George v. Oren Ltd. & Associates

Decision Date29 August 1983
Docket NumberNo. 18359,18359
Citation672 P.2d 732
CourtUtah Supreme Court
PartiesFrank R. GEORGE, dba Frank George & Son Construction, Plaintiff and Respondent, v. OREN LIMITED & ASSOCIATES, a Utah limited partnership, Defendant and Appellant.

Lorin N. Pace, Salt Lake City, for defendant and appellant.

Stephen G. Homer, West Jordan, for plaintiff and respondent.

HALL, Chief Justice:

Plaintiff Frank R. George, dba George & Son Construction, brought this action to recover sums alleged due for services and materials provided in the installation of improvements upon defendant's property, and for a lien against the property so served. Defendant Oren Limited & Associates counterclaimed for damages upon the theory that plaintiff's alleged untimely performance constituted a breach of contract. The trial court entered judgment in plaintiff's favor, awarding him damages in the amount of $58,482.41 and attorney fees of $2,700, and dismissing defendant's counterclaim. Defendant seeks reversal of only the money judgment on this appeal.

In May, 1979, the parties entered into a series of written contracts whereby plaintiff agreed to install improvements (curb and gutter, sidewalks, water and sewage lines, and street paving) within a subdivision located in Farmington, Utah. Inasmuch as these improvements were to eventually become the property of Farmington City (hereinafter "the City"), they were designed and inspected by the City.

To guarantee the completion of the improvements, as well as the entire subdivision project, the City required that defendant, as developer, provide a bond in the amount of $269,500, and that the bond be deposited in an escrow account. Funds in this account were released by the escrow holder (American Savings) for the purpose of paying construction expenses only upon the written approval of the City.

Plaintiff commenced installation of the improvements in May, 1979. Approximately one month later (June 6, 1979), he submitted his first bill, which was paid promptly by defendant. Thereafter, he continued to bill defendant on a monthly basis and to receive payments from defendant as billed, until October, 1979. The bill submitted by plaintiff in October for the work performed during the month of September was only partially paid. However, plaintiff received assurances at that time from John W. Sullivan, a partner in the defendant partnership, that the balance would definitely be paid. On the basis of Mr. Sullivan's assurances, plaintiff continued his work through the months of October and November. He then presented a bill on November 21, 1979, for the balance due from September and for the additional work performed during October and November. This bill was not paid, although again plaintiff received assurances that funds were forthcoming. Plaintiff did not, however, resume installation thereafter.

In May, 1980, Mr. Sullivan tendered to plaintiff a letter addressed to the Farmington City Council, authorizing the Council to release such funds from the bond (escrow account) as were owed to plaintiff. Upon presentment of this letter to the City, plaintiff was informed that the bond (escrow) had been exhausted. Thereupon, plaintiff filed a notice of lien against the subdivision property in the amount of $42,687.50. On July 15, 1980, he instituted the present action to recover the amount owing and enforce the lien.

At trial, the evidence clearly showed that at the times of plaintiff's execution and performance of the contracts in issue, unbeknownst to defendant or any of its individual partners, plaintiff was not licensed to engage in the business of a contractor. Plaintiff therefore acted in violation of U.C.A., 1953, § 58-23-1. 1

The evidence further revealed that although plaintiff had been duly licensed as a contractor from 1957 to 1969, he had failed to renew his license, notwithstanding his continued involvement in the business as a contractor, during an eleven-year period between 1969 and 1980. According to plaintiff's testimony, his failure to become licensed during this extended period of time was not attributable to inadvertence or negligent oversight, but rather to willful disregard of the State's licensing requirements. He testified as follows:

Q Any other reason you didn't license in 1970 or in subsequent years?

A Yes, there was a reason.

Q What was that?

A I didn't like the bureaucracy that dominated that sort of thing.

....

Q You indicated, Mr. George, you didn't like the bureaucracy. Why didn't you like the bureaucracy of the licensing department?

A Well, it was my contention they were revenue raising agencies. They are not a regulator. They don't know whether I know what I am doing or not.

Plaintiff became relicensed in June of 1980, at which time his performance under the subject contract had ceased. To obtain this license after approximately eleven years of unlicensed status, he had to demonstrate his competence anew by taking an examination.

Defendant's sole contention on appeal is that plaintiff's failure to comply with the licensing requirements of U.C.A., 1953, § 58-23-1 precludes his right to recover for materials and services provided under the contract.

The general rule in this jurisdiction with respect to the status of unlicensed contractors has been stated thus:

If the purpose of licensing is to protect the public, then the general rule in this State is that the party who does not obtain a license, but is required to do so, cannot obtain relief to enforce the terms of his contract--including payment thereunder--even though there are other penalties imposed against him expressly by statute including criminal sanctions .... And there is no doubt that the purpose of the licensing statute relating to contractors, supra [Section 58-23-1], is protection of the public. [Emphasis added.] 2

This rule is not, however, applied unconditionally. This Court has held that unless it is shown that the party from whom the unlicensed contractor seeks to recover is within the class of persons whom the licensing statute is designed to protect, the rule will not be applied. 3 Thus, the pivotal issue in this case is whether defendant occupied a protected status.

Defendant contends that it was definitely within the protected class and that the general rule, supra, should therefore have been invoked by the trial court to relieve defendant of its obligation to plaintiff under the contract. Defendant points out that this Court has only refused to apply the general rule in two cases, Fillmore Products, Inc. v. Western States Paving, Inc., 4 and Lignell v. Berg, 5 and that the circumstances upon which the Court's decision rested in those cases are clearly distinguishable from the instant matter.

It is of course plaintiff's position that defendant was not within the class protected under the licensing statute, and thus, should not be afforded the benefits of the general rule. Plaintiff maintains that the two cases noted above (Fillmore Products and Lignell ) are sufficiently similar to the present case to be dispositive hereof.

In the Fillmore Products case, the Court considered the following circumstances to be of controlling significance:

In this case it is clear that an unlicensed subcontractor is dealing with a licensed general or original contractor. And the defendants have not disputed that the entire sewer project was under the supervision of a licensed project engineer, that all of the work had to meet the specifications and requirements of the general contract and that all of the work had to be approved and accepted by the project engineer before any payment was made by the Town of Ferron. 6

Plaintiff argues that these same circumstances, at least in substance, exist in the instant case. He points out that his work had to meet the specifications of the Farmington City subdivision ordinance and that it was inspected by the City's personnel.

In Lignell, while sustaining the general rule, the Court made the following observation with respect to the exception: "A litigant is not a member of that class [protected class] if the required protection (i.e., against inept and financially irresponsible builders) is in fact afforded by another means." 7 The Court then cited the following circumstances as controlling in its determination that the protections contemplated under the statute were in fact provided through other means:

1. BBC [unlicensed contractor] has not failed to satisfy the licensing authority of its technical competence and financial qualification for license. It had inadvertently permitted its license to lapse. Restoration of licensed status involved no new demonstration of qualification, but only payment of fee.

2. The Owners did not rely on any BBC competence they inferred from BBC's having advertised itself as a general contractor. They had previously employed BBC as a builder in apartment house construction. Moreover, the Owners usurped the general contractor's prerogatives in constructing the Terrace Incline complex. They relied on their own competence.

3. BBC supplied a performance bond as well as a labor and material suppliers payment bond. The Owners were infinitely better assured of adequate and complete performance without financial exposure beyond the contract price than they would have been by BBC's mere compliance with the licensing statute. 8

Again, plaintiff maintains that in substance, these circumstances are present in the instant case, and that the required protection was provided in this case by the inspections conducted by the City.

To summarize his position on this point and to justify his reliance upon the Fillmore Products and Lignell decisions, plaintiff quotes the following passage from the memorandum decision issued by the trial court in response to defendant's motion for judgment n.o.v.:

The Court concludes that this case falls within the doctrine enunciated in the Fillmore Products, Inc. v. Western States Paving Inc., 561 P. 2nd 687,...

To continue reading

Request your trial
9 cases
  • Govert Copier Painting v. Van Leeuwen
    • United States
    • Utah Court of Appeals
    • November 8, 1990
    ...rule prohibiting unlicensed contractors from recovering for services rendered under their contracts. See Frank R. George v. Oren Ltd. & Assocs., 672 P.2d 732, 735 (Utah 1982); Fillmore Prods. v. Western States Paving, Inc., 561 P.2d 687, 689 (Utah 1977). In 1981, the Utah Legislature repeal......
  • Lindstrom v. District Bd. of Health Panhandle Dist. I
    • United States
    • Idaho Court of Appeals
    • October 25, 1985
    ...a State to abridge existing contractual relationships...."); accord, State v. Direct Sellers Association, supra; George v. Oren Limited & Associates, 672 P.2d 732 (Utah 1983). As an extension of the argument that the rule is unconstitutional as applied to them, the Lindstroms further conten......
  • R4 Constructors LLC v. Inbalance Yoga Corp.
    • United States
    • Utah Court of Appeals
    • December 24, 2020
    ...at both the time of contracting and at the time the cause of action arose. See id. § 58-55-604 ; see also George v. Oren Ltd. & Assocs. , 672 P.2d 732, 734 (Utah 1983) (observing claimant became relicensed but reversing with order to dismiss the claim for lack of licensure).2 The Assumed Na......
  • Pacific Chromalox Div., Emerson Elec. Co. v. Irey
    • United States
    • Utah Court of Appeals
    • February 12, 1990
    ...though there are other penalties imposed against him expressly by statute including criminal sanctions. George v. Oren Ltd. & Assocs., 672 P.2d 732, 735 (Utah 1983) (quoting Fillmore Prods., Inc. v. Western States Paving, Inc., 561 P.2d 687, 689 (Utah 1977)) (emphasis in original); see also......
  • Request a trial to view additional results
1 books & journal articles
  • Analyzing Mechanics' Lien Claims: a Few Suggestions
    • United States
    • Utah State Bar Utah Bar Journal No. 22-5, October 2009
    • Invalid date
    ...[licensure] rule will not be applied," so "the pivotal issue...is whether defendant occupied a protected status." George v. Oren, Ltd., 672 P.2d 732, 735 (Utah 1983) (citations omitted); see also am. rural Cellular, Inc. v. Sys. Commc'n Corp., 890 P.2d 1035, 1040 (Utah Ct. App. 1995) ("[W]h......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT