Ehard v. Pistakee Builders, Inc., Gen. No. 68--165

Decision Date28 July 1969
Docket NumberGen. No. 68--165
Citation111 Ill.App.2d 227,250 N.E.2d 1
PartiesHenry J. EHARD and Jean Ehard, his wife, Plaintiffs-Appellees, v. PISTAKEE BUILDERS, INC., a Delaware Corporation, Defendant-Appellant.
CourtUnited States Appellate Court of Illinois

Franz & Franz, Perry L. Weed, Crystal Lake, for defendant-appellant.

Stephen R. Yost, Henley & Yost, Cary, for plaintiffs-appellees.

ABRAHAMSON, Justice.

On March 6, 1967, the plaintiffs brought suit against the defendant in the Circuit Court of McHenry County for an alleged breach of a written contract executed by them on May 10, 1965. Paragraph one of the complaint alleged that by the terms of the contract the defendant agreed to 'furnish' a subdivided lot and 'all the materials and perform all the labor necessary for the complete construction of a Park Regent Model Home * * * in a substantial and workmanslike manner * * *.' The complaint further alleged that the defendant, in disregard of the contract, furnished 'defective and unsuitable work, labor and materials * * *' in various particulars and asked judgment in the amount of $4500.00. The defendant's answer admitted the allegations of paragraph one of the complaint, denied the allegations that the work was improperly performed and, as an affirmative defense, raised a document signed by the plaintiffs on August 28, 1965 wherein it is stated that the plaintiffs had inspected the premises and 'find it fully completed in a first class workmanshiplike manner.'

The written contract does not contain the express provision that the construction would be done in 'a substantial and workmanlike manner' as alleged in the complaint but does state that it included '* * * all labor, material and services of every kind necessary for the proper performance of the work in accordance with the plans and specifications * * *'. The contract also provided that the construction would be completed by August 15, 1965, and that the plaintiffs would not be entitled to possession of the home until they indicated 'acceptance of the work by the execution of an appropriate receipt' and complete payment.

The matter proceeded to trial, with a jury waived. Henry J. Ehard testified that construction commenced in June, 1965, and that he visited the site weekly thereafter. The original plans specified that the heating would be forced warm air '* * * of sufficient capacity to heat (the) home' but the parties subsequently agreed to use a hot water system in place of hot air. In late August, Ehard went to the home with a salesman employed by the defendant and advised him that it was necessary that he obtain possession immediately although construction was not completed. Although, Ehard wanted to hold back $1500.00 from the purchase price to insure completion, it was agreed that he would release all of the funds and that the defendant would complete the construction and repair any defects. Accordingly, on August 28, Ehard signed a direction to his mortgage lender to disburse the balance of the loan proceeds to the defendant. That direction was in a form apparently prepared by the defendant and included the following:

'This is to certify that we have inspected the above-captioned building and find it fully completed in a first class workmanship-like manner, everything is in perfect working order and all work and materials are acceptable.

We herewith accept the above building and authorize you to make complete disbursement to the builder from our loan proceeds.

'We understand labor and materials are guaranteed only for a period of one year (1 year) from this date; * * *'

Ehard testified that he signed the direction with the verbal agreement with the defendant that all defects would be repaired. David Ladd, the secretary of Pistakee Builders testified that although he was not personally present at the conversation on August 28 such an arrangement was not unusual.

In November, 1965, Ehard first discovered that he could not adequately heat the house, that some rooms were too cold and others too hot and he complained to the defendant. Since the heating subcontractor who had installed the system was out of business, the defendant directed James Althoff, a heating sub- contractor, to inspect the system and make all necessary corrections. Althoff found that the boiler was of insufficient size and on December 5, 1965, installed a new, larger boiler, additional radiators and three zone valves. Ehard was still dissatisfied and in a conversation with Althoff lost his temper and threw a pencil and pad at a wall. Althoff returned in the spring of 1966 and added more radiation pipes along the baseboard to transmit the hot water throughout the home. Ehard and his wife testified that despite these additions the hearing was still defective, some rooms were much colder than others, and a cold area existed in the center of the recreation room. Both Ladd and Althoff returned to the home but advised Ehard that nothing further could be done to balance the heat distribution until the following winter.

In October, 1966, Ehard employed C. E. Ellison to inspect the heating system and make the necessary corrections to adequately heat the home. Ellison made a chart of the home, computed the necessary BTUs to heat each room and installed an additional 55 feet of baseboard radiation pipe, an increase of almost 50% Of the pipe previously installed. Ehard paid Ellison's bill in the amount of $674.48 and testified that the home was properly heated thereafter.

The presiding magistrate at the trial prepared and filed a memorandum opinion on May 21, 1968, that found that the plaintiffs had not waived their rights to have any defects repaired by their direction of August 28, 1965; that the heating system as installed by the defendant was in fact defective; that the defendant had the obligation to repair the defects and failed to do so; and that as a result the plaintiffs were damaged in the amount of $693.11, being the bill paid to Ellison and an additional $18.63 for some other expenditures by them. The memorandum also added that the action was one brought...

To continue reading

Request your trial
8 cases
  • Jackson v. Mount Pisgah Missionary Baptist Church Deacon Bd.
    • United States
    • United States Appellate Court of Illinois
    • June 30, 2016
    ...See Barrows v. Maco, Inc., 94 Ill.App.3d 959, 966, 50 Ill.Dec. 526, 419 N.E.2d 634 (1981) (quoting Ehard v. Pistakee Builders, Inc., 111 Ill.App.2d 227, 233, 250 N.E.2d 1 (1969) ) (noting that a party to a contract may not complain of the nonperformance of the other party where that perform......
  • Watson Lumber Co. v. Mouser, 74-50
    • United States
    • United States Appellate Court of Illinois
    • July 10, 1975
    ...Corp. v. Snyder, 113 Ill.App.2d 288, 297--298, 251 N.E.2d 641 Affd. 47 Ill.2d 349, 265 N.E.2d 670; Ehard v. Pistakee Builders, Inc., 111 Ill.App.2d 227, 234, 250 N.E.2d 1; Ross v. Danter Associates, Inc., 102 Ill.App.2d 354, 369, 242 N.E.2d The essential points of this contract were twofold......
  • Gamm Const. Co. v. Townsend
    • United States
    • United States Appellate Court of Illinois
    • October 17, 1975
    ... ... (Ehard v. Pistakee Builders, Inc., 111 Ill.App.2d 227, ... ...
  • Stephenson v. Frazier
    • United States
    • Indiana Appellate Court
    • January 29, 1980
    ... ... ) Ind.App., 367 N.E.2d 1120; Building Systems, Inc. v. Rochester Metal Products, Inc., (1976) ... Jones, (1967) 161 Colo. 505, 423 P.2d 321; Ehard v. Pistakee Builders, Inc., (1969) 111 Ill.App.2d ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT