Dunaway v. Roden
Decision Date | 01 February 1916 |
Docket Number | 8 Div. 290 |
Citation | 71 So. 70,14 Ala.App. 501 |
Parties | DUNAWAY v. RODEN. |
Court | Alabama Court of Appeals |
Appeal from Circuit Court, Morgan County; D.W. Speake, Judge.
Action by J.H. Roden against A.M. Dunaway. From a judgment for plaintiff, defendant appeals. Affirmed.
The facts sufficiently appear from the opinion.
The following charges were refused to defendant:
O Kyle, of Decatur, for appellant.
Tidwell & Sample, of New Decatur, for appellee.
Action by appellee, as plaintiff below, against appellant, as defendant below, for compensation for boring a well.
The complaint, to which no demurrer was filed, contained four counts, but the second was eliminated by the giving of the affirmative charge for defendant. The refusal of the court to give such charge for defendant as to each of the other counts is the principal error relied on for a reversal.
The first and third counts sought a recovery under a special contract for boring said well, the only difference between the two being that the latter more fully set out the contract; while the fourth count sought a recovery under the common count for work and labor done at plaintiff's request in boring said well, etc. Defendant pleaded the general issue with leave to give in evidence any matter that might be specially pleaded. The contract relied on by plaintiff for recovery was a parol one. He testified:
The defendant insists that under this evidence he was entitled to the affirmative charge as to count 3 of the complaint on account of an alleged variance between allegation and proof, because the count in describing the special contract sued on, which was the new or modified contract, alleged that under it defendant not only was to pay plaintiff 50 cents per foot for dirt and $1 per foot for rock bored through in sinking the well, but was also to pay for the casing of the well and for the cost of removing plaintiff's machinery to the place of boring, while the testimony as set out, it is insisted, afforded no evidence whatever that defendant was to pay for the latter two items.
We cannot so agree. The facts and circumstances are such that the jury might infer that it was the implied intention of the parties that under the new contract--the contract as modified--the defendant was still to pay for the casing of the well and for the removal of the machinery, though nothing was in fact said about either of these things at the time of the modification.
The testimony of the defendant as to the original contract between the parties and as to the facts and circumstances under which it was modified coincides with that of plaintiff. Both agree that under the new or modified contract plaintiff was to get for boring the well, not a mule, as first agreed, but 50 cents per foot for dirt and $1 per foot for rock bored through in sinking the well; and both agree that at the time of this new agreement nothing was said about defendant's paying for the casing of the well and the removal of plaintiff's machinery, as had been formerly agreed to--that is, under the contract as originally made. What is to be inferred from their silence as to these matters? May it not be reasonably implied from their failure to make any change in these stipulations of the old contract, which they were merely modifying, that they intended them to remain as there agreed? In other words, was it not the implied understanding that the old contract was to stand except as to particulars where a change was expressly agreed on?
As to whether it was or not was a question for the jury, and the court did not err in refusing the affirmative charge as to count 3 on any theory of a variance. Nor did the court err in refusing written charge numbered 7 requested by defendant, and which asserted that:
If the jury believed that "plaintiff and defendant first made a contract for plaintiff to bore the well for a mule, and that afterwards a new contract was made for boring the well in lieu of the old contract, and if thereby the old contract was abandoned, then plaintiff could not recover anything either for moving his machinery or for casing the well, provided you find that plaintiff did not comply with the new contract."
The charge, we think, was not only calculated to mislead the jury for reasons just adverted to, but was positively confusing by reason of the concluding paragraph in it, as above italicized. On this account, the charge, as applied to the evidence, is susceptible of the construction that it meant to assert that, although the jury might believe that under the original contract the defendant was to pay for moving plaintiff's machinery and for casing the well, yet, if they further believed that that contract was abandoned and a new contract entered into in lieu of it, which did not require the defendant to pay for moving plaintiff's machinery and casing the well, the plaintiff could not recover anything for either of these things; "provided the jury believed that plaintiff did not comply with the new contract." Upon the hypothesis stated in the charge, the plaintiff was not entitled to recover anything for moving his machinery and casing the well, even though he had complied with the new contract; and yet the charge, by the concluding proviso mentioned, implies that he would, provided he complied with the new contract. The lower court cannot be put in error for refusing a charge which incorrectly states the law, or which is confusing, although its only fault in this particular lies in the fact that it is too favorable to the opposite party. 6 Mayf.Dig. 11, par. 17.
Parties are at liberty to alter or change an executory contract at their pleasure and in any particular they see fit upon no other consideration than mutual assent. 2 Mayf.Dig. 797, § 48.
That the original contract--the terms of which were undisputed--was altered or changed, both parties agree. The extent...
To continue reading
Request your trial-
Milner v. Earl Fruit Co. of Northwest
... ... (C. S., sec ... 6687, subd. 2; Bates v. Capital State Bank, 21 Idaho ... 141, 121 P. 561; 13 C. J., sec. 835, p. 731; Dunaway v ... Roden, 14 Ala. App. 501, 71 So. 70; Koons v. St ... Louis Car Co., 203 Mo. 227, 101 S.W. 49; Ostrander ... v. Messmer, (Mo. App.), ... ...
-
Little v. Redditt
...v. Vaughn, 198 Ala. 283, 73 So. 507; Wellden v. Witt, 145 Ala. 605, 40 So. 126; Mylin v. King, 139 Ala. 319, 35 So. 998; Dunaway v. Roden, 14 Ala.App. 501, 71 So. 70. Respondent takes the further position that an actual consideration for the option referred to in argument as 'the amendment ......
-
Clarke-Washington Elec. Membership Corp. v. Alabama Power Co.
...249 Ala. 170, 30 So.2d 261; Sibley v. Barclay, 14 Ala.App. 422, 70 So. 201, certiorari denied 195 Ala. 694, 70 So. 1012; Dunaway v. Roden, 14 Ala.App. 501, 71 So. 70, certiorari denied 196 Ala. 701, 72 So. 1019. It seems clear to us that the appellant must rely on the 1953 contract and not ......
-
Shelby County v. Baker
...182; Grissom v. Dahart Ice Cream Co., Inc., 34 Ala.App. 282, 40 So.2d 333, certiorari denied 252 Ala. 235, 40 So.2d 339; Dunaway v. Roden, 14 Ala.App. 501, 71 So. 70; Alabama City G. & A. Ry. Co. v. Ventress, 171 Ala. 285, 54 So. 652. The statement made by the witness 'I said on the average......