrators so that the court will know exactly what it is being asked to enforce." Americas Ins. Co. v. Seagull Compania Naviera, 774 F.2d 64, 67 (2d Cir.1985). Domino sought to convert the arbitrator's award of specific performance into a court judgment, that is, an equitable decree in the nature of mandatory injunctive relief. Rule 65(d) of the Federal Rules of Civil Procedure provides that, "Every order granting an injunction ... shall be specific in terms [and] shall describe in reasonable detail, and not by reference to the complaint or other document, the act or acts sought to be restrained." We agree with the district court that a judgment simply confirming the arbitrator's initial ambiguous award would have been inconsistent with the court's duty to fashion a specific equitable decree that fairly apprised the Foundation of its...

To continue reading

Request your trial
43 cases
  • Van Horn v. Van Horn
    • United States
    • U.S. District Court — Northern District of Iowa
    • October 19, 2005
    ...UHC Mgmt. Co. v. Computer Scis. Corp., 148 F.3d 992, 997 (8th Cir.1998) (making this observation); Domino Group, Inc. v. Charlie Parker Mem'l Found., 985 F.2d 417, 420 (8th Cir.1993) (quoting 9 U.S.C. § 9); accord. P & P Indus., Inc. v. Sutter Corp., 179 F.3d 861, 870 (10th Cir.1999) (notin......
  • LOCAL 36 SHEET MET. WORKERS ASS'N v. KIRKWOOD, INC.
    • United States
    • U.S. District Court — Eastern District of Missouri
    • January 16, 1996
    ...possibly waived any defenses that they may have had to confirmation of the arbitration award. See, Domino Group v. Charlie Parker Mem. Foundation, 985 F.2d 417, 419-20 (8th Cir.1993); Local Union No. 36 v. Atlas Air Conditioning Co., 926 F.2d 770, 772 (8th Cir.1991) aff'g Local Union No. 36......
  • Glass, Molders, Pottery, Plastics and Allied Workers Intern. Union, AFL-CIO, CLC, Local 182B v. Excelsior Foundry Co.
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • June 13, 1995
    ...award he may not revise it. Anderson v. Norfolk & Western Ry., 773 F.2d 880, 883 (7th Cir.1985); Domino Group, Inc. v. Charlie Parker Memorial Foundation, 985 F.2d 417, 420-21 (8th Cir.1993); Colonial Penn Ins. Co. v. Omaha Indemnity Co., 943 F.2d 327, 331-32 (3d Cir.1991); 3 Ian R. Macneil......
  • International Union of Operating Engineers, Local 150, AFL-CIO v. Rabine
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • November 3, 1998
    ...Local Union No. 150 v. Air Systems Eng'g, Inc., 948 F.2d 1089, 1091-92 (9th Cir.1990); see also Domino Group, Inc. v. Charlie Parker Mem'l Found., 985 F.2d 417, 420 n. 1 (8th Cir.1993), and we have done the same in the analogous area of benefit plans governed by the Employee Retirement Inco......
  • Request a trial to view additional results
1 books & journal articles
  • Fortress arbitration: an exposition of functus officio.
    • United States
    • Florida Bar Journal Vol. 80 No. 2, February 2006
    • February 1, 2006
    ...(29) See Green, 200 F.3d at 977; Cadillac Uniform, 920 F. Supp. at 22. (30) Domino Group, Inc. v. Charlie Parker Memorial Foundation, 985 F.2d 417, 420 (8th Cir. (31) Matlack, 118 F.3d at 992. (32) Hyle v. Doctor's Associates, Inc., 198 F.3d 368, 370 (2d Cir. 1999); Cadillac Uniform, 920 F.......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT