Fastrack Crushing Servs., Inc. v. Abatement Int'l/Advatex Assocs., Inc.
Decision Date | 24 February 2006 |
Docket Number | No. 2005–132.,2005–132. |
Citation | 153 N.H. 284,893 A.2d 674 |
Court | New Hampshire Supreme Court |
Parties | FASTRACK CRUSHING SERVICES, INC. v. ABATEMENT INTERNATIONAL/ADVATEX ASSOCIATES, INC. and another. |
Hall, Morse, Anderson, Miller & Spinella, P.C., of Concord (Frank P. Spinella, Jr., on the brief and orally), for the plaintiff.
Rath, Young and Pignatelli, P.A., of Concord (Brian T. Tucker, on the brief and orally), for the defendants.
The defendants, Abatement International/Advatex Associates, Inc. (Advatex), and American Guarantee & Liability Insurance Co. (AGLIC), appeal an order of the Superior Court (Morrill, J.) denying their motion to dismiss the claim of the plaintiff, Fastrack Crushing Services, Inc. (Fastrack), and an order of the Superior Court (McHugh, J.) in favor of Fastrack on the parties' cross-motions for summary judgment. Fastrack cross-appeals an order from the Superior Court (Morrill, J.) denying its motion to reconsider on the issue of attorney's fees and late payment charges. We reverse the trial court's ruling on the defendants' motion to dismiss and therefore do not address the motions for summary judgment or attorney's fees and late payment charges.
The record supports the following facts. Fastrack was a second-tier subcontractor on a public works project for which Advatex was the general contractor. Pursuant to RSA 447:16 (2002), Advatex obtained a payment bond on the project from AGLIC. The project was completed and accepted on June 15, 2000. Within ninety days, Fastrack notified Advatex and AGLIC that it had not been paid what it was owed under its contract with a first-tier subcontractor. Within one year of that notification, it filed suit in the superior court. The defendants moved to dismiss on the grounds that the notice did not comply with RSA 447:17 (2002) (amended 2004, 2005) because it was not filed with the clerk of the superior court. They further argued that, because of the defective notice, the suit was not timely filed within the one-year provision of RSA 447:18 (2002).
Fastrack prevailed on its claims in the superior court, but we reversed on the grounds that, although it had given actual notice to the defendants, Fastrack failed to comply with the statutory notice requirements of RSA 447:17 and RSA 447:18. Fastrack Crushing Servs. v. Abatement Int'l/Advatex Assocs., 149 N.H. 661, 664–67, 827 A.2d 1019 (2003). Within ninety days of that decision, but almost three and one-half years after the project's completion and acceptance, Fastrack filed a statement of claim against the bond with the superior court clerk. Shortly thereafter it filed a new petition in the superior court to enforce the claim.
Advatex and AGLIC moved to dismiss the petition on two grounds: (1) Fastrack's filings were untimely under sections 17 and 18 of RSA chapter 447; and (2) the petition itself was deficient as it did not, nor could it, "contain an allegation ... of the facts showing compliance by the claimant with the provisions of" sections 17 and 18. Fastrack conceded that the section 17 notice was filed with the court clerk after the ninety-day time period, but contended that RSA 508:10 (1997) allowed it to file a second action. The superior court agreed and denied the motion to dismiss. This appeal followed.
Although this comes to us as an appeal from a motion to dismiss, we must interpret sections 17 and 18 to determine whether the ninety-day and one-year time periods included in those sections constitute preconditions to filing a claim on a statutory bond. Interpretation of a statute is a question of law that is reviewed de novo. See Crowley v. Frazier, 147 N.H. 387, 389, 788 A.2d 263 (2001).
We address the ninety-day requirement first. Section 17 states in relevant part:
The only situation in which we have allowed a claim to go forward despite a violation of the ninety-day rule was where the statutorily required notice was given before completion and acceptance of the job. See New Eng. Culvert Co. v. Williams Constr. Co., 105 N.H. 235, 238–39, 196 A.2d 713 (1963). Fastrack has previously asked us to extend the reasoning of New England Culvert
to this case, which we declined to do. Fastrack, 149 N.H. at 666–67, 827 A.2d 1019. We stated:
[W]hereas the deficiency alleged in New England Culvert involved merely a premature delivery of proper notice, here [Fastrack] has failed to file any notice at all with the superior court clerk, the statutorily designated party. Premature notice is, if anything, more advantageous to the respondent than notice within the statutory time window. For this reason, premature notice that is "in form ... in strict compliance with the statute" is not fatal to the claim, even in cases where the underlying statute must be strictly construed. Aside from this special circumstance, however, we have not countenanced any violations of the letter of RSA 447:17.
Id. at 667, 827 A.2d 1019 (citations omitted).
Compliance with time periods such as the ninety-day provision of section 17 are generally considered conditions precedent to the right to maintain a suit against statutory bonds. See 17 Am.Jur.2d Contractors' Bonds § 113 (2004). Such a rule has been adopted by federal courts interpreting similar provisions passed by Congress. See, e.g., United States, Etc. v. J.F. White Contracting, 649 F.2d 29, 31 (1st Cir.1981) (Miller Act, 40 U.S.C. § 270b (1970) ) ; American Builders & Contractors Supply v. Bradley Const., 960 F.Supp. 145, 147 (N.D.Ill.1997) (same).
J.W. Bateson Co. v. Board of Trustees, 434 U.S. 586, 590 n. 4, 98 S.Ct. 873, 55 L.Ed.2d 50 (1978) (citation and quotations omitted); see also 5 S.G.M. Stein, Construction Law ¶ 17.03[10][e] (May 2004) ().
Fastrack makes various arguments why RSA 508:10 should allow its claim to go forward. That section sets forth the requirements in order to file a second suit:
First, Fastrack relies upon Roberts v. General Motors Corp., 140 N.H. 723, 673 A.2d 779 (1996). In that case, a plaintiff had filed various claims against a corporation. The trial court subsequently ruled against the plaintiff on summary judgment motions relating to some of his claims. At the trial court's urging, the plaintiff entered a voluntary non-suit on his remaining claims while he appealed the motion for summary judgment. Within one year of the non-suit the plaintiff filed a new writ, thus reinstating his remaining claims. Roberts, 140 N.H. at 724–25, 673 A.2d 779. In allowing the plaintiff to again...
To continue reading
Request your trial-
Gen. Insulation Co. v. Eckman Constr.
...by RSA 447:17 is a condition precedent to any claim against a statutory bond. See Fastrack Crushing Servs. v. Abatement Int'l/Advatex Assocs., 153 N.H. 284, 287, 893 A.2d 674 (2006) ( Fastrack II ). "[T]he main purpose of [this] notice requirement is to provide parties with an opportunity t......
-
General Insulation Co. v. ECKMAN CONST., 2009-102
...447:17 is a condition precedent to any claim against a statutory bond. See Fastrack Crushing Servs. v. Abatement Int'l/Advatex Assocs., 153 N.H. 284, 287, 893 A.2d 674 (2006) (Fastrack "The main purpose of this notice requirement is to provide parties with an opportunity to settle the claim......
- In re Kaplan
-
Fastrack Crushing v. Abatement Intern., 2005-132.
... 893 A.2d 674 FASTRACK CRUSHING SERVICES, ABATEMENT INTERNATIONAL/ADVATEX ASSOCIATES, INC. and another. No. 2005-132. Supreme Court of New Hampshire. Argued: October 19, 2005. Opinion Issued: February 24, 2006. Page 675 Hall, Morse, Anderson, Miller & Spinella, P.C., of Concord (Frank P. Sp......