Fernwood Realty, LLC v. Aerocision, LLC.

Decision Date21 June 2016
Docket NumberNo. 37627.,37627.
Citation166 Conn.App. 345,141 A.3d 965
CourtConnecticut Court of Appeals
PartiesFERNWOOD REALTY, LLC v. AEROCISION, LLC.

166 Conn.App. 345
141 A.3d 965

FERNWOOD REALTY, LLC
v.
AEROCISION, LLC.

No. 37627.

Appellate Court of Connecticut.

Argued Feb. 1, 2016.
Decided June 21, 2016.


141 A.3d 968

Jeffrey J. White, with whom were Kathleen E. Dion, Hartford, and, on the brief, Sorell E. Negro, for the appellant (defendant).

Hugh D. Hughes, New Haven, with whom was Stephen R. Sheehan, for the appellee (plaintiff).

DiPENTIMA, C.J., and KELLER and PRESCOTT, Js.

DiPENTIMA, C.J.

166 Conn.App. 347

The defendant, AeroCision, LLC, appeals from the judgment, rendered after a court trial, in favor of the plaintiff, Fernwood

141 A.3d 969

Realty, LLC. On appeal, the defendant claims that the court (1) erroneously concluded that it had committed statutory theft of components from an electrical distribution system because the defendant was the rightful owner of those components, and that there was no evidence to support the defendant's good faith belief that it owned those

166 Conn.App. 348

components, (2) erred in its interpretation of a commercial lease, and (3) misapplied the legal standard with respect to the defendant's constructive eviction counterclaim. We affirm the judgment of the trial court.

The following procedural history is relevant to this appeal. The plaintiff's operative amended complaint, filed on January 11, 2010, alleged, inter alia, that the defendant committed statutory theft in violation of General Statutes § 52–564 and breached its contract by defaulting on a commercial lease.1 The defendant filed an answer, special defenses, and a counterclaim. Relevant to this appeal are counts one and two of the counterclaim, which sought to recover damages for the plaintiff's alleged breach of the terms of a commercial lease, and count six, which alleged that the plaintiff constructively evicted the defendant.

A bench trial was conducted over six nonconsecutive days, beginning on June 19, 2014, and ending on July 31, 2014. After the court, Aurigemma, J., reviewed the parties' proposed statements of fact, posttrial briefs, and replies to the posttrial briefs, it issued its memorandum of decision on December 18, 2014. The court rendered judgment in favor of the plaintiff on its statutory theft and breach of contract counts, and it rendered judgment in favor of the plaintiff on all counts of the defendant's counterclaim.2

166 Conn.App. 349

The following facts, as found by the court, are relevant to this appeal. Donald F. Woods (Donald) acquired 167 Elm Street (property), a commercial manufacturing building in Old Saybrook, in 1984.3 The bus ducts,4 branch feeders,5 and transformer (electrical components) that formed the basis for the plaintiff's statutory theft claim were installed in 1990. On November 30, 2001, Donald, Jeffrey D. Woods (Jeffrey), his son, and Barbara A. Woods (Barbara), his daughter, quitclaimed their

141 A.3d 970

interest in the property6 to a three member limited liability company, the plaintiff, of which they were each a member. After the plaintiff acquired ownership of the property, it leased the property to an entity that the Woods family members owned, Pye & Hogan Machine Company, Inc. (Pye & Hogan), for $17,000 per month.

Starting in 2004, Jeffrey and Donald began negotiations to sell Pye & Hogan to Patrick G. Bromley, a Texas businessman who had “engaged in extensive business investments on behalf of a large employer and ... on his own behalf.” On May 5, 2005, the sale was finalized, and Pye & Hogan sold many of its assets, including its personal property, to Pye & Hogan, LLC, through an asset purchase agreement (agreement). On the following day, the plaintiff and Pye & Hogan, LLC, entered into a lease agreement (lease) in which Pye & Hogan, LLC, would rent the property for sixty months, ending

166 Conn.App. 350

on May 6, 2010, for the amount of $17,000 per month. Shortly after signing the lease, Pye & Hogan, LLC, changed its name to AeroCision, LLC, the defendant in this matter.

In December, 2009, the defendant notified the plaintiff that it was vacating the property. It alleged that it had been constructively evicted because of “water intrusion” and a nonfunctioning toilet. Additionally, the defendant alleged that Donald threatened its employees with violence, which left it “no choice but to vacate the property to protect its employees.”7 (Internal quotation marks omitted.) The plaintiff responded in a letter stating that the defendant was not to remove various items from the property, including the electrical components. Afterward, the plaintiff filed its original complaint on December 14, 2009. In conjunction with its original complaint, the plaintiff sought an ex parte temporary injunction ordering the defendant not to remove items that belonged to the plaintiff, namely, “fire alarm and fire suppression systems, electric [bus] ducts and electrical raceway, electrical panels, electrical conduit, mounted and attached fixtures and light fixtures, electrical boxes.” The plaintiff's ex parte temporary injunction was denied that same day.8

During the process of removing items from the property, the defendant changed the locks to the property. As a result, the plaintiff could not “[oversee] in any manner the removal of items from the property.” Subsequently, the defendant relocated the bus ducts to its

166 Conn.App. 351

new location.9 In January, 2010, the defendant provided the plaintiff with keys to the new locks. The plaintiff then hired John M. Lamb10 to inspect the electrical distribution system. Lamb discovered that the electrical components were missing. He opined that it would cost $181,300 to replace the missing

141 A.3d 971

electrical components.11 Additionally, the property was left in disrepair, and the plaintiff spent $34,614.30 to repair it.

The court found that the defendant had violated § 52–56412 and awarded the plaintiff $543,900.13 As to the plaintiff's breach of contract claim, it awarded the plaintiff $219,251.46.14 This appeal followed. Additional facts will be set forth as required.

I

The first issue raised by the defendant on appeal consists of two interrelated claims. It first claims that the court improperly concluded that it had committed statutory theft because either the court “ignored centuries of legal precedent making the distinction between ‘fixtures' and ‘trade fixtures,’ ” or the court's conclusion was “contrary to Supreme Court precedent.” In the

166 Conn.App. 352

alternative, the defendant claims that it could not have committed statutory theft because it had a good faith belief that it owned the electrical components. We address each claim in turn.

A

The following additional facts are necessary to provide context to the defendant's first claim. Section 2.1(a)(ii) of the agreement stated, in relevant part, that Pye & Hogan would “sell, assign, transfer, convey and deliver ... to [the defendant], and the [defendant would] purchase and accept ... all of the assets, properties ... including all right, title and interest of [Pye & Hogan] in ... the personal property described in Schedule 2.1(a)(ii), together with the fixtures, furnishings, furniture, equipment ... [and] property owned or leased by [Pye & Hogan], wherever located, or acquired by [Pye & Hogan] in connection with conduct of the [b]usiness ... or used by [Pye & Hogan] in connection with the conduct of the [b]usiness ....” (Emphasis in original.) Schedule 2.1(a)(ii) listed the individual machinery (e.g., CNC Toyota FH45 NM6424), the furniture and fixtures (e.g., telephone system and equipment), the data processing equipment (e.g., printers and computers), and the vehicles. Section 2.2 of the agreement set forth that certain assets were excluded from the sale. Schedule 2.2(d) of the agreement listed the excluded assets. The electrical components were not listed in either schedule.

In the agreement, Pye & Hogan made two important representations. First, it represented that it did not own the real property but, rather, leased it. The relevant portion of that provision of the agreement stated that to Pye & Hogan's “knowledge, each item of [l]eased [r]eal [p]roperty ha[d] adequate Utilities ... of a capacity and condition to serve adequately such [r]eal [p]roperty.... [T]he term

141 A.3d 972

Utilities ' means all of the

166 Conn.App. 353

following: water distribution and service facilities; sanitary sewers and associated installations ... electrical distribution and service facilities ... and all other utility lines, conduit, pipes, ducts, shafts, equipment, apparatus and facilities.” (Emphasis altered.) Second, Pye & Hogan represented that the purchased...

To continue reading

Request your trial
17 cases
  • Scholz v. Epstein
    • United States
    • Connecticut Court of Appeals
    • 16 June 2020
    ...; the burden of proof for a claim of statutory theft is the preponderance of the evidence standard. Fernwood Realty , LLC v. AeroCision , LLC , 166 Conn. App. 345, 359–60, 141 A.3d 965, cert. denied, 323 Conn. 912, 149 A.3d 981 (2016). Nevertheless, our Supreme Court in Simms determined tha......
  • Wind Colebrook S., LLC v. Town of Colebrook
    • United States
    • Connecticut Supreme Court
    • 2 August 2022
    ...to [the furnaces] in size and depth, and for the express purpose of receiving them," were fixtures); Fernwood Realty, LLC v. AeroCision, LLC , 166 Conn. App. 345, 362–63, 141 A.3d 965 (concluding that electrical components that were specifically adapted to property were fixtures), cert. den......
  • Hamann v. Carl
    • United States
    • Connecticut Court of Appeals
    • 24 March 2020
    ...the intent to deprive another of his property, an element which must be proved by the plaintiff. See Fernwood Realty, LLC v. AeroCision, LLC , 166 Conn. App. 345, 359, 141 A.3d 965, cert. denied, 323 Conn. 912, 149 A.3d 981 (2016). The plaintiff claims that once the defendant became aware t......
  • Washington v. Comm'r of Corr.
    • United States
    • Connecticut Court of Appeals
    • 21 June 2016
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT