Flynn v. W. P. Harlin Const. Co.

Decision Date17 April 1973
Docket NumberNo. 12855,12855
Partiesd 327 L. W. FLYNN, dba L. W. Flynn Construction Company, Plaintiff and Appellant, v. W. P. HARLIN CONSTRUCTION COMPANY et al., Defendants and Respondents.
CourtUtah Supreme Court

James A. McIntosh, Salt Lake City, for plaintiff-appellant.

Elliott Lee Pratt of Clyde, Mecham & Pratt, Salt Lake City, for defendants-respondents.

CROCKETT, Justice:

L. W. Flynn who had the subcontract for cement work installations in building the Biological Science Building at the University of Utah sued Harlin Construction Co. and Morrin and Son Co., general contractors, alleging that defendants had: (1) wrongfully terminated his subcontract, which (2) caused him to lose the benefits therefrom, and (3) converted certain of his equipment and materials. After five days of trial to a jury of the usual eight members, one of them asked to be excused for personal reasons. Upon stipulation of the parties the juror was excused and the trial continued with seven jurors as permitted by our law. 1 The issues were submitted on special verdicts upon which the jury found in favor of the plaintiff on each of the propositions just stated, and assessed damages of $20,000 on (2) above, and $5,000 on (3) above.

Subsequently, the trial judge revived consideration of defendants' motions for directed verdicts on those issues. He denied the motions and refused to overturn the jury's findings as to (1), the finding of wrongful termination of the subcontract and as to (3), the $5,000 award for conversion of equipment and materials. However, as to (2), the assessment of $20,000 damages for the breach, he granted defendant's motion for a directed verdict, indicating that in his opinion there was insufficient evidence to sustain that finding.

Plaintiff appeals, seeking restoration of the jury's verdict on that issue. Defendant's cross-appeal, asking elimination of the $5,000 damage for conversion of plaintiff's property.

The desirability of brevity in the opinions of this court, which are published extensively and expensively, require that the evidence presented in eight days of trial be only in summary; and because the trial court took the issue of concern here from the jury, we survey the evidence in the light favorable to the jury's verdict. 2

The subcontract by which the plaintiff Flynn undertook to do the cement work in the Biological Science Building was executed on November 16, 1965. Stated in generality, he was to set the forms for the second and third floors and the roof, and to pour and install the cement work for all of the floors of the building, including those above mentioned and the first floor and the basement. Because of certain delays Flynn's work did not get under way until February, 1966. Thereafter there were other delays occasioned by bad weather and other causes, including lack of coordination in sequence of work of subcontractors. But the jury findings indicate that Harlin was not justified in blaming Flynn. Nevertheless, on May 13, 1966, defendants gave Flynn notice that his subcontract was terminated. Flynn left the job, but his workmen continued on, becoming employees of the defendants, and the project progressed to completion, using materials and supplies that had been brought onto the job by Flynn and his crews.

There is no disagreement that the measure of damages for breach of a construction contract which prevents its performance is the amount the contractor would have received for finishing the project, less whatever would have been the reasonable expenses in doing so. 3 The controversy is over two basic issues of fact, the determination of which are essential to the proper application of that rule.

The first is: what portion of the work had been done by May 13 when plaintiff was ousted from the job.

The second is: what would have been plaintiff's cost to complete it.

The amount set in the subcontract originally was $86,000; and there were agreed change orders of $2377.44, making a total of $88,377.44. It is not disputed that on the break-off date of May 13 Flynn had expended about $20,000 for materials and about $21,000 for labor costs, a total of about $41,000, thus just under half of the total contract price. Defendants insist that on that date Flynn had completed much less than one-half of the work. Their brief stated:

Flynn under any concept of the evidence still had two thirds of the forming work yet to do and over half of the pouring work to do.

From this they argue that Flynn having already expended $41,000, it would be necessary for him to expend greatly in excess of the $88,000 contract price to finish the job. Defendants presented evidence that it in fact did cost them more than the contract price to complete it.

As opposed to this the plaintiff points to his own evidence that he had completed substantially one-half of the actual construction and had incurred more than half of the expense. Corroborative of this is the testimony of Austin Scott, who had served as foreman for Flynn, and who stayed on as foreman for defendants. His estimate was about 40 per cent complete on that date. Plaintiff argues that even if Scott's 40 per cent estimate be accepted, there is nevertheless adequate basis in the evidence to support the verdict. He reasons thus: that the $20,000 expended for materials represented practically all that would be needed to complete the job; and that the $21,000 expended for labor was substantially half of the total labor cost that would be required. He avers that a substantial amount of the labor cost represented the expenses of getting all of the materials to the job, and of getting them conditioned and organized for the actual construction, and that with that phase of the work completed, and better plans for coordination and progress of the work, he could have completed the entire job for about the same amount on labor expense, that is, another $21,000, which added to the $41,000 already expended, would make a total of $62,000, which would leave him a net of about $26,000 on the contract.

Plaintiff further suggests that the fact that the defendants may have expended more than the original subcontract called for does not compel the conclusion that the plaintiff Flynn could not have done it for less. Bearing on this is other testimony of the foreman, Austin Scott: That after the defendants took over they hired substantially more personnel, in some instances as many as two or three times as many, as could be efficiently working together in doing the job.

An important aspect of the dispute as to the amount of the project that had been completed on the break-off date, May 13, appears to focus more specifically upon the extent that Flynn had progressed in his work on the third floor, which would have been somewhere about the middle of the project.

It is helpful on the factual problem just stated to refer to parts of a somewhat extended analysis of the evidence by the trial judge in connection with his ruling on the directed verdict after the trial. With respect to the third floor he stated that he did not think that there was 'any evidence of any work having been done (by Flynn) on the third floor . . . (and further) . . . in my opinion, Mr. Flynn is entitled to absolutely no credit in computations for anything done on the third floor.' However, the plaintiff rejoins by pointing out from the now transcribed record (of which the trial judge did not then have the benefit) that both the plaintiff and Mr. Austin Scott had testified that substantial work had been done on the third floor; and further, that while Mr. Harlin himself had initially stated that he thought no work had been done on the third floor, after examining some photographs taken on that date, he admitted that some of Flynn's work had been done, but that he had no way of telling exactly how much.

Having an important bearing on both of the critical issues as stated above: the amount of work already done, and the cost of completing the project, is an exhibit referred to as P-93. It consists of figures placed on the board by Mr. Harlin under examination by plaintiff's counsel. When it was offered in evidence defendants' counsel objected on the ground that there was no basis in the evidence for the figures used. After discussion, the objection was overruled and it was received.

It is pertinent to examine the comments the trial judge made regarding that exhibit after the trial when he changed his ruling on the directed verdict:

Now as to the loss of profits that of course is the big question. I think it's readily apparent that the Jury was undoubtedly persuaded by the 32 cents computation which plaintiff's counsel had Mr. Flynn (this was actually Mr. Harlin preparing exhibit P-93) write out for the Jury on the board. In connection with that computation, a profit of $23,000 was alleged. The jury brought in a verdict of $20,000. That...

To continue reading

Request your trial
7 cases
  • State v. Moosman, 870251
    • United States
    • Utah Supreme Court
    • 1 Junio 1990
    ...Productions, Inc. v. Robinson, 604 P.2d 913 (Utah 1979); State v. James, 30 Utah 2d 32, 512 P.2d 1031 (1973); Flynn v. W.P. Harlin Constr. Co., 29 Utah 2d 327, 509 P.2d 356 (1973).7 Kennedy v. Morris, 639 P.2d 142, 143 (Utah 1981) (per curiam); State v. Yeck, 566 P.2d 1248, 1249 (Utah 1977)......
  • Oldenburg v. Clark
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • 3 Enero 1974
    ...Cir. 1972). The state-federal point is not critical in this case in view of the holdings of the Utah court in Flynn v. W. P. Harlin Const. Co., 29 Utah 2d 327, 509 P.2d 356 (1973); Hindmarsh v. O. P. Skaggs Foodliner, 21 Utah 2d 413, 416 P.2d 410 (1968). 2 Holmes v. Wack, 464 F.2d 86 (10th ......
  • U.S.A. United Staffing Alliance v. Wcf
    • United States
    • Utah Court of Appeals
    • 18 Junio 2009
    ...is so plain that there really is no conflict in the evidence upon which reasonable minds could differ." Flynn v. W.P. Harlin Constr. Co., 29 Utah 2d 327, 509 P.2d 356, 361 (1973). Such is the case here. Even viewing the evidence in a light most favorable to USA, as we must, we conclude that......
  • Mel Hardman Productions, Inc. v. Robinson
    • United States
    • Utah Supreme Court
    • 7 Diciembre 1979
    ...& Radio Co. v. Flint, 122 Utah 298, 249 P.2d 826 (1952); Roche v. Zee, 1 Utah 2d 193, 264 P.2d 855 (1953); Flynn v. W. P. Harlin Const. Co., 29 Utah 2d 327, 509 P.2d 356 (1973).5 Koer v. Mayfair Markets, 19 Utah 2d 339, 431 P.2d 566 (1967); Anderson v. Gribble, 30 Utah 2d 68, 513 P.2d 432 (......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT