Gradco, Inc. v. St. Clair County Bd. of Educ.

Decision Date04 October 1985
Citation477 So.2d 365
Parties28 Ed. Law Rep. 687 GRADCO, INC., et al. v. ST. CLAIR COUNTY BOARD OF EDUCATION. 83-589.
CourtAlabama Supreme Court

John F. De Buys, Jr. of Corley, Moncus, Bynum & De Buys, Birmingham, for appellant Gradco, Inc.

Foster Etheredge and Ann McMahan Perry, of Spain, Gillon, Riley, Tate & Etheredge, Birmingham, for appellant U.S. Fidelity & Guar. Co.

William J. Trussell, Church, Trussell & Robinson, Pell City, for appellee.

ALMON, Justice.

The St. Clair County Board of Education (the Board) brought this action for breach of contract against Gradco, Inc., and its surety, United States Fidelity & Guaranty Company (USF & G). After a non-jury trial, the court awarded $55,254.39 to the Board against both defendants.

Gradco had contracted with the Board to perform landscaping work around the St. Clair County schools. After numerous delays, the Board terminated Gradco's right to proceed and hired another contractor to finish the job. The damages awarded were the increased cost of the new contract, plus liquidated damages based on the length of the delay, minus the retained amount owed to Gradco. Gradco argues that the Board prevented it from curing its breach by not considering a subcontract offer, that by this unreasonable refusal the Board failed to mitigate its damages, and that the liquidated damages provision in the contract imposed a penalty, not damages.

On October 5, 1977, Gradco entered into a contract with the Board whereby Gradco was to improve the sidewalks, curbs, grass, and general appearance of the grounds of the public schools in St. Clair County for $211,540.66. USF & G executed a performance bond and a payment bond on Gradco's behalf. The Soil Conservation Service (SCS) of the United States Department of Agriculture had prepared the plans for the work and supplied the form on which the contract between Gradco and the Board was written. SCS employees supervised Gradco's work and progress.

The Board gave Gradco notice to proceed on October 24. The contract called for work to be completed within 208 calendar days but also provided for winter shutdowns, which were not to be counted in the 208 days. Gradco began work in November and worked until the SCS declared a winter shutdown on November 21. The schedule called for Gradco to have performed 23% of the work by that time, but it had only completed 1.5%.

Before resuming in the spring, Gradco submitted a revised construction schedule. By May 27, 1978, Gradco should have finished 31% of the work, but had only finished 5.3%. On June 13, Gradco met with Jimmy Lee, the Board representative, and SCS employees to discuss the schedule. Mike Summers, the president of Gradco, explained that he was having difficulty finding a subcontractor to do the concrete work. The Board and the SCS gave him ten days to submit proposals for how he could meet the schedule. Gradco sent a letter on June 22 listing steps that it would take to improve progress. Although it made these changes, Gradco continued to fall behind.

The parties held another meeting on August 25. Gradco was told to submit another revised schedule and that its work would be reviewed in another ten days. The SCS informed Gradco that if progress was not satisfactory at that time, Gradco's right to proceed would be terminated. Gradco submitted a revised schedule on August 30. On September 11, it had completed 23.3% of the work. The revised schedule called for completion of 35.8% by that time; the original schedule had called for 76%. On September 13, Jimmy Lee mailed a letter (dated September 12) terminating Gradco's right to proceed. Gradco received this letter on September 15. The Board also sent a copy of the letter to USF & G.

In August, Gradco had started talking to Ben Miree of Miree Construction Company about Miree's completing the work under a subcontract. They prepared such a subcontract, and Miree submitted it to the Board for approval by letter dated September 13. Larry McRae, the SCS inspector, had known since September 6 or 7 of Miree's interest in subcontracting the remaining work, but had refused to allow Miree's representatives to inspect the job sites. When Lee received the proposed subcontract, McRae told him not to sign anything and did nothing to ascertain whether Miree would be an acceptable subcontractor.

After terminating Gradco's right to proceed under the contract, the Board sent a letter to six or eight contractors requesting bids on the remaining work. The only bid it received was from Miree. The Board rejected this bid and sent another letter to the same contractors inviting negotiations. Again, Miree was the only bidder. The Board and Miree entered into a contract on January 18, 1979, whereby Miree was to complete the work for $212,726.15. Miree began work in April of that year and finished on January 7, 1980.

The Board filed this action against Gradco and USF & G, as surety, on September 2, 1980. After discovery, the parties tried the case without a jury. The trial court entered final judgment for the Board on November 7, 1983, awarding $55,254.39, against both defendants. Gradco and USF & G filed a timely notice of appeal to this Court.

The contract between Gradco and the Board gave the Board the right to terminate Gradco's right to proceed with the work if Gradco "fail[ed] to prosecute the work ... with such diligence as will insure its completion within the time specified in this contract, or any extension thereof ...." The contract further provided:

"If fixed and liquidated damages are provided in the contract and if the Contracting Local Organization [the Board] so terminates the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs occasioned the Contracting Local Organization in completing the work."

The contract provided for liquidated damages in the amount of $83.00 per day, which was the amount the SCS calculated for the pay and expenses of its supervising personnel assigned to the job. The Board had contracted with the SCS for...

To continue reading

Request your trial
11 cases
  • Mills v. Wex-Tex Industries, Inc., 96-D-1616-S.
    • United States
    • U.S. District Court — Middle District of Alabama
    • September 25, 1997
    ... ... 1285 (M.D.Ala.1995); Saville v. Houston County Healthcare Auth., 852 F.Supp. 1512 (M.D.Ala.1994); Surrency v. Harbison, ... ...
  • Southtrust Bank v. Jones, Morrison, Womack
    • United States
    • Alabama Court of Civil Appeals
    • March 18, 2005
    ... ... a business credit card to LaCoste Construction Company, Inc. ("LCCI"), located in Mobile, Alabama. LCCI authorized nine ... See Lombardo v. County of Nassau, 6 Misc.3d 836, 838, 791 N.Y.S.2d 292, 295 ... ...
  • Whitney Bank v. Pullum-Cecilio, LLC.
    • United States
    • U.S. District Court — Southern District of Alabama
    • June 15, 2015
    ...party utilize the mitigation doctrine to shift the risk of harm to the non-breaching party. See, e.g., Gradco, Inc. v. St. Clair Cnty. Bd. of Educ., 477 So.2d 365, 368 (Ala. 1985) ("A party is obligated to mitigate damages only if they are reasonably foreseeable and the effort to avoid them......
  • EAST ALA. BEHAVIORAL MEDICINE v. Chancey
    • United States
    • Alabama Supreme Court
    • October 10, 2003
    ... ...         883 So.2d 167 In Solmica of Gulf Coast, Inc. v. Braggs, 285 Ala. 396, 232 So.2d 638 (1970), this ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT