First Solar Elec. v. Zurich Am. Ins. Co.
| Court | U.S. District Court — Middle District of Georgia |
| Writing for the Court | MARC T. TREADWELL, JUDGE UNITED STATES DISTRICT COURT |
| Docket Number | Civil Action 5:21-cv-408 (MTT) |
| Decision Date | 24 June 2024 |
| Parties | FIRST SOLAR ELECTRIC, LLC, Plaintiff, v. ZURICH AMERICAN INSURANCE COMPANY, Defendant. |
| topic | Contracts,Insurance Law,Civil Procedure |
1
FIRST SOLAR ELECTRIC, LLC, Plaintiff,
v.
ZURICH AMERICAN INSURANCE COMPANY, Defendant.
Civil Action No. 5:21-cv-408 (MTT)
United States District Court, M.D. Georgia, Macon Division
June 24, 2024
ORDER
MARC T. TREADWELL, JUDGE UNITED STATES DISTRICT COURT
Plaintiff First Solar Electric LLC (“First Solar”) filed this action seeking determination of its rights under a Master Builder Risk (“MBR”) Policy issued by defendant Zurich American Insurance Company (“Zurich”) following five rain events[1]that caused significant damage to a solar field First Solar was building. Doc. 1. Zurich moves for summary judgment arguing, among other things, that the damage to the solar field resulted from five separate occurrences of “flood” and that the $2,500,000 flood deductible applies. Doc. 88. First Solar moves for partial summary judgment arguing that the flood deductible is $100,000 or, in the alternative, that the “water damage” deductible should apply. For the reasons that follow, First Solar's motion (Doc. 90) is
GRANTED in part and DENIED in part and Zurich's motion (Doc. 88) is GRANTED in part and DENIED in part.
I. BACKGROUND[2]
A. The Twiggs Project and Flood Zone Determination
1. Preliminary pricing
In February 2018, First Solar entered into an agreement with Twiggs County Solar LLC to provide engineering, procurement, and construction services for a solar farm in Twiggs County, Georgia (the “Twiggs Project”). Docs. 88-2 ¶¶ 1-3; 100-1 ¶¶ 13; 101-10. On July 20, 2018, Hector Mestre, First Solar's insurance broker, requested “a premium indication for the Twiggs Project based on a completed Builder's Risk Insurance Information questionnaire.” Docs. 88-12; 102-1 ¶ 48; 115 ¶ 48. First Solar's questionnaire provided the project location using the coordinates latitude 32.59108, longitude -83.445652. Docs. 88-12 at 3; 102-1 ¶ 48; 115 ¶ 48. On the same day, “John Hernandez, Zurich's underwriter for the Twiggs Project, responded” to Mestre's request with “preliminary pricing.” Docs. 90-12 at 2; 102-1 ¶ 50; 115 ¶ 50. “Hernandez noted that the preliminary pricing conservatively used Flood [Level] 1,”-i.e., properties with the highest risk of flooding-but that he would need the “exact location and footprint of the project” to determine the applicable flood zone and associated deductible. Docs. 90-12 at 2; 102-1 ¶ 50; 115 ¶ 50.
On July 24, 2018, Mestre emailed Hernandez with additional information and requested “that a project certificate be issued with certain coverage limits, sublimit, and deductibles.” Docs. 90-14 at 4-5; 102-1 ¶ 51; 115 ¶ 51. While Mestre requested a $100,000 flood deductible, he asked Hernandez to “confirm which Flood deductible is to apply depending on the zone.” Docs. 90-14 at 5; 102-1 ¶ 52; 115 ¶ 52. Mestre also noted that he was requesting an Estimated Major Loss (“EML”) report to further analyze the potential risk of loss from flooding and advised that “depending on the outcome, [First Solar] may come back to [Zurich] asking to revise the flood or named storm sublimit.” Docs. 90-14 at 5; 102-1 ¶ 65; 115 ¶ 65. After comparing the Twiggs Project site map with a flood map, Hernandez determined that the project was in Flood Zone A, a subset of Flood Level 1. Docs. 90-4 at 68; 102-1 ¶ 53; 115 ¶ 53; see also Doc. 84-1 at 55:5-16, 87:13-88:3.
2. The project certificate
On July 26, 2018, Hernandez informed Mestre “that the Twiggs Project would be subject to the 2% deductible (subject to a minimum of $250,000 and maximum of $2.5 million).” Docs. 90-14 at 2-3; 102-1 ¶ 56; 115 ¶ 56. Mestre asked for confirmation on the flood zone stating, “I wasn't sure about the Flood Zone, so it is Zone A then?” Doc. 90-14 at 2. Hernandez responded, “That's correct. A significant amount of the project is located in the 100 year flood plain.” Id.
On July 27, 2018, Zurich issued a project certificate to First Solar “with a Certificate Period of August 1, 2018, to July 31, 2020.” Docs. 1-3; 102-1 ¶ 58; 115 ¶ 58. “The location of the Twiggs Project specified in the project certificate is the pair of coordinates of ‘32.59108 degrees' and ‘-83.445652 degrees,'” the same coordinates
First Solar provided in its initial questionnaire. Docs. 1-3 at 2; 88-2 ¶ 16; 88-12 at 3; 100-1 ¶ 16. The certificate included a flood deductible “of 2% (subject to a minimum of $250,000 and maximum of $2.5 million).” Docs. 1-3 at 3; 102-1 ¶ 62; 115 ¶ 62. Mestre forwarded the project certificate to First Solar's risk manager and stated:
One thing I wanted to point out is that Flood deductible which is 2% subject to the minimum $250,000 and maximum $2.5M as Zurich confirmed the majority of the project is located in high hazard flood zone
Docs. 88-62 at 2; 102-1 ¶ 61; 115 ¶ 61.
3. The EML report
On September 5, 2018, Zurich sent First Solar the EML report. Doc. 90-16 at 3 12. The EML report noted that the risk of flooding was “high”:
[T]he project site is located in FEMA Flood Zone X, unshaded, with the eastern portions of the site adjacent to Flat Creek which is in FEMA Flood Zone A. Flood Zone X, unshaded is defined by FEMA as an area outside the 0.2% annual chance (500-year) floodplain. Flood Zone A is defined by FEMA as a special flood hazard area subject to inundation by the 1% annual chance (100-year) flood.
It is assumed that First Solar will set back the solar field at a distance of at least 50 feet from Zone A as has been typical of previous projects with similar hydrology. However, without appropriate flood control measures in place, flood depths reaching 13 feet could potentially engulf some areas of the solar field adjacent to Flat Creek. The AECOM memo does not provide flood exposure abatement recommendations but does recommend further drainage studies. It is understood that a complete Drainage Study is being prepared and it is assumed that First Solar will implement measures that will minimize identifying post development flood exposures to the solar field.
Id. at 9. First Solar did not follow up with Zurich after the EML report to revise the flood deductible. See Docs. 102-1 ¶ 66; 115 ¶ 66.
B. The Rain Events
The Twiggs Project experienced five separate, heavy rain events “that occurred on or around December 13, 2019; February 5, 2020; February 13, 2020; March 3, 2020; and April 18, 2020.” Docs. 88-2 ¶¶ 31, 33; 100-1 ¶¶ 31, 33 (“It did not rain continuously at the Twiggs Project from December 13, 2019 until April 18, 2020.”). Each rain event resulted in rainwater “accumulat[ing] on and diffus[ing] over the ground,” damaging solar arrays, access roads, security fences, grading, and other civil, structural, and electrical works. Docs. 88-2 ¶¶ 39-40; 90-2 ¶ 26; 100-1 ¶¶ 39-40; 102-1 ¶ 26. Although “[t]he Twiggs Project occupied normally dry land,” photographs of the solar field show portions of the project underwater after the rain events. Docs. 102-1 ¶ 47; 115 ¶ 47; see, e.g., Docs. 88-25 at 11-22 (photographs following December 2019 and February 2020 rain events); 88-26 at 5-9 (photographs following December 2019 rain event); 88-27 at 3-4 (photographs following December 2019 rain event); 88-28 at 4-13 (photographs following February 2020 rain events); 88-29 at 4-5 (photographs following March 2020 rain event).
(IMAGE OMITTED)
Doc. 88-26 at 5; see also Docs. 90-7 at 79:5-6 (discussing Doc. 88-27 “Q: What do you see in that picture? A: I see water on the surface.”); 90-20 at 102:13-18 (“Q: Do you recall in your drive around the property after the February the 13th, 2020 rain event that the modules in block two, array four were under water? ... A: Yes, I believe so.”). After each rain event First Solar performed necessary remediation, including “pump[ing] out” standing water, and then resumed working on the project. Docs. 88-2 ¶¶ 41, 44, 47; 100-1 ¶¶ 41, 44, 47. “At the time of the first rain event on December 13, 2019, the ‘total project value in place' was, at minimum, $141,900,000.00.” Docs. 102-1 ¶ 100; 115 ¶ 100.
“First Solar provided notice to Zurich of the five rain events on December 20, 2019, February 19, 2020 (both February 2020 rain events), March 18, 2020, and April 22, 2020.”[3] Docs. 88-2 ¶ 32; 100-1 ¶ 32. Zurich adjustor Scott Klaben was assigned to handle all of First Solar's claims. Docs. 82-2 ¶ 28; 103-1 ¶ 28.
C. Claims Investigation and Communications
On February 7, 2020, Klaben visited the Twiggs Project to inspect the damage. See Docs. 88-2 ¶ 71; 86-1 at 201; 90-20 at 88:20-22, 89:9-12; 100-1 ¶ 71. John Shaw, First Solar's insurance broker, testified that he had “several” conversations with Klaben during which Klaben stated that First Solar's claims “were going to be viewed as water damage claims.”[4]Doc. 90-22 at 50:24-51:24, 52:25-53:3. Consistent with these
representations, Klaben, on February 8, 2020, noted in First Solar's claim file that “[t]his loss if [sic, presumably] for water damage to the roads and washed out areas around the solar paneling support array for this Builder's Risk claim” (Doc. 86-1 at 201); on February 20, 2020, Klaben recorded the February 5 loss in his claim notes, answering “No” to the question “Was the loss caused by flood?” (Doc. 86-2 at 4); and in a February 21, 2020 email to a Zurich claims manager Klaben noted that “[e]ach claim carrie[d] a $100K deductible.” Doc. 90-28 at 3.
On June 10, 2020, Klaben approved a “$200K advance [payment] request” for the first three rain events, noting that “claimed damages per Insured = $577K and so less $100K deductible we noted/in agreement with insured for $200K advance request.” Docs. 88-2 ¶ 69; 86-1 at 196; 100-1 ¶ 69. “On June 11,2020, Zurich issued three checks each for $200,000, representing advance payments for the rain events of December 13, 2019, and February 5, 2020, and February 13, 2020.” Docs. 90-2 ¶ 29; 102-1 ¶ 29.
On August 4, 2020, Klaben sent First Solar “a status report and...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting