FMA Financial Corp. v. Hansen Dairy, Inc.

Decision Date21 August 1980
Docket NumberNo. 16528,16528
Citation617 P.2d 327
PartiesFMA FINANCIAL CORPORATION, Plaintiff and Appellant, v. HANSEN DAIRY, INC.; Steven L. Hansen; Larell Hansen; Muriel O. Hansen; and Val Jean Hansen, dba Hansen Dairy, a partnership; and Federated Dairy Farms, a Utah cooperative association, Defendants and Respondents, v. James M. LEVIE and LeVoy Christensen, Third-Party Defendants and Respondents.
CourtUtah Supreme Court

Milo Marsden, Jr., and Grant A. Hurst of Marsden & Liljenquist, Salt Lake City, for plaintiff and appellant.

Gayle Dean Hunt, Salt Lake City, for defendants and respondents.

James Levie, pro se, for third-party defendants and respondents.

CROCKETT, Chief Justice:

Plaintiff FMA Financial Corporation, a leasing company, brought this action seeking damages for an alleged breach of a written agreement to lease a used corn silo and other farm equipment to defendants-lessees Hansen Dairy, Inc. The defendants asserted the defense that the silo was not installed on their property in time for use as agreed; and they counterclaimed for the rentals they had already paid. In addition, they filed a cross-complaint against James M. Levie who, in order to finance the transaction, had conveyed the subject property to the plaintiff, and who was then to deliver the equipment to the defendants and reconstruct the silo on their farm.

Upon a plenary trial of the issues, the court found in accordance with the defendant's contention that there had been "a complete failure of consideration" as to the defendants, and that they were entitled to recover $19,342.80 from the plaintiff as reimbursement for lease payments, minus $5,000 for two feed wagons which they retained. However, the court further found that the plaintiff was entitled to recover $36,000 from Mr. Levie, representing what had been paid for the silo and the equipment, less certain sums credited to him, described below. 1

The plaintiff appeals, contending that the court erred in finding a failure of consideration because: (1) The lease agreement did not provide when the construction of the silo was to be completed; and (2) The defendants had allegedly prevented Mr. Levie from completing the construction. The plaintiff also urges that the defendants should be estopped to claim there was a failure of consideration because, knowing that the silo construction was incomplete, they signed an acceptance notice, subsequently delivered by Mr. Levie to the plaintiff, which provided that the "items received by us ... were and are in good order and condition and acceptable to us as delivered or installed."

The defendants owned and operated a dairy farm near Centerfield, Utah. They had had prior dealings with Mr. Levie in leasing some grain silos obtained by him, but financed by another leasing company. Pursuant to negotiations, on June 25, 1973, the defendants agreed with him to lease two feed wagons, a blower, and a used silo, which Mr. Levie had located in Nevada. Their preliminary agreement included that the defendants would pay $835 per month for five years for the stated equipment, which Mr. Levie would transport and install on the defendants' farm. However, when the defendants requested a lower monthly payment and a longer lease term, Mr. Levie contacted the plaintiff, which indicated a willingness to finance the transaction. Pursuant to negotiations between Mr. Levie and Mr. Scott Mayme, an official acting for the plaintiff, it was arranged that the plaintiff would purchase, pay for, and take title to the above-described equipment from Mr. Levie, and then lease it to the defendants who would make the payments to the plaintiff.

This case is in that class where there is considerable difference between the versions of what happened as to essential occurrences. In accordance with the standard rule of review, we assume that the trial court believed the testimony which supports his findings. 2 He found and concluded that the plaintiff gave a lease contract to Mr. Levie, which included the acceptance notice referred to above, which he was to deliver to the defendants, obtain signatures thereon and return the documents to the plaintiff. The court also found that the defendants executed the documents on August 1, 1973, on the condition that the silo would "be erected and operational by corn harvest time," i. e., about the end of the first week in September, 1973. The contract required the defendants to make 84 payments of $748.64 each, with the first two installments to be paid as an initial commitment fee.

Mr. Levie returned the signed documents to the plaintiff's office and, on August 7, 1973, he issued a sales invoice to the plaintiff and received a $36,000 check for the equipment. Although he subsequently delivered the two wagons and the parts for the silo to the defendants' farm, and later installed a concrete footing, Mr. Levie never completed the construction of the silo because it had become obvious that the requirement that the silo be installed and operational by corn harvest time could not be satisfied.

Included in the findings and judgment is that the parties agreed that the defendants would retain the two feed wagons, valued at $2,500 each. Some of the parts for the silo, including those which had been delivered to the defendants' farm, were sold for $5,000 and those proceeds were delivered to the plaintiff. The parts which were not sold and were left at the defendants' farm, or in Mr. Levie's possession, could be retrieved by the plaintiff and Mr. Levie given credit for their value.

In its attack upon the finding of failure of consideration for the lease, plaintiff argues that the agreement is "integrated, clear, definite, and unambiguous" and the defendants' attempt to incorporate the requirement that the silo was to be installed by corn harvest time into the agreement violates the parol evidence rule.

The standard parol evidence rule is that extraneous evidence may not be used to contradict or vary the terms of a written instrument. 3 That rule serves a useful purpose in appropriate circumstances in safeguarding the integrity of such documents. However, it should not be applied with any such unreasoning rigidity as to defeat what may be shown to be the actual purpose and intent of the parties, but should be applied in the light of reason to serve the ends of justice. 4 It does not preclude proof of agreements as to collateral matters relating to the contract or its performance, so long as they are not inconsistent with nor in repudiation of the terms of the written agreement. Nor does it prevent proof that a party did not perform an obligation which it was understood and agreed by the parties was a condition precedent to the contract becoming effective. 5 That applies to the circumstances here, where the court found that the parties had an understanding and agreement that in order for the silo to be useful to the defendants it was to be installed by harvest time, and that this was an essential to the contract becoming effective. Whether there was such a separate agreement, not in contradiction of the written document, is for the trier of fact to determine. 6

Significantly, the court found that there was no contact directly between the plaintiff and the defendants, "but all of the dealings were done by or through the Levies." Thus, a key proposition to be borne in mind as bearing on all of the issues in this case is that Mr. Mayme, acting for the plaintiff, entrusted the handling of its interests in this transaction to Mr. Levie. Consequently, his knowledge in that regard should be imputed to it. 7

There was ample basis in the testimony of the defendants Stephen L. Hansen, Val Jean Hansen and Larell Hansen upon which the trial court could make its findings that the lease was negotiated and executed upon the understanding that the defendants were to make the lease payments on the condition that the silo would be installed and operational by corn harvest time. Accor...

To continue reading

Request your trial
13 cases
  • Medianews Group, Inc. v. McCarthey
    • United States
    • U.S. District Court — District of Utah
    • April 24, 2006
    ...the collateral matters "are not inconsistent with nor in repudiation of the terms of the written agreement." FMA Fin. Corp. v. Hansen Dairy, Inc., 617 P.2d 327, 329 (Utah 1980); see also, e.g., Dayvault v. Baruch Oil Corp., 231 F.2d 413, 414 (10th Cir.1956) (noting the "well known policy ru......
  • Myrah v. Campbell
    • United States
    • Utah Court of Appeals
    • May 17, 2007
    ...rule is that extraneous evidence may not be used to contradict or vary the terms of a written instrument." FMA Fin. Corp. v. Hansen Dairy, Inc., 617 P.2d 327, 329 (Utah 1980). The Renewal Agreement stated that the property was in a state of good repair and clean condition and that Tenants h......
  • SCM Land Co. v. Watkins & Faber
    • United States
    • Utah Supreme Court
    • December 26, 1986
    ...obligations under the written lease. Faber relies on Nielsen v. MFT Leasing, 656 P.2d 454 (Utah 1982), and FMA Financial Corp. v. Hansen Dairy, Inc., 617 P.2d 327 (Utah 1980), for the proposition that there was a failure of consideration justifying rescission in this case. Both FMA Financia......
  • Macris v. Sculptured Software, Inc.
    • United States
    • Utah Supreme Court
    • May 25, 2001
    ...to his or her principal, for it is presumed that such knowledge will be disclosed to the principal. See FMA Fin. Corp. v. Hansen Dairy, Inc., 617 P.2d 327, 329-30 (Utah 1980) (holding that when all transactions are accomplished through an agent, the agent's knowledge of the transaction is i......
  • Request a trial to view additional results
1 books & journal articles
  • Article the Parol Evidence Rule in Utah: a Brief Survey
    • United States
    • Utah State Bar Utah Bar Journal No. 29-2, April 2016
    • Invalid date
    ...preclude evidence of the failure of a condition precedent to the contract becoming effective. See FMA Fin. Corp. v. Hansen Dairy, Inc., 617 P.2d 327, 329 (Utah 1980). "Admittingparol evidence in such circumstances avoids the judicial enforcement of a writing that appears to be a binding int......