Erlich v. Hendrick Const. Co., Inc., 750878

Decision Date11 June 1976
Docket NumberNo. 750878,750878
Citation217 Va. 108,225 S.E.2d 665
CourtVirginia Supreme Court
PartiesBerl M. ERLICH et al. v. HENDRICK CONSTRUCTION COMPANY, INC. and Fidelity and Deposit Company of Maryland. Record

Robert C. Fitzgerald, Fairfax (John F. Carlton, Jr., Manassas, Fitzgerald & Smith, Fairfax, on briefs), for appellants.

Ivy P. Blue, Jr., Hanover, for appellees.

Before I'ANSON, C.J., and CARRICO, HARRISON, COCHRAN, HARMAN, POFF and COMPTON, JJ.

POFF, Justice.

On August 15, 1972, Arthur W. Patton and Berl M. Erlich, partners in Tysons Ice Rink (owner), signed a $675,000 contract with Hendrick Construction Company, Inc., (contractor), for the construction of an ice rink at Tysons Corner. The contract, prepared by contractor, provided that work would begin within 10 days and would be 'substantially completed within 150 calender (sic) days.' Architect's specifications, expressly incorporated in the contract, provided that 'time is of the essence of this contract' and fixed liquidated damages of $200 per day '(i)f the contractor shall neglect, fail or refuse to complete the work within the time specification'. In a written addendum to the contract, the following language appeared:

'WE OMIT ANY AND ALL PENALTY CLAUSES CONCERNING TIME ALLOTTED FOR COMPLETION OF THIS PROJECT.'

An attachment to the contract, entitled 'Conditions', stated:

'There are no oral or written understandings or agreements between buyer and seller relative to this sale that are not fully expressed in this contract or in the contract of which this is a part.'

At the time of execution, Patton and Erlich signed a note, post-dated January 15, 1973, promising to pay contractor $25,980 on January 15, 1974. On the face of the note were the words: 'Not valid if building is not built.' On brief and at trial, contractor said that the note constituted consideration in addition to that stated in the contract, and that the note was executed and the time completion clause was inserted in the contract to induce lenders to finance construction. The amount of the security and performance bonds issued by Fidelity and Deposit Company of Maryland (surety) was $800,000.

The Ice Rink was not completed within the 150-day period. On June 13, 1973, a change order was executed authorizing a modification in a masonry partition. The last paragraph (hereinafter, 'the time extension paragraph'), stated:

'This is also an extension of time to the contract agreement between Tysons Ice Rink Limited Partnership and Hendrick Construction Company, Inc. dated 15 August 1972 until the project can be completed due to the many change orders and severe weather conditions this project has been working under. If anyone should instigate any suits against Hendrick Construction Company, Inc., Tysons Ice Rink Limited Partnership, or Burl (sic) M. Erlich or Arthur W. Patton will stand all cost, plus 25% For attorney fees to defend said suits.'

By September 1973, the project was still not completed, and owner terminated the contract. On October 3, 1973, the parties executed a written agreement which stated that it was 'being entered into for the purpose of allowing the Contractor to return to the job site'. Referring to the August 15, 1972, contract completion clause and reciting owner's 'opinion' that contractor had failed to complete construction 'in the time included in the written contract', the agreement provided that 'execution of this Agreement in no way alters the terms of the written contract . . . (or) serve(s) to extend the time for performance of the contract beyond the 150 days set in the written contract'. It provided further that '(e)ach party specifically reserves any and all rights it might have . . . to seek damages for breach of contract.' The agreement authorized contractor to 'finish the work' within 40 days and fixed a penalty of $1000 per day in liquidated damages for any delay beyond that time. Contemporaneously with the new agreement, the parties executed a change order which duplicated the language of the June 13, 1973, change order, except that the time extension paragraph was omitted.

Contractor completed the project on November 14, 1973, and owner claims no damages for breach of the October 3, 1973, agreement.

On January 22, 1974, contractor filed a memorandum of mechanic's lien in the sum of $133,919.24. Contractor filed a motion for judgment on the note (Law No. 31029) on March 25, 1974. Three days later, owner filed a motion for judgment against contractor seeking $513,400 in damages for fraud and breach of contract (Law No. 31056). Four days later, contractor filed a bill of complaint to enforce its mechanic's lien (Chancery No. 42224), and owner filed a cross-bill seeking damages for fraud and breach of contract. Sitting without a jury, the trial court consolidated the three cases for trial.

Owner introduced evidence to show that the time extension paragraph did not appear on the June 13, 1973, change order at the time it was signed. An expert in the analysis of typewritten documents testified that the different color type and the misalignment of margins indicated that the paragraph had been added to the document some time after its initial preparation. Owner contended that because the project had not been completed on time, it had suffered substantial damages, including increased interest costs and loss of rental revenues during the period of delay. Owner testified that the roof was defective and that, because of the improper installation of a 'header trench', the ice rink had to be closed for repairs for nearly a month during the fall of 1974.

Edward Hendrick, president and sole stockholder of contractor, testified that the August 15, 1972, agreement between the parties consisted of three components: the written contract, the promissory note, and a contemporaneous oral agreement to execute a change order at a later date extending the time for completion. He said that the time extension paragraph was included in the June 13, 1973, change order pursuant to the oral agreement and that it was placed there before Patton signed his name. Hendrick believed that, until the 40-day limit was fixed in the October 3, 1973, agreement, contractor was not bound to any completion deadline.

Contractor introduced evidence to show that the soil on the job site would not percolate, that the water table was high and that pools of water accumulated during the course of construction; that heavy rains, high winds, and 'unfavorable' weather conditions slowed progress; and that, but for these problems and several change orders for work not included in the original plans, there would have been no delay.

On April 4, 1975, pursuant to letter opinion dated March 27, 1975, the trial court entered three final orders. In Law No. 31029, the order awarded contractor judgment for the face of the note, plus interest and attorney's fee. In Law No. 31056, the order denied owner's claim for damages for breach of contract. In Chancery No. 42224, the order awarded contractor $113,650 for 'money due and owing . . . for construction work under the contract' and denied owner's claim under its cross-bill.

I.

Challenging the final order in Law No. 31056 and the order on the cross-bill in Chancery No. 42224 denying damages for breach of contract, owner argues that 'parole (sic) evidence . . . which tended to vary the terms of the written contract' was inadmissible, and that the trial court committed reversible error in admitting evidence to support contractor's contention that the parties orally agreed to issue a change order amending the 150-day completion deadline written into the formal contract. Contractor, on the other hand, says that 'a separate oral agreement as to any matter on which the written contract is silent and which is not inconsistent with the terms thereof, may be proved by parol evidence if it was not the intention of the parties that the instrument was the complete and final statement of the entire transaction.' Here, argues contractor, the August 15, 1972, agreement was not 'totally integrated' and parol evidence was admissible to prove the 'entire agreement between the parties.'

'The rule which excludes parol evidence when offered to vary the terms and conditions of an integrated written contract has nowhere been more strictly adhered to in its integrity than in Virginia. It, in effect, declares that, where parties have reduced their contract to a writing which imposes a legal obligation in clear and explicit terms the writing shall be the sole memorial of that contract, and it is conclusively concluded that the writing contains the whole contract, and is the sole evidence of the agreement.' (Citation omitted). Pulaski Bank Ex'r v. Harrell, 203 Va. 227, 233, 123 S.E.2d 382, 387 (1962).

See also High Knob, Inc. v. Allen, 205 Va. 503, 506, 138 S.E.2d 49, 52 (1964); Durham v. Pool Equipment Co., 205 Va. 441, 446, 138 S.E.2d 55, 59 (1964); Enlow & Son v. Higgerson, 201 Va. 780, 789--90, 113 S.E.2d 855, 862 (1960).

The written contract of August 15, 1972, 'imposes a legal obligation in clear and explicit terms', Viz., the obligation to complete construction in 150 days. The parties expressly agreed that 'time is of the essence of this contract', and they entered into mutual covenant that '(t)here are no oral or written understandings or agreements . . . that are not fully expressed in this contract'. Contractor insists that the addendum to the contract omitting 'any and all penalty clauses concerning time allotted for completion' must be construed as a revocation of the time completion clause in the body of the contract. In our view, the language in the addendum, chosen by contractor, does nothing more than eliminate the penalty clause in the architect's specifications fixing liquidated damages for delay, leaving unimpaired owner's right to recover conventional damages resulting from unexcused delay.

Evidence pertaining to the alleged 'separate oral...

To continue reading

Request your trial
16 cases
  • Williams v. Williams, Record No. 1176-08-2 (Va. App. 7/21/2009)
    • United States
    • Virginia Court of Appeals
    • July 21, 2009
    ...Braden v. Isabell K. Horsley Real Estate, Ltd., 245 Va. 11, 16, 425 S.E.2d 481, 484 (1993) (citing Erlich v. Hendrick Constr. Co., 217 Va. 108, 114, 225 S.E.2d 665, 669 (1976)); see Chappell v. White, 182 Va. 625, 632-34, 29 S.E.2d 858, 861-62 Furthermore, under the "plain meaning rule" the......
  • Synchronized Constr. Servs., Inc. v. Prav Lodging, LLC
    • United States
    • Virginia Supreme Court
    • October 31, 2014
    ...a mechanic's lien. Johnston & Grommett Bros. v. Bunn, 108 Va. 490, 493, 62 S.E. 341, 342 (1908) ; see also Erlich v. Hendrick Constr. Co., 217 Va. 108, 115, 225 S.E.2d 665 (1976).In a suit by a subcontractor to enforce a mechanic's lien the focus of the equity court's determination is upon ......
  • Suntrust Mortgage Inc. v. Aig United Guar. Corp.. A/K/A United Guar. Corp..
    • United States
    • U.S. District Court — Eastern District of Virginia
    • April 26, 2011
    ...The parol evidence rule “has nowhere been more strictly adhered to in its integrity than in Virginia.” Erlich v. Hendrick Const. Co., Inc., 217 Va. 108, 225 S.E.2d 665, 668 (1976). The rule provides: “[W]here an agreement is complete on its face, is plain and unambiguous in its terms, the c......
  • Advanced Marine Enterprises v. Prc Inc.
    • United States
    • Virginia Supreme Court
    • June 5, 1998
    ...and granting legal remedies which would otherwise be beyond the scope of [the chancellor's] authority." Erlich v. Hendrick Constr. Co., Inc., 217 Va. 108, 115, 225 S.E.2d 665, 670 (1976) (citing Johnston v. Bunn, 108 Va. 490, 493, 62 S.E. 341, 342 (1908)); see Iron City Sav. Bank v. Isaacse......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT