Foley Co. v. U.S., 93-5084

Decision Date04 November 1993
Docket NumberNo. 93-5084,93-5084
Parties39 Cont.Cas.Fed. (CCH) P 76,590 FOLEY COMPANY, Plaintiff-Appellee, v. The UNITED STATES, Defendant-Appellant.
CourtU.S. Court of Appeals — Federal Circuit

Seth Price, Shapiro, Fussell, Wedge & Smotherman, Atlanta, GA, argued for plaintiff-appellee. With him on the brief was Connie H. Buffington.

Kirk T. Manhardt, Atty., Commercial Litigation Branch, Dept. of Justice, Washington, DC, argued for defendant-appellant. With him on the brief were Stuart E. Schiffer, Acting Asst. Atty. Gen. and David M. Cohen, Director. Also on the brief were Frank Carr, Saul Perloff and Jerusha White, Dept. of Army Corps of Engineers, of counsel.

Before ARCHER, LOURIE and CLEVENGER, Circuit Judges.

CLEVENGER, Circuit Judge.

The United States appeals the December 16, 1992 judgment of the United States Court of Federal Claims on cross-motions for partial summary judgment that denied the Government's request for an equitable adjustment pursuant to the Variation in Estimated Quantity (VEQ) clause, 48 C.F.R. Sec. 52.212-11 (1992), contained in a contract to close hazardous waste lagoons and awarded Foley Company $212,517.63 plus interest for the removal of sludge in excess of 115 percent of the estimated contract quantity. Foley Co. v. United States, 26 Cl.Ct. 936 (1992). * In ruling on the motions, the Court of Federal Claims, rejecting the holding in Burnett Construction Co. v. United States, 26 Cl.Ct. 296 (1992), held that the grant of an equitable adjustment under the VEQ clause requires proof of an actual increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. We affirm.

I

On September 28, 1988, Foley contracted with the Government to close four hazardous waste lagoons at the Lake City Army Ammunition Plant in Independence, Missouri. Foley completely discharged its contractual obligations to reduce the lead content of waste water contained in the lagoons to an appropriate level, to dispose of the treated waste water, to remove and dispose of sludge and contaminated soil, and lastly, to fill, grade and seed the lagoons. This appeal solely concerns the aspect of sludge removal and disposal under the contract.

Foley agreed to remove and dispose of the sludge at the unit price of $308 per ton, based on an estimated quantity of 6,600 tons. In May 1989, Foley advised the Government that the quantity of sludge requiring removal would exceed the estimated quantity. Instructed by the Government to continue its sludge removal, Foley ultimately removed 23,937.51 tons of sludge.

The Government paid Foley $2,337,720 for the first 7590 tons of sludge removed, representing payment of the contract unit price of $308 per ton for 115 percent of the estimated quantity under the contract. As for the remaining 16,347.51 tons of sludge removed, the Government paid Foley $4,822,515.45, which represented a unit price of only $295 per ton. On February 22, 1991, Foley submitted a properly certified claim to the contracting officer (CO), requesting $212,517.63, the differential between the $295 unit price paid and the $308 contract unit price for the excess 16,347.51 tons of sludge removed.

On March 21, 1991, the CO issued a final decision denying Foley's claim. The CO further determined that the contract's VEQ clause entitled Foley to only $3,780,685, which represented Foley's actual costs plus a reasonable profit for the removal of sludge in excess of 115 percent of the estimated contract quantity. Having already paid Foley $4,822,515.45, the CO demanded a refund of $773,316.45.

On July 23, 1991, Foley filed a complaint with the Court of Federal Claims, asserting entitlement to the full contract unit price of $308 for each ton of sludge removed in excess of 115 percent of the estimated contract quantity. On cross-motions for summary judgment, the Court of Federal Claims held that absent proof that Foley experienced cost savings due solely to the remaining 16,347.51 tons of sludge removed, the Government was not entitled to an equitable adjustment under the VEQ clause. The Government subsequently stipulated that it could not demonstrate that Foley's unit cost for sludge removal decreased solely as a result of the amount removed in excess of 115 percent of the estimated contract quantity. Consequently the Court of Federal Claims entered an order holding that the Government owed Foley $212,517.63 plus interest.

II

This court reviews judgments of the Court of Federal Claims to determine whether they are premised on clearly erroneous factual determinations or otherwise incorrect as a matter of law. Transamerica Ins. Corp. v. United States, 973 F.2d 1572, 1576 (Fed.Cir.1992). As a matter of law, the grant of summary judgment by the Court of Federal Claims receives de novo review by this court. Confederated Tribes of Colville Reservation v. United States, 964 F.2d 1102, 1107 (Fed.Cir.1992). The interpretation of regulations which are incorporated into government contracts is a question of law also requiring de novo review. Ingalls Shipbuilding, Inc. v. O'Keefe, 986 F.2d 486, 488 (Fed.Cir.1993).

III

The Government argues that the contract's VEQ clause entitles it to an equitable downward adjustment from the contract unit price for the sludge removed in excess of 115 percent of the estimated contract quantity. The VEQ clause provides, in pertinent part:

If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity.

48 C.F.R. Sec. 52.212-11 (1992). Neither party contends that the language of the VEQ clause is ambiguous. The Government, however, contests the Court of Federal Claims' construction of the phrase "costs due solely to the variation" to limit the availability of equitable adjustments to the circumstances where an increase or decrease in costs occurs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. In the Government's view, the second sentence of the VEQ clause instead should have been interpreted simply to inform a CO of which quantities' costs must be considered in making an equitable adjustment.

Contract interpretation begins with the plain language of the agreement. Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed.Cir.1991). The VEQ clause requires an equitable adjustment to be based upon any increase or decrease in costs. The Government's preferred construction, however, requires the establishment of a new unit price for the overrun amounts by an equitable adjustment of the contractor's unit profit, even where the contractor's unit costs remained constant. This interpretation clearly contravenes the plain meaning of the VEQ clause. The express language of the VEQ clause precludes an equitable adjustment based on anything other than the contractor's costs.

In light of the Government's concession that the terms of the VEQ clause are not ambiguous, we need not address the drafters' intent in promulgating the VEQ clause. Even if we were to examine such legislative history, however, we would reject the Government's contention. The 1968 revision to the VEQ clause added the sentence "[t]he equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity." The Department of Defense issued explanatory notes with regard to the revision stating that the revision was "to make more explicit that only the quantities which exceed 115%, or are less than 85% of the estimated quantities are subject to adjustment under this clause." Department of Defense, Armed Servs. Procurement Regs. 1963 Ed. Revision No. 27 III (Apr. 15, 1968). While the notes support the Government's position of a legislative intent to inform a CO of which quantities' costs to consider in making an equitable adjustment, nothing in the notes suggests that the...

To continue reading

Request your trial
59 cases
  • Dobyns v. United States
    • United States
    • U.S. Claims Court
    • September 16, 2014
    ...Fed. Bank, FSB v. United States, 323 F.3d 1035, 1038 (Fed. Cir. 2003); see also Bell/Heery, 739 F.3d at 1331; Foley Co. v. United States, 11 F.3d 1032, 1034 (Fed. Cir. 1993). When interpreting a contract, "if the 'provisions are clear and unambiguous, they must be given their plain and ordi......
  • Stathis v. United States
    • United States
    • U.S. Claims Court
    • April 1, 2015
    ...reh'g denied (Fed. Cir. 2009); Barron Bancshares, Inc. v. United States, 366 F.3d 1360, 1375 (Fed. Cir. 2004); Foley Co. v. United States, 11 F.3d 1032, 1034 (Fed. Cir. 1993); Eden Isle Marina, Inc. v. United States, 113 Fed. Cl. at 483-84; Bell/Heery v. United States, 106 Fed. Cl. 300, 309......
  • Bruhn NewTech v. United States, 16-783C
    • United States
    • U.S. Claims Court
    • August 23, 2019
    ...reh'g denied (Fed. Cir. 2009); Barron Bancshares, Inc. v. United States, 366 F.3d 1360, 1375 (Fed. Cir. 2004); Foley Co. v. United States, 11 F.3d 1032, 1034 (Fed. Cir. 1993); Nw. Title Agency, Inc. v. United States, 126 Fed. Cl. 55, 57-58 (2016) (citing Foley Co. v. United States, 11 F.3d ......
  • Land of Lincoln Mut. Health Ins. Co. v. United States
    • United States
    • U.S. Claims Court
    • November 10, 2016
    ...language of the agreement. Coast Fed. Bank, FSB v. United States, 323 F.3d 1035, 1038 (Fed. Cir. 2003) (citing Foley Co. v. United States, 11 F.3d 1032, 1034 (Fed. Cir. 1993)). When the terms of the agreement are "clear and unambiguous, they must be given their plain and ordinary meaning." ......
  • Request a trial to view additional results
2 books & journal articles
  • Pricing Construction Contracts
    • United States
    • ABA Archive Editions Library Construction Law
    • June 22, 2009
    ...the actual cost of purchase (and related bulk-quantity discounts), variations in 17. 48 C.F.R. § 52.212–11 (1992). 18. Foley Co. v. U.S., 11 F.3d 1032, 1034 (Fed. Cir. 1993). 19. See Chapter 16. 234 C O N S T R U C T I O N L A W estimated quantities of construction elements apart from goods......
  • Pricing Construction Contracts
    • United States
    • ABA Archive Editions Library Construction Law
    • January 1, 2009
    ...the actual cost of purchase (and related bulk-quantity discounts), variations in 17. 48 C.F.R. § 52.212–11 (1992). 18. Foley Co. v. U.S., 11 F.3d 1032, 1034 (Fed. Cir. 1993). 19. See Chapter 16. 234 C O N S T R U C T I O N L A W estimated quantities of construction elements apart from goods......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT