Garrison v. Jervis B. Webb Co.

Decision Date14 August 1978
Docket NumberNo. 76-2456,76-2456
Citation583 F.2d 258
PartiesGeraldine GARRISON, Administratrix of the Estate of Kenneth L. Garrison, Deceased, Plaintiff-Appellant, v. JERVIS B. WEBB COMPANY, Defendant-Appellee.
CourtU.S. Court of Appeals — Sixth Circuit

John Frith Stewart, Segal, Isenberg, Sales, Stewart & Nutt, Stephen J. Tillman, Louisville, Ky., for plaintiff-appellant.

David R. Monohan, Woodward, Hobson & Fulton, Fielden Woodward, Louisville, Ky., for defendant-appellee.

Before CELEBREZZE, ENGEL and MERRITT, Circuit Judges.

CELEBREZZE, Circuit Judge.

This appeal involves a wrongful death action instituted in Kentucky state court and removed to federal court on the basis of diversity of citizenship. Plaintiff-appellant, Geraldine Garrison, is administratrix of the estate of her husband, Kenneth Garrison (decedent). The decedent was killed in a work-related accident while employed as an ironworker by the Austin Company (Austin), which was general contractor for the construction of a Clark Equipment Company (Clark) plant near Georgetown, Kentucky. Defendant-appellee, Jervis B. Webb Company (Webb), was a subcontractor. The district court directed a verdict for Webb at the close of all the evidence, reasoning that there had not been a sufficient showing of negligence on the part of Webb to send the case to the jury. We affirm.

Webb was a subcontractor responsible for the installation of a conveyor system in the Clark plant. The conveyor was to run, in part, over a large concrete pit in the floor of the plant. To support the conveyor at this point, Webb installed a long steel "header beam" between two large steel "truss beams" near the ceiling of the plant. The truss beams were parallel to one another and the header beam ran between them at a right angle and in the same horizontal plane as the truss beams. All these beams were roughly thirty feet above the bottom of the concrete pit, which was a few feet lower than the surrounding floor.

At the time of the accident, Webb had connected the header beam to the truss beams with steel clips. These clips consisted of steel plates above and below the header beam which plates were connected by several nuts and bolts. The tightening of the nuts and bolts served to clamp the header beam onto the truss beams. Webb had "tack welded" 1 the bottom portion of these clips to the header beam in order to facilitate attachment of the header beam to the truss beams in their elevated position by obviating having to hold onto the tack welded portions. The responsibility for holding the header beam in place, however, rested wholly on the steel clips, as tightened by the nuts and bolts, and the tack welding was only meant to facilitate installation.

Austin officials decided that the header beam should be moved about one foot along the truss beams. The decedent and another Austin employee undertook this task by removing some of the steel clips on the header beam and loosening the bolts on the remaining clips just enough so that the header beam would slide along the truss beams when struck with a large hammer. When the decedent so struck the header beam at one end, the tack weld between the remaining steel clips and the header beam broke. This caused the clip to separate from the header beam and the header beam thereby fell apart from the truss beam. The decedent, apparently believing the steel clips were welded to the header beam solidly enough to withstand his hammering, fell to his death in the concrete pit some thirty feet below. 2

Appellant contends that the case should have gone to the jury on the issue of whether Webb was negligent in failing to solidly weld the clips to the header beam or alternatively whether, having tack welded the clips, Webb had the duty to warn foreseeable third parties, such as the decedent, of this fact. The district court, in directing a verdict for Webb, accepted Webb's theory of the case that the steel clips were properly installed by Webb in accordance with the construction specifications and that Austin had full knowledge that the clips were only tack welded to the header beam. 3 We agree with the district court that a directed verdict for Webb was appropriate. 4

As noted, appellant's case had two theories for recovery. The first was that Webb negligently and improperly installed the header beam by only tack welding the steel clips to the header beam rather than solidly welding them. The only evidence supporting this contention relates to a note, akin to a footnote, on a blueprint which depicted, Inter alia, the clamp connection between the header beam and truss beams in question. This note read: "All Connections To Be Welded Solid." Aside from introducing the blueprint itself and having several witnesses merely read this note, the only testimony favorable to appellant's case regarding this note came from one witness who testified that he would interpret the note to mean that Webb should have solidly welded the clips to the header beam. This witness, however, was not qualified as an expert in reading blueprints. 5 He also admitted that if all the clips had been welded solidly the header beam would not have moved at all along the truss beams. This completely destroyed the credibility of his testimony that the welds should have been solid since appellant concedes that the header beam had to be movable along the truss beams. Moreover, this testimony was squarely contradicted by several qualified witnesses, including some called by appellant and including the project engineer employed by Austin, who testified that Webb installed the header beam precisely as specified in the blueprint. They said that the note "All Connections To Be Welded Solid" did not apply to the clips in question because the blueprint clearly showed the use of nuts and bolts to tighten the clips in place.

The district court was thus faced with the question of whether Webb could be held liable when it installed the header beam precisely as called for in the blueprint, in the absence of any showing of negligent design on its part. While we have found no Kentucky cases directly on point, we believe that the Supreme Court of Kentucky would not sanction recovery against Webb under these circumstances. See Ulrich v. Kasco Abrasives Co., 532 S.W.2d 197, 201 (Ky.1976); Hercules Powder Co. v. Hicks, 453 S.W.2d 583, 590 (Ky.1970). See also Garrison v. Rohm and Haas Co., 492 F.2d 346, 350-51 (6th Cir. 1974).

Appellant's second theory of recovery is that, having only tack welded the clips, Webb had the duty to warn foreseeable third parties of this fact. Appellant, however, made no showing of an inadequate warning. Webb, on the other hand, put forward uncontradicted testimony from the project engineer employed by Austin that he knew that the clips had only been tack welded to the header beam and that this was appropriate. Thus, even assuming a warning was called for, the knowledge of the project engineer employed by Austin, the decedent's employer, was clearly sufficient warning under Kentucky law. Hercules Powder Co. v. Hicks, 453 S.W.2d 583, 590-91 (Ky.1970). See also Garrison v. Rohm and Haas Co., 492 F.2d 346, 352 (6th Cir. 1974).

Appellant's reliance on Restatement of Torts § 388 6 is misplaced. There was no evidence "that the chattel (was) or (was) likely to be dangerous for the use for which it (was) supplied." Restatement § 388(a). The header beam installation was not at all dangerous until altered by the decedent by removing several of the steel clips holding the header beam to the truss beams. Also, assuming it to be dangerous, Webb Had "reason to believe that those for whose use the chattel (was) supplied (would) realize its dangerous condition," Restatement § 388(b), since Austin's project engineer was fully aware of the condition of the header beam and under Kentucky law that notice was sufficient. This knowledge by Austin's project engineer that the clips were only tack welded also means that Webb could not have been held liable for "fail(ing) to exercise reasonable care to inform them of its dangerous condition or of the facts which make it likely to be dangerous." Restatement § 388(c).

The judgment of the district court is affirmed.

1 "Tack weld" is a term used to describe a small weld, perhaps no more than one-half inch in diameter, designed to temporarily attach one piece of steel to another. It is often done intermittently along a meeting of two pieces of steel and is a weak weld not intended to ultimately bear significant weight or stress. It is to be distinguished from a "solid weld" or "structural weld" meant to create a permanent attachment of two pieces of steel which is as strong as the surrounding steel. A solid or structural weld is generally much larger than a tack weld, often being solid along the entire intersecting seam.

2 While the record is not entirely clear on the point, the decedent was apparently sitting on the header beam, which he was trying to move with his hammering, when that beam fell from the truss beam.

3 Formal findings of fact and conclusions of law were not required in this cause since Federal Rule of Civil Procedure 52(a) states that such "are unnecessary on decisions of motions under Rules 12 or 56...

To continue reading

Request your trial
24 cases
  • Brown v. Board of Educ. of Topeka, Shawnee County, Kan.
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • 11 Diciembre 1989
  • Bailey v. V & O Press Co., Inc.
    • United States
    • U.S. Court of Appeals — Sixth Circuit
    • 16 Agosto 1985
    ...66 L.Ed.2d 114 (1980). In addition, consideration may be given to positions expressed in restatement of law, Garrison v. Jervis B. Webb Co., 583 F.2d 258, 262 n. 6 (6th Cir.1978), law review commentaries, McKenna, 622 F.2d at 662-63, and decisions from other jurisdictions or the "majority" ......
  • Equity Planning Corp. v. Westfield Ins. Co.
    • United States
    • U.S. District Court — Northern District of Ohio
    • 26 Febrero 2021
    ...66 L.Ed.2d 114 (1980). In addition, consideration may be given to positions expressed in restatement of law, Garrison v. Jervis B. Webb Co. , 583 F.2d 258, 262 n.6 (6th Cir. 1978), law review commentaries, McKenna , 622 F.2d at 662-63, and decisions from other jurisdictions or the "majority......
  • North v. Madison Area Ass'n for Retarded Citizens-Developmental Centers Corp.
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • 4 Abril 1988
    ...an advisory jury, Fed.R.Civ.P. 52(a); they are not required on the granting of a motion for directed verdict. Garrison v. Jervis B. Webb Co., 583 F.2d 258, 261 n. 3 (6th Cir.1978); Weir v. Chicago Plastering Institute, 272 F.2d 883, 888 (7th Cir.1959). The district court's findings in the p......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT