Environmental Defense Fund, Inc. v. Froehlke, 72-1628.

Decision Date20 April 1973
Docket NumberNo. 72-1628.,72-1628.
Citation477 F.2d 1033
PartiesENVIRONMENTAL DEFENSE FUND, INC., et al., Appellants, v. Robert F. FROEHLKE, Secretary of the Army, et al., Appellees.
CourtU.S. Court of Appeals — Eighth Circuit

Edward Lee Rogers, Gen. Counsel, East Setauket, N. Y., for appellants.

Eva R. Datz, Atty., Dept. of Justice, Washington, D. C., for appellees.

Lyman Field and F. Philip Kirwan, Kansas City, Mo., for intervenors.

Before HEANEY and ROSS, Circuit Judges, and BENSON, Chief District Judge.*

HEANEY, Circuit Judge.

The primary issue on this appeal is whether the trial court erred in refusing to enjoin the defendants from proceeding with all activities relating to the construction of the Harry S Truman Dam and Reservoir Project on the Osage River in Missouri, pending the filing of a final Environmental Impact Statement (E.I.S.) by the Corps of Engineers in accordance with § 102(2)(C) of the National Environmental Policy Act of 1969. 42 U.S.C. §§ 4321, 4332(2)(C).

The project was authorized by Congress in 1954. Its basic purpose was to alleviate the flooding of towns and farms along the Osage, Mississippi and Missouri Rivers. The project was reauthorized in 1962 to promote conservation, power development and recreation. The dam, if built according to present design, will consist of an earth-fill embankment about 5,000 feet in length, a concrete structure slightly less than 1,000 feet long, and a dike 7,500 feet in length. Maximum height of the dam will be ninety-six feet above the valley floor. The reservoir will inundate 209,300 acres at full flood control pool and 55,600 acres of land at conservation or multi-purpose level. The reservoir's capacity is 5,202,000 acre-feet at flood control level. The dam will be located in the vicinity of Warsaw, Missouri, immediately upstream from the Lake of the Ozarks. The expected total cost of the project to the federal government is $234,692,000.

The first contract was awarded on July 15, 1963, six years prior to the passage of NEPA. By June of 1972, $74,000,000 had been expended for planning, land acquisition, road relocation and construction.

In March of 1972, the plaintiffs initiated this action in the United States District Court for the Western District of Missouri, seeking to enjoin the defendants from proceeding with the project. They contended that the defendants were proceeding with the project in violation of NEPA, the Fish and Wildlife Coordination Act of 1934,1 16 U.S.C. § 661 et seq.; the Environmental Improvement Act of 1970, 42 U.S.C. § 4371; the Water Bank Act of 1970, 16 U.S.C. § 1301 et seq.; various other statutes and the United States Constitution. The principal violation alleged was the failure to prepare and file an E.I.S. pursuant to § 102(e) of NEPA. The plaintiffs asked the court to enjoin road relocations, land acquisitions, construction activity and all other work on the project until a final E.I.S. was filed in accordance with NEPA.

Carefully directed pretrial proceedings were conducted by the court in March and April, 1972. In May of 1972, the court held an evidentiary hearing on the merits. Thereafter, the parties stipulated that the environmental impact of the project would be significant, particularly with respect to fish fauna, archaeological and paleontological sites, wildlife and waterfowl habitat, mussels, society, agriculture and economics.

The parties further stipulated that certain activities would be halted by the Corps of Engineers pending the completion of a final E.I.S. They agreed: (1) that a draft E.I.S. would be prepared by September 15, 1972, and a final E.I.S. by March 1, 1973; (2) that the plaintiffs could include data, comments and statements as appendices to the studies; and (3) that specified guidelines would be followed by the Corps in preparing the study. They were unable to agree on the crucial question of whether the Corps should be required to cease all activities until the final E.I.S. had been filed and reviewed. That question was left for the court to decide.

The District Court's judgment, accompanied by a detailed and scholarly memorandum opinion, was entered on September 13, 1972. Environmental Defense Fund, Inc. v. Froehlke, 348 F.Supp. 338 (W.D.Mo.1972). The court held that the plaintiffs were entitled to judicial review of the defendants' actions, and that the defendants were obligated to comply with the provisions of NEPA in completing the project, even though the project was well under way before NEPA was passed.2 It found that the Corps had started the preparation of an E.I.S. prior to the commencement of this action and was completing it as fast as the circumstances permitted. It enjoined the defendants from proceeding with certain activities and contracts, including those which the defendants had agreed to defer, but permitted the defendants to continue certain on-going construction activities, road relocations, cemetery relocations, voluntary property acquisitions, and design contracts, pending the filing of a final E.I.S. Moreover, it retained jurisdiction of the matter pending the filing of the final E.I.S.

The court held, however, that the plaintiffs were not entitled to an injunction halting all work on the project pending a final E.I.S. It did so on the grounds that not every violation of NEPA gives rise to a right to blanket injunctive relief. The court stated:

"It is our judgment that the procedures provided for in the final judgment and decree, if and when complied with, will assure full compliance with NEPA and all other applicable law as promptly as is practicable under the circumstances. It is further our judgment that the issuance of a blanket injunction stopping all construction would not speed the preparation or enhance the probabilities that a sufficient EIS will be prepared. Under these circumstances, we believe that a proper balancing of the factors which must be given appropriate consideration under general equity principles requires that the most substantial costs incident to the termination or suspension or work to an extent greater than that provided in the final judgment and decree should be avoided."

Environmental Defense Fund, Inc. v. Froehlke, supra at 353. The court gave the following additional reasons for its action:

(1) The work, which will go forward pending the filing of an E.I.S., will only have a minimal environmental impact on the Osage Basin. No work will be done on the dam which will impede the free flow of the river and affect the fish, wildlife and wildfowl habitat in or along the river. The new roads will affect some wildlife habitat, but the old road sites will, in time, partially replace the habitat lost.

(2) The project was commenced six years prior to the passage of NEPA, and a number of contracts have been let pursuant to congressional authorization. Substantial cost would be involved in terminating these contracts. Additional costs would be incurred in start-up costs if the ultimate decision is to proceed. Moreover, the defendants were in various stages of acquiring land, and the cost involved in terminating such acquisitions would be substantial.

(3) The Corps of Engineers was acting in good faith in bringing the project into compliance with NEPA. It began the preparation of a preliminary E.I.S. prior to the initiation of this action. It filed that statement in October, 1972, and committed itself to filing a final E. I.S. by May 1, 1973. It agreed to permit the plaintiffs to file data, comments and statements with the Corps for inclusion in the E.I.S. It also committed itself to follow the guidelines set out by the court in preparing the final E.I.S.

(4) The families involved desire that the cemetery...

To continue reading

Request your trial
33 cases
  • United States v. Stoeco Homes, Inc.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (3rd Circuit)
    • May 23, 1974
    ...§ 4332(c). That requirement is applicable to major federal actions by the Army Corps of Engineers. E. g., Environmental Defense Fund, Inc. v. Froehlke, 477 F.2d 1033 (8th Cir. 1973). Neither The Fish and Wildlife Coordination Act nor The National Environmental Policy Act by their terms appl......
  • Kipperman v. McCone
    • United States
    • U.S. District Court — Northern District of California
    • October 26, 1976
    ...981, 987 (E.D.Wis.1975); Environmental Defense Fund, Inc. v. Froehlke, 348 F.Supp. 338, 364 (W.D.Mo.1972), aff'd on other grounds, 477 F.2d 1033 (8 Cir. 1973); English v. Town of Huntington, 335 F.Supp. 1369, 1373 (E.D.N.Y.1970); Macias v. Finch, 324 F.Supp. 1252, 1254-1255 (N.D. The Court ......
  • Driver v. Helms
    • United States
    • United States Courts of Appeals. United States Court of Appeals (1st Circuit)
    • May 25, 1978
    ...388 F.Supp. 981, 987 (E.D.Wis.1975); Environmental Defense Fund, Inc. v. Froehlke, 348 F.Supp. 338, 364 (W.D.Mo.1972), aff'd, 477 F.2d 1033 (8th Cir. 1973); English v. Town of Huntington, 335 F.Supp. 1369, 1373 (E.D.N.Y.1970); Macias v. Finch, 324 F.Supp. 1252, 1255 (N.D.Cal.1970); Brotherh......
  • I-291 Why? Association v. Burns
    • United States
    • U.S. District Court — District of Connecticut
    • February 7, 1974
    ...else when finally obtained." Lathan v. Volpe, supra, 455 F. 2d at 1117 (emphasis in original). See also Environmental Defense Fund, Inc. v. Froehlke, 477 F.2d 1033, 1037 (8th Cir. 1973): "We recognize that the injunction is the vehicle through which the congressional policy behind NEPA can ......