Emlenton Area Mun. Authority v. Miles

Decision Date05 October 1988
Citation378 Pa.Super. 303,548 A.2d 623
PartiesEMLENTON AREA MUNICIPAL AUTHORITY v. Sidney L. MILES, Doing Business, as Miles Developing and Contracting, Appellant.
CourtPennsylvania Superior Court

David B. Acker, Dist. Atty., Coudersport, for appellant.

Jon M. King, Emlenton, for appellee.

Before BROSKY, KELLY and HESTER, JJ.

BROSKY, Judge.

This is an appeal from the Order of December 30, 1987, which permanently stayed arbitration of the disputes between the parties. Appellant now contends that the trial court erred in finding that the contract between the parties required mutual agreement before any disputes arising from the contract could be submitted to arbitration.

Upon consideration of the record and the briefs of counsel, we now reverse and remand for further proceedings consistent with this Opinion.

On March 13, 1985, appellee Emlenton Area Municipal Authority ("Emlenton") entered into a contract with appellant Sidney L. Miles, d/b/a Miles Developing and Contracting ("Miles"), wherein Miles was to construct a municipal waste water collection and treatment works in Venango and Clarion Counties, Pennsylvania. During the performance of the contract, certain disputes pertaining to the contract arose between the parties, causing them to assert claims for damages against one another.

On June 2, 1986, Miles, in an attempt to resolve his claims against Emlenton, filed a demand for arbitration with the American Arbitration Association. Emlenton responded on August 6, 1986, by filing an application for stay of arbitration proceedings with the Clarion County Court of Common Pleas.

With that matter still pending, Emlenton then filed, on May 4, 1987, an action at law in the same court, asserting its claims for damages against Miles and his surety, 1 Fidelity and Deposit Company of Maryland. In response to the action at law, Miles filed, on June 5, 1987, an application to compel arbitration. The court entered an order that same day to stay the proceedings at law, pending resolution of the issue of the arbitrability of the dispute.

On October 1, 1987, an order was entered with respect to Miles' claims against Emlenton, granting Emlenton's application for a stay of arbitration; similarly, on October 7, 1987, an order was entered in Emlenton's action at law against Miles, denying Miles' application to compel arbitration. In both instances, the court held that those portions of the contract comprising the parties' agreement to arbitrate, only provide for the submission of any dispute or disputes to arbitration upon the mutual consent of the parties to so submit, and that, in light of Emlenton's opposition to arbitration of these disputes, Emlenton could not be compelled to submit to arbitration in either action.

Miles requested reconsideration in both cases, and reconsideration was expressly granted by the order of October 28, 1987. On December 30, 1987, however, the court entered a final order in equity in both actions, permanently staying arbitration. This timely consolidated appeal followed.

Appellant now argues that the trial court erred in finding that the agreement to arbitrate contained within the parties' contract requires mutual consent for the submission of any particular dispute or disputes to arbitration, and maintains that the court's narrow reading of the agreement precluding arbitration violates the liberal policy favoring arbitration, as well as the relevant rules of contractual interpretation and construction, expressed in Pennsylvania appellate law. 2 Conversely, appellee maintains that Pennsylvania law requires strict construction of arbitration agreements, and that a party may be compelled to arbitrate a dispute only upon the finding of a clear, express, and unequivocal agreement to do so.

Our scope of review of an adjudication in equity is well established. The chancellor's findings of fact have the force of a jury verdict, and are not to be disturbed where supported by competent evidence. Presbytery of Beaver-Butler of United Presbyterian Church in U.S. v. Middlesex Presbyterian Church, 507 Pa. 255, 489 A.2d 1317, 1323 (1985), cert den. 474 U.S. 887, 106 S.Ct. 198, 88 L.Ed.2d 167; Sechler v. Sechler, 403 Pa. 1, 169 A.2d 78, 80 (1961). However, the chancellor's conclusions of law are always reviewable, as they are no more than his reasoning from the underlying facts. Presbytery of Beaver-Butler, supra; Sechler, supra; Village Beer and Beverage, Inc. v. Vernon D. Cox & Co., Inc., 327 Pa.Super. 99, 475 A.2d 117, 118 (1984).

In the matter sub judice, the chancellor was called upon to determine whether the parties had agreed to submit any and all disputes to arbitration. Voluntary arbitration is purely a matter of contract, and, absent an express agreement between the parties to arbitrate their disputes, they cannot be compelled to arbitrate. Gaslin, Inc. v. L.G.C. Exports, Inc., 334 Pa.Super. 132, 482 A.2d 1117, 1121 (1984). As such, it is for the court to determine whether an agreement to arbitrate exists, for the construction and interpretation of contracts is a question of law. Utica Mutual Ins. Co. v. Contrisciane, 504 Pa. 328, 473 A.2d 1005, 1008 (1984). As a question of law, therefore, the chancellor's conclusion as to whether the parties have agreed to arbitrate, is reviewable by this Court.

