Forte Hotels, Inc. v. Kansas City Power & Light Co., WD

Decision Date24 October 1995
Docket NumberNo. WD,WD
Citation913 S.W.2d 803
PartiesFORTE HOTELS, INC. and Forte Hotels (UK) Ltd., Appellants, v. KANSAS CITY POWER & LIGHT COMPANY, Respondent. 50364.
CourtMissouri Court of Appeals

Mark V. Bodine, Wallace, Saunders, Austin, Brown and Enochs, Kansas City, for appellants.

Robert Gingrich, Kansas City, for respondent.

Before FENNER, C.J., and KENNEDY and SMART, JJ.

PER CURIAM:

Forte Hotels, Inc., and Forte Hotels (UK) Ltd. (collectively referred to as "Forte") appeal from a summary judgment in their negligence and breach of contract action against the Kansas City Power & Light Company ("KCP & L"). Forte contends that the summary judgment was improper because KCP & L's tariffs or rules for electric service do not exempt the utility from liability for its own negligence, and because KCP & L's motion for summary judgment did not address Forte's action in tort.

The summary judgment is reversed and the cause remanded.

At approximately 4:40 a.m. on March 20, 1991, one of KCP & L's underground electrical cables failed at an office building in Mission, Kansas, causing a power outage inside the building. When one of KCP & L's linemen attempted to unbolt the failed cable from the bushing where it was bolted to the transformer, the transformer's ceramic electrical bushing broke. As a result, poly-chlorinated biphenyl (PCB) oil flowed out of the transformer and onto and under the concrete pavement inside the office building's underground garage. Because of the broken electrical bushing, the transformer had to be replaced, and the PCB oil spill had to be cleaned up to meet applicable EPA standards. Electrical service was restored at approximately 10:50 p.m. on March 20, 1991, after an outage of approximately eighteen hours.

Forte maintained a telephone reservation center inside the office building where the power outage occurred. Due to the outage, Forte was unable to operate its reservations center on March 20, 1991, and Forte subsequently filed a negligence and breach of contract action against KCP & L, seeking lost revenue, lost labor and other damages. In its petition, Forte alleged that the termination of electrical power to the office building was due to the negligence of KCP & L, and that KCP & L was also negligent in failing to make timely and efficient repairs. Forte also alleged that KCP & L breached the obligation of its service contract with either Forte or the owner of the building, and that, in the latter case, Forte was a third-party beneficiary of the contract.

KCP & L then filed a motion for summary judgment which asserted that, regardless of whether Forte's suit was treated as a tort or a contract action, the ultimate origin of the suit was in the breach of a contractual obligation. Referring to the contractual origin of the case at bar, KCP & L argued that its service contract with its customers incorporated KCP & L's tariffs or rules for electric service, and that those tariffs preclude KCP & L's liability for the type of service interruption experienced by Forte. Specifically, KCP & L cited the following rules or tariffs as barring recovery:

7.06 CONTINUITY OF SERVICE:

The Company will use reasonable diligence to supply continuous electric service to the Customer but does not guarantee the supply of electric service against irregularities or interruptions. The Company shall not be considered in default of its service agreement with the Customer and shall not otherwise be liable for any damages occasioned by any irregularity or interruption of electric service.

7.12 LIABILITY OF COMPANY

The Company shall not be considered in default of its service agreement and shall not otherwise be liable on account of any failure by the Company to perform any obligation if prevented from fulfilling such obligation by reason of any delivery delay, breakdown, or failure of or damage to facilities, an electric disturbance originating on or transmitted through electric systems with which the Company's system is interconnected, act of God or public enemy, strike, or other labor disturbance involving the Company or the Customer, civil, military or governmental authority, or any cause beyond the control of the Company.

The trial court sustained KCP & L's motion for summary judgment and Forte appeals.

In its first point on appeal, Forte claims that Rules 7.06 and 7.12 do not, as a matter of law, exempt KCP & L from liability under the circumstances in the case at bar, and, therefore, the trial court erred in granting a summary judgment in favor of KCP & L. Forte argues that the occurrences enumerated in Rule 7.12 indicate an intent that KCP & L be exempted from liability only when it is prevented from fulfilling its obligations by acts outside its control. Forte also argues that Rule 7.06 does not exempt KCP & L from liability because that rule only applies to acts or circumstances which cause the initial interruption in service, and Forte is claiming that KCP & L is liable for prolonging the initial interruption by various acts of negligence.

The parties agree that Kansas substantive law is applicable, so a choice of law analysis will not be undertaken. With regard to procedural issues, however, the law governing is that of the forum state, Missouri. Ernst v. Ford Motor Co., 813 S.W.2d 910, 921 (Mo.App.1991).

Pursuant to Missouri law, the party moving for summary judgment has the burden of establishing, on the basis of facts as to which there is no genuine dispute, a right to judgment as a matter of law. ITT Commercial Finance Corp. v. Mid-Am. Marine Supply Corp., 854 S.W.2d 371, 376 (Mo. banc 1993). "The key to summary judgment is the undisputed right to judgment as a matter of law; not simply the absence of a fact question." Id. at 380. This court's review of a summary judgment is essentially de novo. Callaway Hosp. Ass'n v. Dept. of Corr., 885 S.W.2d 740, 743 (Mo.App.1994).

KCP & L is entitled to summary judgment as a matter of law if its tariff provisions, Rules 7.06 and 7.12, effectively exempt KCP & L from liability for the interruption of service to Forte. Clearly, there is language in the tariff provisions which attempts to limit KCP & L's liability. Forte argues on appeal that the language of the tariff does not, in fact, limit KCP & L's liability under the circumstances of this case. It is not necessary to consider how the terms of the tariff should be interpreted, since Forte's first point can be disposed by considering whether the tariff provisions limiting KCP & L's liability are valid and enforceable in light of the law of Kansas.

Under Kansas law, public utilities are required to file with the State Corporation Commission tariffs which govern the terms and conditions of the relationship between the utility and its customers. Southwestern Bell Tel. Co. v. State Corp. Com'n, 233 Kan. 375, 664 P.2d 798, 800 (1983). A tariff so filed is more than a mere contract; it is the law. Shehi v. Southwestern Bell Telephone Company, 382 F.2d 627, 629 n. 2 (10th Cir.1967). In ruling on the enforceability of the exculpatory language in Rules 7.06 and 7.12, such provisions must be examined in light of Kansas Supreme Court decisions which find unreasonable limitations of a public utility's liability to be unenforceable.

A provision attempting to limit the liability of a public utility was first subjected to a reasonableness rule in Shawnee Milling Co....

To continue reading

Request your trial
5 cases
  • HL & P v. Auchan USA, Inc.
    • United States
    • Texas Supreme Court
    • 10 September 1998
    ...(holding that no Kansas statute gives the Commission authority to limit a utility's liability); Forte Hotels, Inc. v. Kansas City Power & Light Co., 913 S.W.2d 803, 804-06 (Mo. Ct. App. 1995) (applying Kansas law) (holding that the tariff's limitation of liability is unreasonable and unenfo......
  • Szeto v. Ariz. Pub. Serv. Co.
    • United States
    • Arizona Court of Appeals
    • 30 November 2021
    ...("[A]ll the reasons for disfavoring [exculpatory] clauses in contracts also apply to tariffs."); Forte Hotels, Inc. v. Kan. City Power & Light Co. , 913 S.W.2d 803, 806 (Mo. App. 1995) (disfavoring contract or tariff provisions that purport to absolve public utilities from liability for neg......
  • Danisco Ingredients USA, Inc. v. Kansas City Power & Light Co.
    • United States
    • Kansas Supreme Court
    • 9 July 1999
    ...liability were unreasonable and, so, unenforceable and invalid, citing to this Court's decision in Forte Hotels, Inc. v. Kansas City Power & Light Company, 913 S.W.2d 803 (Mo. App. 1995). In that case, this Court did hold these rules unreasonable in reliance on two Kansas Supreme Court case......
  • Dansico Ingredients, Usa, Inc. v. Kansas City Power & Light Co.
    • United States
    • Missouri Court of Appeals
    • 14 September 1999
    ...to the extent that it relates to a limitation of ordinary negligence. To the extent the decision in Forte Hotels, Inc. v. Kansas City Power & Light Co., 913 S.W.2d 803 (Mo.Ap.. 1995), holds to the contrary, it is no longer to be Accordingly, this court reverses summary judgment on Danisco's......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT