Empire Pipeline, Inc. v. Town of Pendleton
Decision Date | 14 July 2020 |
Docket Number | 17-CV-141S |
Citation | Empire Pipeline, Inc. v. Town of Pendleton, 472 F.Supp.3d 25 (W.D. N.Y. 2020) |
Parties | EMPIRE PIPELINE, INC., and National Fuel Gas Supply Corporation, Plaintiffs, v. TOWN OF PENDLETON, Defendant. |
Court | U.S. District Court — Western District of New York |
John G. Schmidt, Jr., JoAnna Jung-Yao Chen, Kenneth A. Manning, Phillips Lytle LLP, Buffalo, NY, for Plaintiffs.
Gary A. Abraham, Law Office of Gary A. Abraham, Great Valley, NY, for Defendant.
DECISION AND ORDER
Before this Court is Plaintiffs’ Motion for Partial Summary Judgment(DocketNo. 10) arguing that the Natural Gas Act, 15 U.S.C. §§ 717, et seq., and FERC regulations preempt Defendant Town of Pendleton's ("Town") ordinance restricting Plaintiffs’ proposed gas pipeline project, construction and operation of a compression station in Pendleton.They seek declaratory judgment or an injunction against enforcement of the Town's zoning ordinance against their gas pipeline project.
Plaintiffs also moved for expedited hearing of this motion (DocketNo. 11), which was granted (DocketNo. 13).
Responses to the summary judgment motion initially were due on April 3, 2017, with replies due April 7, 2017(id. ).Defendant responded (DocketNo. 14), Plaintiffs replied (DocketNo. 15).Defendant then submitted a sur-reply (DocketNo. 16) but Plaintiffs moved to strike the sur-reply (DocketNo. 18).After briefing on the motion to strike(DocketNos. 19, 20), this Court denied the motion to strike(DocketNo. 39).
The parties meanwhile supplemented the motion for summary judgment and defense opposition (DocketNos. 21, 22, 24, 25, 26, 28, 29, 31, 35, 36, 44;seeDocketNos. 23, 27, 34( );cf.DocketNo. 30( )) supplying and updating authorities.On October 10, 2018, this Court granted leave Plaintiffs’ motion to supplement and deemed briefing completed (DocketNo. 38;see alsoDocketNo. 39, deeming briefing completed).On May 8, 2020, Plaintiffs moved to further supplement authorities (DocketNo. 40), which this Court granted (DocketNo. 41).Final responses to the supplemental authorities were due by May 26, 2020, and Plaintiffs’ reply were due June 3, 2020(id. ).Defendant filed its supplemental submission (DocketNo. 42) and Plaintiffs replied (DocketNo. 43).Plaintiffs on July 10, 2020, moved to further supplement authorities to update a previously cited case(DocketNo. 44).With the motion thus fully briefed, it was submitted without oral argument.
Upon consideration of the above-cited briefing and the arguments made therein and for the reasons stated herein, Plaintiffs’ Motion for Partial Summary Judgment(DocketNo. 10) is granted in part , granting declaratory judgment to them.
.After concluding that the project (if consistent with Plaintiffs’ application) would not affect the quality of the environment (id., Ex. A, 158 FERC ¶ 61,145, Certificate ¶ 197, 2017 WL 496277, at *47 ), FERC issued the Certificate conditioned upon Plaintiffs completing authorized construction within two years of date of the Certificate; compliance with applicable FERC regulations; compliance with environmental conditions; and executing contracts (id., Ex. A, 158 FERC ¶ 61,145, Certificate, Commission Ordering Paragraph (C), 2017 WL 496277, at *48 ).
Plaintiffs allege that this Certificate, among other things, bars defendant Town from prohibiting, interfering with, or unreasonably delaying the construction or operation of the pipeline project (id.¶ 11).Plaintiffs assert that the Town opposed construction (id.¶¶ 60-64), delaying the siting, construction, and operation of the compression station (id.¶¶ 74-75, 77-90, 93-98, 105-12).They allege that the Town building inspector refused to act on their building permit application (id.¶¶ 93-98) and, after plaintiffs obtained the Certificate, the Town denied the building permit (id.¶¶ 105-12).
The First Claim seeks a declaratory judgment that National Fuel need not comply with the Town Code as they related to siting, constructing, or operating the compression facility as the Code was interpreted by the Town or declare "that the Town Building Inspector must issue a Building Permit for the Facility and Project in accordance with and consistent with the Certificate"(id.¶¶ 121, 114-21, WHEREFORE Cl. ¶ (a), (b)).The Second Claim seeks an injunction against enforcing the Town Code and future attempts to interfere with, delay, or prevent the siting, construction, or operation of the compression station (id.¶¶ 130, 131, 123-31, WHEREFORE Cl. ¶ (c)).Plaintiffs also seeks continued jurisdiction over this matter "to address any future actions by defendant that contravene this Court's Order, the Certificate or the Natural Gas Act"(id., WHEREFORE Cl. ¶ (d)) and direct and consequential damages from the wrongful enforcement of the Town Code(id., WHEREFORE Cl. ¶ (e)).
The Town answered (DocketNo. 7).The Town raised an affirmative defense that this claim was not ripe (id.¶¶ 132-36) because Plaintiffs entered a stipulation with the New York State Department of Environmental Conservation("DEC") agreeing to allow the DEC to determine Plaintiffs’ application for a Clean Water Act Section 401 Water Quality Certification by April 7, 2017(id.¶ 134, Ex. B).The Town argues that Plaintiffs’ claims are not ripe until they obtain the Clean Water Act Water Quality Certification or a waiver of the requirement (id.¶ 135).Alternatively, the Town contends that Plaintiffs had not obtained all federal approvals and had appealed to the FERC conditions under the Certificate, thus the Town argues that this Court should abstain from deciding this case until the FERC had decided Plaintiffs’ appeal (id.¶¶ 137-41, Ex. C).The Town also asserts that Plaintiffs failed to exhaust administrative remedies by not appealing the denial of the building inspector to the Town's Zoning Board of Appeals or seeking a special exception permit (id.¶¶ 142-50).
Plaintiffs obtained the Certificate in February 2017 and appealed a month later (id., Ex. C).The appeal sought reconsideration of rate determination (id., Ex. C, at 2-3).They also sought clarification whether the DEC's failure to issue a decision on their application for the Clean Water Act Water Quality Certification resulted in a waiver of that requirement (id. at 3-4, 17-26).Plaintiffs also contend that they were not required to seek state law permits (id. at 3-4), arguing that the state requirements were preempted by federal law (id. at 4-17).
Magistrate Judge Schroeder then ordered the parties to submit proposed deadlines for a Case Management Order (DocketNo. 9).Plaintiffs moved for summary judgment on the same day (DocketNo. 10).While their motion was pending, plaintiffs also submitted a proposed Case Management Order (DocketNo. 17); a Scheduling Order or Case Management Order has not been entered.
Plaintiffs moved for partial summary judgment (DocketNo. 10).They argue that the Natural Gas Act and the FERC preempts the Town Code and its restrictions on the construction and operation of the compression station . )They seek summary judgment for a declaration of this preemption (id. at 12-20) and an injunction against the Town (id. at 21-23).If granted, the issues remaining for adjudication would be any monetary damages Plaintiffs incurred (seeDocketNo. 1, Compl., WHEREFORE Cl. ¶ (e)).
The material facts are not in dispute (the Town did not submit a Statement of Facts, although the Town's Memorandum of Law includes a statement of fact, DocketNo. 14, Def. Memo. at 11-21;see alsoDocket No. 16, Def. Sur-Reply Memo.at 3-5).Plaintiffs engage in the transportation of natural gas in interstate commerce and are regulated by FERC .Plaintiffs jointly filed an application with the FERC for a Certificate of Public Convenience and Necessity for the Northern Access 2016 Project (id.¶ 2).FERC approved the project, including construction of the compressor station in Pendleton (id.¶¶ 3-5).The Town intervened in the FERC proceeding shortly after Plaintiffs ap...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

Start Your 7-day Trial
-
Minner v. Navient Corp.
... ... Liberty Lobby, ... Inc. , 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 ... (W.D.N.Y. Feb. 16, 2022) (Skretny, J.); Empire Pipeline, ... Inc. v. Town of Pendleton , 472 ... ...