General Ins. Co. of America v. Interstate Service Co., Inc.

Decision Date01 September 1997
Docket NumberNo. 163,163
Citation701 A.2d 1213,118 Md.App. 126
PartiesGENERAL INSURANCE COMPANY OF AMERICA, et al. v. INTERSTATE SERVICE COMPANY, INC. ,
CourtCourt of Special Appeals of Maryland

Stephen M. Seeger (Quagliano & Seeger, on the brief), Washington, DC, for appellants.

Van Powers, Hyattsville, for appellee.

Argued before CATHELL, EYLER and THIEME, JJ.

EYLER, Judge.

This case, which is before us for the second time, involves application of the Restatement (Second) of Conflict of Laws § 187(2)(b) (1971). In particular, we must decide whether to enforce contractual limitations provisions that are against Maryland public policy when the contracts at issue provide that the laws of Virginia and the District of Columbia shall govern. Because we cannot say that Maryland has a materially greater interest in the determination of the issue than do Virginia and the District of Columbia, we will apply the laws of Virginia and the District of Columbia, uphold the contractual limitations provisions, and reverse the judgment of the trial court.

Facts

Appellee Interstate Service Company, Inc. ("Interstate") is a mechanical subcontractor who, pursuant to subcontracts with NICO Construction Co. ("NICO"), performed work on five separate construction projects located in the District of Columbia and the Commonwealth of Virginia. Appellant General Insurance Company of America ("General") issued to NICO a performance and payment bond on the project located at Georgetown University Hospital in the District of Columbia ("Georgetown bond"), while Westchester Fire Insurance Company ("Westchester") issued to NICO a performance and payment bond on the project located at Alexandria Hospital in Virginia ("Alexandria bond").

Interstate last performed work on the Georgetown University project on July 29, 1991, and NICO certified that the project was 100% complete on January 8, 1992. By letter dated April 9, 1992, Interstate sent notice to NICO and General of its claim on the Georgetown payment bond.

Interstate last performed work on the Alexandria Hospital project on February 27, 1991, and NICO certified that the project was 100% complete on December 26, 1991. By letter dated April 20, 1992, Interstate sent notice to NICO and Westchester of its claim on the Alexandria bond.

On September 9, 1992, Interstate filed an action in the Circuit Court for Prince George's County against NICO for nonpayment on the two projects, and on November 19, 1993, Interstate filed an amended complaint adding claims against General and Westchester for breach of the payment bonds.

On August 9, 1994, pursuant to a settlement agreement between the two parties, Interstate obtained a judgment against NICO in the amount of $321,742.86. Although the settlement did not resolve the issue of the respective liabilities of General and Westchester on the bonds, the sureties did agree, at the request of the settling parties, that they would not invoke the forum selection clauses contained in the bonds. 1

Thereafter, General and Westchester filed a motion for summary judgment based upon one year limitations of actions provisions located in each of the payment bonds. Specifically, the Georgetown bond stated in pertinent part No suit or action shall be commenced by a Claimant under this Bond ... after expiration of one year from the date ... on which the last labor or service was performed by anyone or the last materials or equipment were furnished by anyone under the Construction Contract.... If the provisions of this Paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable.

The Alexandria bond provided in pertinent part:

No suit or action shall be commenced hereunder by any claimant: ... [a]fter the expiration of one (1) year following the date on which Principal ceased Work on said Contract. It being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof, such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law.

In their motion, General and Westchester argued that the trial court should apply Virginia law because the contracts between Interstate and NICO contained choice of law provisions selecting Virginia law, and these contracts were incorporated by reference in the payment bonds. General and Westchester further argued that Virginia law permitted one year contractual limitations provisions. Interstate filed a cross-motion for summary judgment arguing that the trial court should apply Maryland law and that the limitations of actions provisions were void and unenforceable under Maryland law. Interstate alternatively argued that Virginia law would not enforce the contractual limitations provisions. The trial court granted summary judgment in favor of General and Westchester and denied Interstate's motion for summary judgment, and Interstate appealed.

On appeal, in an unreported opinion, we reversed the judgment based upon Md.Code Ann. (1957, 1994 Repl.Vol.), Art. 48A § 377B, which prohibits the enforcement of any provision in an insurance contract that shortens the applicable period of limitation contained in Maryland statutes. We noted that, in the absence of a contractual provision, the period of limitations generally is an issue of procedural rather than substantive law, and accordingly, the law of the forum applies. With respect to General's and Westchester's arguments that the parties had contractually agreed to limit the period of limitations and had selected Virginia law to govern, we noted that the payment bonds did not incorporate the Interstate-NICO contracts. Instead, the payment bonds incorporated the general contracts between NICO and the project owners. As we did not have those contracts before us, and could not ascertain whether they included choice of law provisions, we had no choice but to remand the case for further proceedings.

On remand, General and Westchester provided the trial court with copies of the general contracts for both the Georgetown and the Alexandria projects. General Conditions Article 19.1 of both the Georgetown and Alexandria contracts provides that "[t]he Contract shall be governed by the law of the place where the Project is located." The location of the Georgetown project is described on the first page of the Georgetown contract as follows: "Modular Laboratories Renovation, Ground Floor and Lower Level, Preclinical Sciences Building, Georgetown University Medical Center." It is undisputed that this location is within the District of Columbia. The location of the Alexandria project is described on the first page of the Alexandria contract as follows: "Renovation to the Third Floor Obstetrical Nursing Unit and Full-term Nursery at the Alexandria Hospital." It is undisputed that this location is within the Commonwealth of Virginia.

Notwithstanding these provisions, the trial court, on remand, held that Maryland law applied to the limitations issue and that Maryland law prohibited the inclusion in an insurance contract of a provision shortening the period of limitations. Consequently, the trial court entered summary judgment in favor of Interstate. Thereafter, General and Westchester filed this timely appeal.

Standard of Review

Recently, in Marriott v. Morgan State University, 115 Md.App. 493, 694 A.2d 123 (1997), we reviewed the principles governing appellate review of a grant of summary judgment as follows:

Rule 2-501(e) directs the trial court to grant summary judgment in favor of the movant "if the motion and response show that there is no genuine dispute as to any material fact and that the party in whose favor judgment is entered is entitled to judgment as a matter of law." Under the summary judgment rule, a trial court does not resolve disputed issues of fact, but instead, makes rulings as a matter of law. Southland Corp. v. Griffith, 332 Md. 704, 712 (1993); Beatty v. Trailmaster Prods., Inc., 330 Md. 726, 737 (1993). Thus, the standard for appellate review of a grant of summary judgment is whether the trial court was legally correct. Griffith, 332 Md. at 712 ; Beatty, 330 Md. at 737 .

Marriott, 115 Md.App. at 501-502, 694 A.2d 123.

Discussion

As we noted upon the first appeal of this case, in the absence of contractual provisions that would produce a contrary result, the statute of limitations applicable to the payment bonds is twelve years. See Md.Code Ann. (1974, 1995 Repl.Vol.), Cts. & Jud. Proc. § 5-102(a)(2). See also Doughty v. Prettyman, 219 Md. 83, 88, 148 A.2d 438 (1959) (holding that statutes of limitations are matters of procedural law governed by the law of the forum state); Mandru v. Ashby, 108 Md. 693, 695, 71 A. 312 (1908)(holding that procedural matters are governed by the law of the forum). Further, while both of the payment bonds purport to shorten the limitations period, such a shortening is prohibited by Maryland law. Specifically, Article 48A, § 377B of the Maryland Code provides as follows:

All provisions and stipulations contained in any contract of insurance or suretyship, whatsoever, heretofore or hereafter issued, fixing the time in which suits or actions may be instituted under or upon any such contracts at a period of time less than that provided at the time of the issuance or delivery of any such contract by the laws of the statutes of Maryland in respect of limitations are hereby declared to be against State public policy, illegal and void, and no court in this State shall give any effect to any provisions or stipulation in any contract mentioned in this section; nor shall any defense to liability under any such contract be based upon any such shorter limitation period.

Md.Code (1957, 1994 Repl.Vol.). Accordingly, if Maryland law is controlling, the contractual limitations provisions are not valid, and Interstate's...

To continue reading

Request your trial
14 cases
  • U.S. ex rel. Ackley v. Intern. Business Machines, No. Civ. PJM 97-3189.
    • United States
    • U.S. District Court — District of Maryland
    • 27 Julio 2000
    ...matter governed by the law of the forum — Maryland — not by the law of the place of the wrong. General Ins. Co. of Am. v. Interstate Serv. Co., 118 Md.App. 126, 130, 701 A.2d 1213, 1215 (1997); see Black v. Leatherwood Motor Coach Corp., 92 Md.App. 27, 37, 606 A.2d 295, 300 (1992); see also......
  • Notre Dame v. Morabito, 327
    • United States
    • Court of Special Appeals of Maryland
    • 9 Marzo 2000
    ...Article (original version at Md.Code (1957, 1994 Repl.Vol.), Art. 48A § 377B); see also General Ins. Co. of America v. Interstate Serv. Co., Inc., 118 Md.App. 126, 133-38, 701 A.2d 1213 (1997),cert. denied, 349 Md. 103, 707 A.2d 89 (1998), cert. denied, 350 Md. 276, 711 A.2d 869 (1998)(citi......
  • Petitto v. Petitto
    • United States
    • Court of Special Appeals of Maryland
    • 6 Septiembre 2002
    ...govern their transaction, even as to issues going to the validity of the contract." General Insurance Company of America v. Interstate Service Company, Inc., 118 Md.App. 126, 137, 701 A.2d 1213 (1997); see National Glass, Inc. v. J.C. Penney Properties, Inc., 336 Md. 606, 650 A.2d 246 (1994......
  • Accrued Financial Services, Inc. v. Prime Retail
    • United States
    • U.S. Court of Appeals — Fourth Circuit
    • 29 Julio 2002
    ...whether Maryland has a materially greater interest in the determination of the issue." General Ins. Co. of Am. v. Interstate Serv., Inc., 118 Md.App. 126, 701 A.2d 1213, 1218-19 (Md.Ct. Spec.App.1997). In determining whether Maryland has a materially greater interest in an issue, the courts......
  • Request a trial to view additional results
1 books & journal articles
  • Annual survey of fidelity and surety law.
    • United States
    • Defense Counsel Journal Vol. 65 No. 3, July 1998
    • 1 Julio 1998
    ...661 N.E.2d 967 (N.Y. 1995), on certified question, 49 F.3d 48 (2d Cir. 1995). Decision below: 872 F.Supp. 1212 (S.D.N.Y. 1994). (14.) 701 A.2d 1213 (Md. App. 1997). (15.) 938 P.2d 372 (Cal.1997). (16.) Citing, among others, Koch v. Construction Technology Inc., 924 S.W.2d 68 (Tenn. 1996); O......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT