Endres v. Warriner

Decision Date17 June 1981
Docket NumberNo. 13194,13194
Citation307 N.W.2d 146
PartiesJames N. ENDRES, Plaintiff and Appellee, v. Jesse E. WARRINER and Agnes D. Warriner, Defendants and Appellants.
CourtSouth Dakota Supreme Court

Thomas F. Burns of Gribbin, Burns & Eide, Watertown, for plaintiff and appellee; Francis C. Burns of Gribbin, Burns & Eide, Watertown, on brief.

Thomas K. Wilka of Burns, Hagen & Wilka, Sioux Falls, for defendants and appellants.

WOLLMAN, Chief Justice.

Appellants, Jesse E. Warriner and Agnes D. Warriner, appeal from the entry of judgment that granted James N. Endres (appellee) specific performance of a real estate contract. We affirm.

Jesse Warriner owns a quarter section of land in Codington County, South Dakota. His brother and sisters (hereinafter "siblings") owned two adjacent quarter sections of land. On July 2, 1979, appellee, who had rented these three quarters for approximately five years, entered into a contract to purchase the two quarters of land from the siblings. That same day appellee entered into a contract with appellants for the purchase of Jesse's quarter section in order to provide access to the other two quarters. Under the terms of the latter contract, appellee was to pay appellants $46,000 on or before January 1, 1980, plus eight percent interest from the date of the agreement. The contract was conditioned upon the completion of the sale of the siblings' quarters.

Appellee thereafter applied for a loan from the Farmers Home Administration. 1 According to appellee, he realized in September of 1979 that there might be some delay in receiving the loan proceeds; as a result, he had a conversation with Jesse Warriner regarding certain fall farm work that appellee wanted to do on the quarter section.

Appellee testified, and the trial court found, that appellee had spoken with Jesse Warriner in November of 1979 and explained to Jesse that he wanted to put a well and waterline on the quarter section. Appellee asked Jesse if it mattered whether the loan proceeds were late, because if it did, appellee did not want to dig the well. Jesse replied that "it was okay." Appellee told Jesse that he was proceeding with the loan and stated that there were no problems but simply some unforeseen delays. Jesse then assured appellee that appellee should not be concerned about not being able to buy the farm or losing any investment in the well and waterline.

The loan proceeds did not arrive on January 1, 1980. Appellants made no demand for the purchase price on January 1, did not tender a deed, and did not attempt to terminate the contract at that time. Sometime prior to January 13, 1980, appellee had a conversation with one of the siblings and explained the delay to her.

There was testimony that on January 13, 1980, appellee explained to Jesse that he (appellee) was still proceeding with the loan and that the proceeds were expected soon. Jesse replied that he understood how things got slowed down. He did not indicate that there was any problem with a further delay. Appellee testified that he reminded Jesse that the Warriners were still drawing interest on the contract price. Appellants did not demand the purchase money nor tender a deed on this occasion. The parties set no other date for completion of the contract.

On February 1, 1980, appellants sent appellee a letter attempting to terminate the contract because of appellee's failure to pay the contract price plus interest on or before January 1, 1980. On February 22, 1980, appellee tendered the purchase price plus interest to appellants. Appellants refused to convey title.

Appellee purchased the siblings' quarters on February 22, 1980. There was testimony that appellee could have gotten an interim loan from a different source to pay for the land on or before January 1, 1980, had he not been assured that there would be no problem with payment after that date.

I

Appellants contend that the grant of specific performance was improper because there was no mutuality of remedy. Appellants argue that appellee could have unilaterally abrogated the contract without recourse to appellants by virtue of the following provision of the contract:

It is agreed that this contract is conditioned upon the completion of the sale of (the siblings' quarters) to the Purchaser herein. In the event that said sale has not been completed prior to January 1, 1980, or for any reason cannot be completed, this contract shall be null and void.

Citing SDCL 21-9-4, 2 appellants contend that specific performance could have been granted only if appellee had fully performed under the contract or appellants could have compelled appellee's performance under the contract.

Initially, we recognize that "(t)he modern decisional tendency is against lending the aid of courts to defeat contracts on technical grounds of want of mutuality." Texas Gas Utilities Company v. Barrett, 460 S.W.2d 409, 412 (Tex.1970) (citation omitted).

It is not essential that mutuality of remedy exist at the inception of the contract. J. I. Case Threshing Mach. Co. v. Farnsworth, 28 S.D. 432, 134 N.W. 819 (1912). Rather, "it is sufficient if such mutuality of remedy is available at the time suit is filed or even at the time of the decree." 71 Am.Jur.2d Specific Performance § 23 (1973). By tendering the purchase price and bringing this suit for specific performance, appellee indicated that he was willing to complete the contract and submitted himself to the jurisdiction of the court and was bound by its determination. Therefore, mutuality of remedy existed at the time the suit was filed. Harper v. Goldschmidt, 156 Cal. 245, 104 P. 451 (1909); Mangus v. Porter, 276 So.2d 250 (Fla.Dist.Ct.App.1973); Jones v. Barnes, 105 A.D. 287, 94 N.Y.S. 695 (1905).

Appellants also contend that the contract was not supported by adequate consideration. Appellants argue that under the previously quoted provision of the contract appellee could have refused to perform the siblings' contract and thus relieved himself from any obligation under the contract in question here.

Appellee's promise to buy Jesse Warriner's land was conditioned upon the completion of the sale of the siblings' land. A conditional promise may be adequate consideration.

Very often parties reach an agreement, the performance of which is agreed to be contingent upon some future event. There is no doubt that if the happening of the event is outside the control of the parties, the agreement does not fall for lack of consideration. If, however, the happening of the event is within the control of one of the parties, is his promise illusory? The better decisions have through a process of interpretation answered in the negative....

J. Calamari & J. Perillo, Law of Contracts § 4-18 (2d ed. 1977) (footnotes omitted). See also Restatement (Second) of Contracts § 78 (Tent. Draft No. 2, 1965).

A promise is illusory "only if it in no way limits the promisor's future action." Douglas v. City of Dunedin, 202 So.2d 787, 788 (Fla.Dist.Ct.App.1967). We agree with the following statement from the Law of Contracts, supra, at 166 (footnotes omitted):

Agreements of this kind serve a vital purpose. They are entered into with the understanding that both parties are firmly committed to the performance of the agreement provided that cooperation is forthcoming from a financial institution, landlord or licensing authority. The purchaser or lessee has wisely protected himself, with the seller's consent, against the possibility that he will be unable to obtain the financing, lease or license. In so doing, however, he has impliedly promised to use his best efforts to bring about the happening of the condition to his promise. His conditional promise is thus by no means illusory.

So also here, appellee impliedly promised to use his best efforts to complete the purchase of the siblings' quarters. We hold that there was adequate consideration. See also Petroleum Refractionating Corp. v. Kendrick Oil Co., 65 F.2d 997 (10th Cir. 1933); Scott v. Moragues Lumber Co., 202 Ala. 312, 80 S. 394 (1918); Vickrey v. Maier, 164 Cal. 384, 129 P. 273 (1912); Douglas v. City of Dunedin, supra. 3

II

Appellants contend that the trial court erred in finding that the time of payment and the time of the essence clauses in the contract were waived by appellants. We do not agree.

There was conflicting testimony with regard to the substance of various conversations between appellee and Jesse Warriner subsequent to July 2, 1979. It is for the trial court to determine the credibility of the witnesses and the weight to be accorded their testimony, and a reviewing court is required to accept...

To continue reading

Request your trial
8 cases
  • Famous Brands, Inc. v. David Sherman Corp.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • March 20, 1987
    ...promote it would be consideration. Famous' promise would be contingent on Sherman fulfilling its promise to sell. Cf. Endres v. Warriner, 307 N.W.2d 146, 149 (S.D.1981) (finding adequate consideration in promise contingent on third party action). Contrary to Sherman's arguments, this is not......
  • Hanna v. Landsman
    • United States
    • South Dakota Supreme Court
    • June 17, 2020
    ...is not an alteration of a written contract." Johnson v. Sellers , 2011 S.D. 24, ¶ 16, 798 N.W.2d 690, 695 (citing Endres v. Warriner , 307 N.W.2d 146, 149 (S.D. 1981) ). In Johnson , we held "that notwithstanding the statute of frauds, parties may orally waive conditions involving the perfo......
  • O'Brien v. R-J Development Corp., R-J
    • United States
    • South Dakota Supreme Court
    • May 14, 1986
    ...Johnson v. Elliot, 123 Mont. 597, 218 P.2d 703 (1950); and Leadbetter v. Price, 103 Or. 222, 202 P. 104 (1921). Cf. Endres v. Warriner, 307 N.W.2d 146, 148 (S.D.1981), wherein this Court stated that by the real estate purchaser's tender of the price and institution of suit for specific perf......
  • Lamar Advert., L.L.C. v. City of Rapid City, #28903
    • United States
    • South Dakota Supreme Court
    • June 3, 2020
    ...competent jurisdiction or other competent authority to be invalid, void, or otherwise unenforceable."[¶30.] Lamar cites Endres v. Warriner, 307 N.W.2d 146 (S.D. 1981), for the unremarkable proposition that a contract contingent on a future event is nevertheless valid and enforceable. What L......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT