Elec. Contractors, Inc. v. 50 Morgan Hospitality Grp., LLC
Decision Date | 12 April 2022 |
Docket Number | AC 44475 |
Citation | 211 Conn.App. 724,273 A.3d 726 |
Parties | ELECTRICAL CONTRACTORS, INC. v. 50 MORGAN HOSPITALITY GROUP, LLC, et al. |
Court | Connecticut Court of Appeals |
Paul R. Fitzgerald, Hartford, for the appellant (plaintiff).
Edward R. Scofield, Bridgeport, with whom, on the brief, were Heather Spaide and Joseph J. Cessario, Stamford, for the appellee (defendant Greython Construction, LLC).
Alvord, Cradle and Lavine, Js.
The plaintiff, Electrical Contractors, Inc., appeals from the summary judgment rendered by the trial court in favor of the defendant Greython Construction, LLC (Greython), regarding claims arising out of a contract between the plaintiff and Greython pursuant to which the plaintiff, as Greython's subcontractor, was to complete work on a property owned by the defendant 50 Morgan Hospitality Group, LLC (50 Morgan).1 On appeal, the plaintiff claims that the court erred in granting Greython's motion for summary judgment (1) based on language in the contract providing that payment by 50 Morgan to Greython was a "condition precedent" to Greython's obligation to make payments to the plaintiff, and (2) because Greython failed to present any evidence demonstrating the absence of a genuine issue of material fact either that it was not the cause of 50 Morgan's failure to make payment or that it had made a substantive effort to collect payment. We disagree with the plaintiff and, accordingly, affirm the judgment of the court.
The record reveals the following relevant undisputed facts and procedural history. Greython served as the general contractor for a project involving the renovation of a property owned by 50 Morgan. The plaintiff served as a subcontractor for Greython. On or about February 3, 2017, Greython entered into a contract with the plaintiff in which the plaintiff agreed to "furnish all labor, material, and equipment to perform all [electrical] work" for the project. The plaintiff provided Greython with requisitions seeking payment for materials furnished and services provided in connection with the project.
At the heart of this appeal is the meaning of the following language of the contract between the plaintiff and Greython. Article 2 of the contract provides that Greython will pay the plaintiff fixed sums of money in accordance with article 6 of the contract. Article 6 provides in relevant part: (Emphasis added.)
On January 31, 2018, the plaintiff commenced this action seeking payment for the costs of the materials it had furnished and the services it had provided in connection with the renovation project. On July 6, 2018, the plaintiff filed the amended complaint, which is the operative complaint. In the complaint, the plaintiff alleged that it performed its obligations under the subcontract by providing labor, materials, and equipment for the project. Greython, however, failed to pay the plaintiff for all amounts due for the work it had completed on the project. The plaintiff asserted that "the sum of $350,616.65, plus attorney's fees, accrued interest, and costs remains due and owing to [the plaintiff]."
The plaintiff alleged the following relevant counts against Greython:2 breach of contract for failing to pay the plaintiff the contract balance of $350,616.65 (count two); breach of the implied covenant of good faith and fair dealing for "failing to make payment of the sums due to [the plaintiff] that are not subject to a good faith dispute" and for "failing to provide notice or response to [the plaintiff] in good faith as to the specific, justifiable reasons for Greython's failure to make payment to [the plaintiff]" (count three); unjust enrichment (count four); and a violation of General Statutes § 42-158j for failure to pay the plaintiff any undisputed amount and refusing to place any disputed funds in escrow when it was put on notice of the plaintiff's claim (count six).3
On March 4, 2019, Greython filed an amended answer and special defenses to the operative complaint, in which it asserted two special defenses, both of which contended that the relevant language in article 6 made clear that Greython's obligation to pay the plaintiff was dependent upon Greython first receiving payment from 50 Morgan. On the same date, Greython filed a motion for summary judgment as to the second, third, fourth, and sixth counts of the operative complaint. Greython filed a memorandum of law in support of its motion, in which it argued that the language in article 6 of the contract was clear and unambiguous that it was not obligated to pay the plaintiff until it received payment from 50 Morgan. Because it had not yet received payment from 50 Morgan, Greython argued, "[it] ha[d] no duty to pay [the plaintiff] ...." On April 5, 2019, the plaintiff filed an objection to Greython's motion and an accompanying memorandum of law. The gist of the plaintiff's argument was that the payment provision in article 6 was ambiguous as to which party bore the risk of 50 Morgan's nonpayment. Thus, the plaintiff argued, this provision should be interpreted to mean that nonpayment by 50 Morgan "merely postpone[s] for a reasonable period of time" Greython's obligation to pay the plaintiff. On April 18, 2019, Greython filed a reply to the plaintiff's objection.
On April 24, 2019, the court heard oral argument on Greython's motion for summary judgment. On April 30, 2019, the court issued a memorandum of decision granting Greython's motion for summary judgment in its entirety as it pertained to the plaintiff. The court concluded that, pursuant to article 6 of the contract, Greython was not obligated to pay the plaintiff until 50 Morgan paid Greython. The court stated: "[The plaintiff] say[s] the court should read the language at issue [in article 6 of the contract] to mean that [Greython] will pay [the plaintiff] within a reasonable period of time even if the owner never pays [Greython]." The court noted that 4 But none of [their decisions] bind court to do likewise." (Footnote added.) On the contrary, the court stated, "[t]he courts that do bind court suggest that [a reviewing court] will see an obvious condition precedent and the risk bearing arrangement it reflects and enforce it."
The court further stated: (Emphasis in original.) The court concluded: "So [the plaintiff cannot]—under the present circumstances—win under the plain language of the contract."
Regarding the count alleging breach of the covenant of good faith and fair dealing, the court stated:
On May 15, 2019, the plaintiff, pursuant to Practice Book §§ 11-11 and 11-12, filed a "motion for reargument/reconsideration and articulation" of the court's decision on Greython's motion for summary judgment. On May 20, 2019, the court denied that motion. This appeal followed.5 Additional facts and procedural history will be set forth as necessary.
We begin by setting forth the relevant standard of review, which applies to both of the plaintiff's claims. (Internal quotation marks omitted.) Buehler v. Newtown , 206 Conn. App. 472, 480–81, 262 A.3d 170 (2021).
The plaintiff first...
To continue reading
Request your trial-
Randolph v. Mambrino
...logically correct and find support in the record." (Internal quotation marks omitted.) Electrical Contractors, Inc. v. 50 Morgan Hospitality Group, LLC , 211 Conn. App. 724, 730–31, 273 A.3d 726 (2022)."Summary judgment may be granted where the claim is barred by the statute of limitations.......
- Kling v. Hartford Cas. Ins. Co.
-
Subcontract Payment Provisions Mean Exactly What They Say in Connecticut
...Connecticut Appellate Court decision in Electrical Contractors, Inc. v. 50 Morgan Hospitality Group, LLC, 211 Conn. App. 724 (2022), eliminated any remaining doubt regarding a subcontractor’s right to payment for work performed when the subcontract includes a “pay-if-paid” provision. A pay-......