Upon undertaking such review, we are confronted with two basic, and seemingly contradictory, propositions, as noted by the parties themselves: (1) arbitration agreements are to be strictly construed and not extended by implication; and (2) when parties have agreed to arbitrate in a clear and unmistakable manner, every reasonable effort should be made to favor the agreement, unless it may be said with positive assurance that the arbitration clause involved is not susceptible to an interpretation that covers the asserted dispute. See Hassler v. Columbia Gas Transmission Corp., 318 Pa.Super. 302, 464 A.2d 1354, 1356, 1357 (1983); also see Lincoln University of the Comm. System of Higher Education v. Lincoln University Chapter of the American Assoc. of University Professors, 467 Pa. 112, 354 A.2d 576, 581-82 (1976). Obviously, some tension may arise between the two propositions; in making every effort to favor the settlement of a dispute by arbitration, one must be careful not to extend the arbitration agreement by implication beyond the clear, express, and unequivocal intent of the parties as manifested by the writing itself. Hassler, supra.

To resolve this tension, resort may be had to the rules of contractual construction. In construing a contract, the intention of the parties is paramount, and the court will adopt an interpretation which under all circumstances ascribes the most reasonable, probable, and natural conduct of the parties, bearing in mind the objects manifestly to be accomplished. Village Beer, supra, 475 A.2d at p. 121; Unit Vending Corp. v. Lacas, 410 Pa. 614, 190 A.2d 298, 300 (1963). Moreover, one part of a contract cannot be so interpreted as to annul another part, but, rather, the agreement must be interpreted as a whole, giving effect to all of its provisions. Village Beer, supra; Shehadi v. Northeastern Nat'l Bank of Pa., 474 Pa. 232, 378 A.2d 304, 306 (1977). Where a contract may be interpreted in a manner giving effect to all provisions, that interpretation is preferred. Rothstein v. Jefferson Ice Mfg. Co., 137 Pa.Super. 298, 306, 9 A.2d 149 (1939). Finally, where an act or event mentioned in a contract is not expressly made a condition precedent, it will not be so construed absent the clear intent of the parties. Village Beer, supra; American Leasing v. Morrison Co., 308 Pa.Super. 318, 454 A.2d 555, 559 (1982).

The relevant provisions of the parties' contract, as determined by the court in equity, are as follows:

Standard General Conditions

Article 16--Arbitration

16.1 All claims, disputes and other matters in question between Owner and Contractor arising out of, or relating to the Contract Documents or the breach thereof ... shall be decided by arbitration ...

Article 17--Miscellaneous

17.4 The duties and obligations imposed by the General Conditions and the rights and remedies available to the parties hereto, ..., and all of the rights and remedies available to Owner and Engineer thereunder, shall be in addition to and shall not be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by law or contract, ...

Supplemental General Conditions

1. General

(a) The owner and Contractor agree that the following supplemental general provisions shall apply to the work to be performed under this contract and that such provisions shall supercede [sic] any conflicting provisions of this contract.

* * *

* * *

(c) The rights and remedies of the Owner provided for in these clauses are in addition to any other rights and remedies provided by law or under this Contract.

7. Remedies

Except as may be otherwise provided in this Contract, all claims, counter-claims, disputes and other matters in question between Owner and Contractor arising out of or relating to this agreement or the breach thereof will be decided by arbitration if the parties hereto mutually agree, or in a court of competent jurisdiction within the State in which the Owner is located.

(Emphasis supplied.)

In construing the above, the court relied heavily upon the language in Supplemental General Condition 1(a), stating that the Supplemental General Conditions are to supersede "any conflicting provisions" elsewhere in the contract. From 1(a), the court concluded that Supplemental General Condition 7, providing for arbitration only upon the mutual agreement of the parties to submit a dispute or disputes to arbitration, supersedes the mandatory arbitration provision in Article 16.1 of the Standard General Conditions, and precludes appellee from being compelled to arbitrate...

To continue reading

Request your trial
18 cases
  • Trombetta v. Raymond James Financial
    • United States
    • Pennsylvania Superior Court
    • 22 Agosto 2006
    ...Light Co. v. New Warwick Mining Co., 443 Pa.Super. 53, 660 A.2d 1341, 1343-1344 (1995), citing Emlenton Area Municipal Auth. v. Miles, 378 Pa.Super. 303, 548 A.2d 623, 625 n. 2 (1988). 7. In Duquesne, this Court was faced with a somewhat similar situation as the one we now have before us. T......
  • Smith v. Cumberland Group, Ltd.
    • United States
    • Pennsylvania Superior Court
    • 21 Enero 1997
    ...is for the court to determine whether an express agreement between the parties to arbitrate exits. Emlenton Area Municipal Authority v. Miles, 378 Pa.Super. 303, 307, 548 A.2d 623, 625 (1988), allocatur denied, 522 Pa. 613, 563 A.2d 498 (1989) (citing Utica Mutual Insurance Company v. Contr......
  • Highmark Inc. v. Hospital Service Ass'n
    • United States
    • Pennsylvania Superior Court
    • 21 Septiembre 2001
    ...not susceptible to an interpretation that covers the asserted dispute. Midomo, 739 A.2d at 190 (quoting Emlenton Area Mun. Auth. v. Miles, 378 Pa.Super. 303, 548 A.2d 623, 625 (1988)). "To resolve this tension, courts should apply the rules of contractual construction, adopting an interpret......
  • Duquesne Light Co. v. New Warwick Min. Co.
    • United States
    • Pennsylvania Superior Court
    • 12 Junio 1995
    ...apply, the contract at issue must evidence a transaction in or relating to interstate commerce. Emlenton Area Mun. Authority v. Miles, 378 Pa.Super. 303, 306 n. 2, 548 A.2d 623, 625 n. 2 (1988). This inquiry involves a factual determination. Id. Where the factfinder makes no such findings, ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT