Frieden Const., Inc. v. Lower & Co.

Decision Date15 December 1988
Docket NumberNo. 87-269,87-269
Citation766 P.2d 527
PartiesFRIEDEN CONSTRUCTION, INC., Appellant (Defendant), Neosho Construction Co., Inc. and the Western Railroad Properties, Inc., (Defendants), American Insurance Company and Fireman's Fund Insurance Company, (Third-Party Defendants), v. LOWER & COMPANY, Appellee (Plaintiff), Western Railroad Properties, Inc., (Third-Party Plaintiff).
CourtWyoming Supreme Court

Douglas G. Madison and John E. Masters of Dray, Madison & Thomson, P.C., Cheyenne, for appellant.

Harold E. Meier of Schwartz, Bon, McCrary & Walker, Casper, for appellee.

Before CARDINE, C.J., and THOMAS and URBIGKIT, JJ., and BROWN, * and ROONEY, JJ., Retired.

URBIGKIT, Justice.

This appeal is a factually simple controversy involving compensation to appellee on a 1983 quantities dirt moving sub-contract for construction of a new railroad line for Western Railroad Properties, Inc. (Chicago and Northwestern Railroad) in the Lusk, Wyoming area. Summary judgment in the claimed amount plus interest was granted to the dirt contractor, and appeal is taken contesting both the amount allowed in judgment and right to accrued interest.

We affirm.

Stripped of the complexities of prior parties to the litigation and the panorama of changed attorneys, this court is invited to consider a contract entered into by Lower & Company (appellee) as an earth moving sub-sub-contractor for work completed in 1984 for Frieden Construction, Inc. (appellant), which served as a general sub-contractor on the railroad line construction project. Although appellant 1 presents a somewhat complex argument involving defenses to the judgment, the issue, simplistically stated, is whether the trial court erred in the grant of summary judgment in a defined amount for amounts due on the written contractual services agreement with interest. After a course of pleadings which had originally involved the owner, the general contractor and the sureties, the case came to the trial court for a pretrial pursuant to an order for pretrial conference filed April 17, 1986. The pretrial order required pretrial memoranda by the litigants, as well as a joint pretrial submission to be filed in advance. Appellee submitted a pretrial memorandum in proper detail and appellant failed to favor the trial court with any memoranda or other documentation required by the convening order. The file to that date indicated a quantities controversy.

With this state of the record, the trial court entered an order in lieu of pretrial conference which required appellant to produce contractual documents and a cross-section of the final survey so that a determination could be made of dirt quantities moved pursuant to the contract. In the event there was no final cross-section available, appellant's defense data pertaining to the amounts was requested in order for appellant to show errors, if any, in appellee's tally sheet.

Thereafter, pursuant to the order, appellant furnished cross-section details as contained within a May 16, 1986 letter from a surveyor. 2 Appellee promptly moved for summary judgment based upon the contractual documents and the newly furnished cross-section data which established the quantities covered in its roadbed construction activities. In support of the motion for summary judgment, an affidavit of Harold Lanham, as the treasurer and an officer of Lower & Company and who had been designated as a prospective witness in the prior pretrial memorandum, was submitted. A brief in support of summary judgment was also furnished as supported by an affidavit filed a few days later by another company employee. Appellant provided the trial court no affidavits to even contest its cross-section analysis, which established the balances due or the amount of those balances as had been computed in appellee's affidavits. Lacking resistive affidavits, the hearing, as convened on summary judgment, resulted in a summary judgment for the plaintiff as appellee and interest based in computation on the cross-section and prior billing for the amount claimed to be due since work completion in 1984. 3

In challenging the summary judgment, appellant essentially raises procedural contentions which fail by virtue of non-presentation to the trial court.

1. The affidavit of Warren Ash as not showing proper service. Our decision in the case of Matter of the Estate of Obra, 749 P.2d 272 (Wyo.1988) is dispositive since the affidavit was clearly considered by the trial court without objection and no objection on lack of service was made at the regularly convened hearing. Conway v. Guernsey Cable TV, 713 P.2d 786 (Wyo.1986). The affidavit was timely filed and at issue was the lack of mailing certificate or effect of an incomplete certificate attached to the accompanying brief.

2. Insufficiency in the form of the affidavit of treasurer, Harold Lanham. Appellant tries hard, but fails to find for us within the affidavit where the witness, who had been previously designated as an officer of the company, improperly computed or defined a specific amount stated to be due and payable. A minimum attack on the affidavit would require notice by hearing date and preferably by contesting evidence. 4 Conway, 713 P.2d 786.

A contention is found in present argument of appellant that in fact the price per yard should have been computed at a rate of .85 cents per cubic yard east of Lusk and .95 cents per cubic yard west of Lusk, rather than the charged total of $.85 and $.95. This argument is ingenious in that it was apparent from billing computation and common reasoning that the parties recognized the latter figure properly reflected the agreed compensation base for the earth work involved. The difference of one hundred times was significant. Furthermore, if appellant desired to raise this issue as a question of fact as indicating a different contention from what was contemplated by the pretrial order, the issue properly required affidavit support in advance of the pretrial hearing. Logically, such support could include comparison with compensation paid to appellant by Neosho with whom it had its subcontract. Affiant Lanham had provided as evidence of a total amount in his affidavit:

3. That your affiant, in connection with his duties on behalf of Lower & Co., received the daily time tally sheets, calculated the amounts paid on invoices submitted, and calculated the balance due under the contract.

4. That subsequent to the commencement of this litigation your affiant was furnished with the figures and calculations of Mr. Ronald Vogel, engineer and surveyor, who calculated the quantities of earth work done, and that accepting Mr. Vogel's calculation as true and correct, your affiant has prepared a total amount due under the contract, including the items of equipment as shown on the invoice. That the total amount due Lower & Co. as of the date of this affidavit, including interest, is the sum of $213,106.98.

Attached to the affidavit as Exhibit F was the surveyor's letter as the cross-section determination from which the computation was...

To continue reading

Request your trial
2 cases
  • Estate of Reed, Matter of
    • United States
    • Wyoming Supreme Court
    • January 31, 1989
    ...to the party against whom the motion was sought. See Matter of Estate of Newell, 765 P.2d 1353 (Wyo.1988); Frieden Construction, Inc. v. Lower & Company, 766 P.2d 527 (Wyo.1988); Matter of Estate of Obra, 749 P.2d 272 (Wyo.1988); and Cordova v. Gosar, 719 P.2d 625 (Wyo.1986). Thus, this cas......
  • Bueno v. CF & I Steel Corp.
    • United States
    • Wyoming Supreme Court
    • May 15, 1989
    ...computation of the amount due itself. Mathematical computability is the criterium for a liquidated claim. See Frieden Const., Inc. v. Lower & Co., 766 P.2d 527, 530 (Wyo.1988); Horseshoe Estates v. 2M Co., Inc., 713 P.2d 776, 781 (Wyo.1986); Holst v. Guynn, 696 P.2d 632, 635 (Wyo.1985); Mou......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT