Friedman Bros. Inv. Co. v. Lewis

Decision Date12 May 1982
Docket NumberNo. 81-5478,81-5478
Citation676 F.2d 1317
Parties, 12 Envtl. L. Rep. 20,962 FRIEDMAN BROTHERS INVESTMENT COMPANY, a partnership, Appellant, v. Andrew Lindsay Drew LEWIS, Jr., United States Secretary of Transportation; Arthur Teele, Administrator of the Urban Mass Transportation Administration; and the City of Torrance, a municipal corporation, Appellees.
CourtU.S. Court of Appeals — Ninth Circuit

Michael M. Berger, Fadem, Berger & Norton, Santa Monica, Cal., argued, for appellant; Diane E. Berley, Fadem, Berger & Norton, Santa Monica, Cal., on brief.

James R. Arnold, Asst. U. S. Atty., Los Angeles, Cal., Michael L. Martinez, Washington, D. C., argued, for appellee; Stuart B. Scudder, Torrance, Cal., on brief.

Appeal from the United States District Court for the Central District of California.

Before POOLE, and BOOCHEVER, Circuit Judges, and SOLOMON, * District Judge.

POOLE, Circuit Judge:

Appellant Friedman Brothers (Friedman) appeals the district court's dismissal of its action alleging appellees, the Urban Mass Transportation Administration (UMTA) and the City of Torrance, failed to comply with National Environmental Policy Act (NEPA) requirements for issuance of an environmental impact statement (EIS). The district court found that Friedman's claim was not ripe since there had been no final agency action as required by Section 10 of the Administrative Procedures Act (APA).

UMTA granted funds to Torrance to acquire Friedman's land for the site of a new bus maintenance depot, and categorically exempted construction and operation of the bus yard from NEPA requirements for the issuance of an EIS. We hold that UMTA's grant of funds and concurrent decision to exempt the project together constituted final agency action under the circumstances, even though formal action to acquire the property by condemnation had not commenced. Accordingly, we reverse.

I. FACTS

Friedman owns an 11.5 acre parcel of land in downtown Torrance, 3.5 acres of which the city plans to acquire for the site of its new transit operations center. The property, one block south of the city's current bus maintenance depot, is bounded on the west by a major thoroughfare, and is zoned for heavy industrial use. Part of the land is vacant and part is leased by an industrial user for a manufacturing facility.

The city submitted its initial request for project funding to UMTA in 1975, and informed Friedman of its intention to acquire the land. In June, 1980, UMTA granted the city $819,638.00 to purchase the site and complete design and engineering studies for depot construction, and authorized the city to begin condemnation proceedings. Torrance had not commenced condemnation action nor filed a final application for construction funds when this law suit was initiated.

On the basis of information provided by the city, UMTA determined that construction and operation of the bus yard would not entail significant environmental impact. It granted the project a categorical exclusion from further environmental review pursuant to its internal agency guidelines developed in response to a mandate from the Council on Environmental Quality and later codified. See 23 CFR 711.115 (1981). The regulations provide an exclusion for:

Construction of new bus storage and maintenance facilities in areas predominately zoned for industry and located on or near an arterial street with capacity adequate to handle anticipated bus traffic. 1

Friedman sought to enjoin the grant of site acquisition funds, claiming that UMTA violated Section 102(2)(C) of NEPA, 42 U.S.C. § 4332(2)(c), by not issuing an EIS. 2 The district court found that the acquisition grant was not final agency action as required by Section 10 of the APA, 5 U.S.C. § 704, 3 and held that judicial review of the adequacy of UMTA's environmental assessment would not be appropriate until the agency approved a construction grant. Accordingly, it dismissed Friedman's claim as unripe.

II. RIPENESS

The ripeness doctrine is designed to prevent premature judicial intervention in uncompleted agency proceedings and to insure that challenged agency decisions have a concrete impact on the parties involved. Abbott Laboratories v. Gardner, 387 U.S. 136, 148-9, 87 S.Ct. 1507, 1515, 18 L.Ed.2d 681 (1967). Whether an issue is ripe for judicial determination depends on the combined weight of the question's fitness for adjudication and the hardship to the parties if review is delayed. Pacific Legal Foundation v. State Energy Resources Conservation and Development Commission, 659 F.2d 903, 915 (9th Cir. 1981); Western Oil and Gas Association v. EPA, 633 F.2d 803, 807 (9th Cir. 1980).

The aspect of ripeness which chiefly concerns us here is finality. This case squarely presents legal issues which further factual inquiry will not make more concrete. See Western Oil and Gas, 633 F.2d at 808. UMTA's decision that the bus yard qualified for a categorical exclusion is "final" in that it is the culmination of the agency's administrative procedures and will not be reconsidered at any later date.

In Aberdeen & Rockfish R. Co. v. Students Challenging Regulatory Agency Procedures (SCRAP II), 422 U.S. 289, 95 S.Ct. 2336, 45 L.Ed.2d 191 (1975), the Supreme Court held that the Interstate Commerce Commission's decision not to issue an EIS in a general revenue proceeding concerning railroad freight rate increases was final agency action despite the interim nature of the proceeding. "When agency or departmental consideration of environmental factors in connection with that 'federal action' is complete, notions of finality and exhaustion do not stand in the way of judicial review of the adequacy of such consideration, even though other aspects of the (action) are not ripe for review." Id. at 319, 95 S.Ct. at 2355.

While UMTA has not made a final commitment to fund construction of the bus depot, 4 the agency has spoken its last word on the project's environmental impact. Similarly, although UMTA contended at oral argument that its acquisition grant was a "floating" grant not tied to the purchase of any specific site, the agency has performed all federal actions necessary to enable Torrance to acquire Friedman's land. The agency's memorandum approving the acquisition grant referred to Friedman's parcel, and the categorical exclusion was also site-specific. 5 The city has received the $820,000.00 disbursement and has been authorized to condemn the property. No federal procedural hurdles remain in its way. Since judicial review of the exclusion at this time will not interfere with any ongoing agency decision-making...

To continue reading

Request your trial
25 cases
  • Envtl. Def. Ctr. v. Bureau of Ocean Energy Mgmt.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • June 3, 2022
    ...EA, no permits could be sought. We have repeatedly held that final NEPA documents are final agency actions. Friedman Bros. Inv. Co. v. Lewis , 676 F.2d 1317, 1318 (9th Cir. 1982) ; Te-Moak Tribe of W. Shoshone of Nev. v. U.S. Dep't of Interior , 608 F.3d 592, 598 (9th Cir. 2010) ; Rattlesna......
  • Edwards v. District of Columbia
    • United States
    • U.S. District Court — District of Columbia
    • October 31, 1985
    ...review context is designed to prevent premature judicial intervention in uncompleted agency proceedings. See Friedman Bros. Inv. Co. v. Lewis, 676 F.2d 1317, 1318 (9th Cir.1982); Pilots Rights Ass'n v. Federal Aviation Administration, 86 F.R.D. 174 (D.D.C.1980). Accordingly, section 704 of ......
  • Thorsted v. Gregoire
    • United States
    • U.S. District Court — Western District of Washington
    • February 10, 1994
    ...for Alaska v. Hodel, 806 F.2d 1378, 1381 (9th Cir.1986); Helm v. California, 722 F.2d 507 (9th Cir.1983); Friedman Bros. Inv. Co. v. Lewis, 676 F.2d 1317, 1319 (9th Cir.1982). The questions raised here are purely legal: whether a state may add qualifications for election to Congress beyond ......
  • Central Delta Water v. Fish and Wildlife
    • United States
    • U.S. District Court — Eastern District of California
    • September 8, 2009
    ...NEPA context, the action must be the agency's "last word on the project's environmental impact" as a whole. Friedman Bros. Inv. Co. v. Lewis, 676 F.2d 1317, 1319 (9th Cir.1982). The issuance of a final EIS or a ROD constitutes final agency action. Sierra Club v. Slater, 120 F.3d 623, 631 (6......
  • Request a trial to view additional results