Gergora v. R. L. Lapp Forming, Inc.

Decision Date18 June 1980
Docket NumberNo. 78-1673,78-1673
Citation619 F.2d 387
Parties92 Lab.Cas. P 55,307 Michele GERGORA et al., Plaintiffs-Appellees, v. R. L. LAPP FORMING, INC., etc., Defendant, Travelers Indemnity Co., etc., Defendant-Appellant.
CourtU.S. Court of Appeals — Fifth Circuit

John Downing, Luther Cochrane, Fort Lauderdale, Fla., for defendant-appellant.

Kaplan, Dorsey, Sicking & Hessen, Joel V. Lumer, Steven Bloom, Howard S. Susskind, Robert A. Sugarman, Miami, Fla., for plaintiffs-appellees.

Appeal from the United States District Court for the Southern District of Florida.

Before MORGAN, ANDERSON and RANDALL, Circuit Judges.

LEWIS R. MORGAN, Circuit Judge.

Appellant Travelers Indemnity Co. appeals from a judgment holding it liable as surety for the default of R. L. Lapp Forming, Inc., subcontractor for a public construction project in Broward County, Florida. The plaintiffs-appellees are trustees of the Broward County Carpenters' Health & Welfare Pension, Vacation and Apprenticeship & Training Trust Funds. They brought this action in the United States District Court for the Southern District of Florida based on the labor organization dispute jurisdiction provided federal courts by 29 U.S.C. § 185.

In January 1975 the School Board of Broward County entered into an agreement with Edward L. Nezelek, Inc. for the construction of Coral Springs High School. Travelers issued a payment bond on the project for Nezelek pursuant to the requirements of Florida Statutes section 255.05.

As general contractor for the project, Nezelek gave a subcontract to R. L. Lapp Forming for all concrete form work at the construction site. R. L. Lapp Forming was a party to the collective bargaining agreement between the Broward County Carpenters' District Council and various regional construction associations. Among the provisions of the collective bargaining agreement was a requirement that every employer contribute a stated amount to the fringe benefit trust fund of which the appellees are trustees. The agreement further provided that if any employer should default on its obligation to contribute to the trust fund, the employer would bear additional liability for all reasonable attorneys fees and audit charges incurred by the trustees in collecting the unpaid contributions.

Early in the spring of 1975, R. L. Lapp Forming began to experience severe financial difficulties. In April, the company ceased all payments to the fringe benefits fund. Work continued, however, and by August 22, 1975, Lapp Forming owed the fund an accumulated debt of $16,642.11. On September 24, 1975, the trustees notified Nezelek, Travelers Indemnity and the School Board of Broward County that Lapp Forming had failed to make the trust fund contributions required by the collective bargaining agreement. After Nezelek failed to pay the debt of its subcontractor, the trustees initiated this lawsuit and named Lapp Forming, Nezelek, and Travelers Indemnity as defendants.

A default judgment was entered against Lapp Forming, and after a trial on the merits of the complaint against the remaining defendants, the district court entered its final judgment in favor of the trustees. On appeal, Travelers Indemnity contends that the trustees' written notice of Lapp Forming's default was tardy, precluding any suit against the general contractor and surety. Travelers Indemnity also contends that the district court's award of attorneys fees to the trustees was contrary to Florida law.

I. NOTICE OF DEFAULT

The bond issued by Travelers Indemnity on the construction of the Coral Springs High School was accepted by the School Board and general contractor Nezelek as the security required by law under section 255.05 of the Florida Statutes. Hence, all rights and obligations under the bond are governed by the statute. Unpaid suppliers of subcontractors on the bonded project may recover on the bond under subsection 255.05(2) provided they deliver written notice of nonpayment to the general contractor "within ninety days after performance of the labor or after complete delivery of materials and supplies." The delivery of ninety-day notice is a strict condition precedent to the maintenance of an action on the bond by any supplier. Fuller Industries, Inc. v. R. Terry Blazier and Son, Inc., 188 So.2d 2 (Fla.Dist.Ct.App.1966).

The plaintiffs delivered written notice within ninety days of the last day on which labor was performed, but more than ninety days from the performance of much of the labor for which trust fund contributions are owed. The question thus framed is whether the statutory ninety day notice period should run separately for each day of labor, or whether the period should commence for all labor only after the last day of performance.

In the case of materials suppliers, the ninety day notice period commences for all sales after the supplier's last delivery of materials to the subcontractor. Clutter Construction Corporation v. Baker Brothers, 168 So.2d 576 (Fla.Dist.Ct.App.1964). Travelers Indemnity notes that the rule for materialmen is based on statutory language inapplicable to suppliers of labor. Section 255.05 states that notice must be within ninety days of "complete delivery" of materials, whereas the statute refers only to the "performance" of labor and not complete performance as beginning the ninety day period.

We regard this variation in phraseology within the same statute as more ambiguous than meaningful. The statute is subject to at least two reasonable interpretations. Either the qualification that delivery of materials must be "complete" creates a different rule for severable materials contracts than for severable labor contracts, or it merely emphasizes that materials must be delivered to the construction site ready for use before the notice period begins to run. See Board of Public Instruction v. Fidelity and Casualty Co., 184 So.2d 491 (Fla.Dist.Ct.App.1966).

In interpreting ambiguous statutory language, our task is to discover what interpretation will best accomplish the intention of the legislature. Devin v. City of Hollywood, 351 So.2d 1022 (Fla.Dist.Ct.App.1976). The Florida courts have recognized the purpose of section 255.05 to be "the protection of materialmen, laborers and the like, whose labor and materials are put into public works projects, upon which they can acquire no lien." City of Fort Lauderdale v. Hardrives Co., 167 So.2d 339, 340 (Fla.Dist.Ct.App.1964). Being remedial in nature, the statute is entitled to a liberal construction. Id.

Because section 255.05 is intended to serve in lieu of the mechanic's lien remedy, the Florida courts have found it helpful to resolve inclarities by looking to the analogy of the Mechanic's Lien Law (Florida Statutes Ch. 713). Miller v. Knob Const. Co., 368 So.2d 891 (Fla.Dist.Ct.App.1979). Section 713.08(5) of the Florida Statutes provides that a lien may be recorded at any time within "ninety days after the final furnishing of the labor." The notice provision of section 255.05 should be no more rigorous if the protection of the public construction bond is to be truly commensurate with that of a mechanic's lien, as it is intended to be.

The Florida courts have also sought interpretive aid in the example of the Miller Act, 40 U.S.C. §§ 270a et seq., after which section 255.05 is modeled. Board of Public Instruction v. Rood Const. Co., 166 So.2d 701 (Fla.Dist.Ct.App.1964). The ninety day notice period of the Miller Act begins "after the day on which the last of the labor was performed." Travelers Indemnity would conclude that since section 255.05 lacks this straightforward language, the Florida legislature must have intended a different rule. Had...

To continue reading

Request your trial
12 cases
  • Harvesters Group, Inc. v. Westinghouse Elec. Corp.
    • United States
    • Florida District Court of Appeals
    • June 7, 1988
    ... ... 2d DCA), cert. denied, 194 So.2d 617 (Fla.1966); see Gergora v. R.L. Lapp Forming, Inc., 619 F.2d 387 (5th Cir.1980). Cf. National Gypsum Co. v. Travelers ... ...
  • Greenblatt v. Delta Plumbing & Heating Corp.
    • United States
    • U.S. District Court — Southern District of New York
    • April 7, 1994
    ... ... Citing Crisafulli Brothers, Inc. v. Clanton, 128 A.D.2d 963, 512 N.Y.S.2d 927, 928 (1987), the Court ... Carter, 353 U.S. 210, 77 S.Ct. 793, 1 L.Ed.2d 776 (1957), nor Gergora v. R.L. Lapp Forming, Inc., 619 F.2d 387 (5th Cir.1980), support the ... ...
  • Xaros v. U.S. Fidelity and Guar. Co.
    • United States
    • U.S. Court of Appeals — Eleventh Circuit
    • July 7, 1987
    ... ... U.S. FIDELITY AND GUARANTY COMPANY and Darin & Armstrong, ... Inc., a foreign corporation, Defendants-Appellees ... No. 86-5172 ... United ... are directly in conflict with the Fifth Circuit's decision in Gergora v. R.L. Lapp Forming, Inc., 619 F.2d 387 (5th Cir.1980), and that of the ... ...
  • US v. Expert Environmental Control, Inc., Civ. A. 89-K-656.
    • United States
    • U.S. District Court — District of Colorado
    • March 5, 1992
    ... ... A majority of courts also follow this approach. See, e.g., Gergora v. R.L. Lapp Forming, Inc., 619 F.2d 387, 391 (5th Cir. 785 F. Supp. 898 1980) (state law case ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT