Englebert v. Ryder

Decision Date22 August 1958
Docket NumberNo. 9677,9677
Citation77 S.D. 333,91 N.W.2d 739
PartiesGene ENGLEBERT, doing business as Englebert Plumbing & Heating, Plaintiff and Respondent, v. C. F. RYDER, doing business as Ryder Construction, Defendant and Appellant.
CourtSouth Dakota Supreme Court

James Clapp and John C. Searle, Rapid City, for defendant and appellant.

Julius F. Sieler, and William F. Brady, Rapid City, for plaintiff and respondent.

SMITH, Judge.

This is an action for damages for breach of contract. Trial to a jury resulted in a verdict and judgment for plaintiff for $1,500 as prayed in his complaint. Thereafter a motion for new trial was made and denied. Defendant has appealed.

In view of the result below, under settled principles, the facts are stated in the light most favorable to plaintiff.

The plaintiff is a plumbing and heating contractor of Rapid City, South Dakota. The defendant is a general construction contractor of Gordon, Nebraska.

At a letting on November 14, 1956, defendant was awarded the contract to construct an addition to the elementary grade school at Pine Ridge, South Dakota. Plaintiff had procured a copy of the plans and specifications from the architect and prepared an estimate on the plumbing and heating. On the day of the letting defendant used the telephone to solicit a bid from plaintiff on that phase of the construction. In that conversation plaintiff offered to do the plumbing and heating for $4,700. Defendant informed him that his was the lowest bid he had received. Nothing further transpired between the parties until December 23rd. On that day defendant telephoned and asked plaintiff if he was still interested. Plaintiff made an affirmative answer and defendant asked him to come to Pine Ridge and bring with him a roof drain. Plaintiff drove to Pine Ridge on the 24th of December and took with him the requested drain. Plaintiff's testimony of their conference includes the following: 'Yes, Mr. Ryder said that I could go ahead with the job; * * *. Mr. Ryder and I decided it would be best before I started to wait until he got the outside closed in, because it was snowing and a blizzard, and so I told him I would be down as soon as he was ready and had the top on. And he said he would call me. He said, 'O.K., we will go ahead with it, then,' and he asked me for a bond which I told him I would mail down to him. He asked me for a performance bond made out to him for the price of the contract.'

In January 1957 plaintiff ordered materials for use in the Pine Ridge construction and waited for the promised call from defendant. Of such material a minor item was taken to the job on January 5th, and a quantity of material was delivered there on January 24th. On Sunday, January 21st, defendant was in Rapid City and called plaintiff about 9:00 a. m. and asked him to come to the Alex Johnson Hotel. Plaintiff said he would be down in about 45 minutes. He did not arrive there until 10:30. He then inquired at the desk and was informed that defendant had checked out. On January 25th plaintiff received a letter from defendant informing him that he had 'made other arrangements relative to the plumbing & heating at Pine Ridge.' On January 28th defendant telephoned plaintiff to remove his materials from the job. Plaintiff complied with that command on the 29th.

Plaintiff had not furnished a performance bond as promised when he received the above described letter from defendant. He had contacted his insurance agency early in January and received assurance that the bond would be written. He had also sent a form of written subcontract to defendant for execution. Defendant did not execute that instrument. Plaintiff's insurance agent was sworn as a witness and testified that according to insurance practice such performance bonds are written after a construction contract is reduced to writing. On January 24th the insurance agent wrote defendant for a copy of a written plumbing and heating subcontract awarded plaintiff to submit to the bonding company in connection with plaintiff's application for a performance bond. Defendant responded to that letter by telephone and informed plaintiff's insurance agent that when plaintiff failed to meet him at the hotel in Rapid City as promised he had let the subcontract to another plumbing and heating concern.

On the theory that plaintiff had failed to prove a prima facie case defendant moved for a directed verdict at the close of plaintiff's case in chief and renewed his motion at the close of the evidence. The trial court's refusal to direct is assigned as error. Two specifications of insufficiency of the evidence were asserted in defendant's motion, viz., (1) Exhibit (1), the prime contract, and specifications, and the oral testimony establish that plaintiff never completed an offer, and (2) if an offer was made by plaintiff, the evidence fails to establish an acceptance of that offer by defendant.

The prime contract and specifications, which were received in evidence as Exhibit 1, are contained in a booklet of upwards of seventy-five pages. Included therein are provisions denominated 'conditions'. It is provided therein, before work is awarded to a subcontractor, that he must be approved in writing by the owner, and that he place approved policies of workmen's compensation and public liability insurance in effect before commencing work. The 'conditions' make no reference to a subcontractor's performance bond, but defendant asked for such a bond, and plaintiff readily agreed to mail him such a bond. According to defendant's version of the talk between the parties on December 24th, after mentioning the foregoing requirements, he said to plaintiff 'Well, Gene, you get...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT