Great Lakes Const. Co. v. Republic Creosoting Co.
Decision Date | 10 December 1943 |
Docket Number | No. 12607.,12607. |
Parties | GREAT LAKES CONST. CO. et al. v. REPUBLIC CREOSOTING CO. |
Court | U.S. Court of Appeals — Eighth Circuit |
William R. Bascom, of St. Louis, Mo. (William G. Pettus, Jr., and Arthur B. Shepley, Jr., both of St. Louis, Mo., McKnight, McLaughlin, Dunn & Sims, of Chicago, Ill., and Nagel, Kirby, Orrick & Shepley, of St. Louis, Mo., on the brief), for appellants.
Forrest M. Hemker, of St. Louis, Mo., and George A. Reilly, of Chicago, Ill. (Greensfelder & Hemker, of St. Louis, Mo., and Scott, MacLeish & Falk, of Chicago, on the brief), for appellee.
Before SANBORN, WOODROUGH, and RIDDICK, Circuit Judges.
This appeal is to reverse a judgment for $12,279.29, found to be the value of work and materials furnished by Republic Creosoting Company, a sub-contractor, to Great Lakes Construction Company, the prime contractor, in the construction of the Post Office Building at Eighteenth and Market Streets in St. Louis, Missouri. Republic intervened in the action brought by another materialman under the Heard Act, 40 U.S. C.A. § 270, against the bond supplied by Great Lakes as principal and several companies appellants as sureties pursuant to the terms of that statute. Republic originally had a sub-contract with Great Lakes to furnish the work and material to complete the wood flooring in the building for $32,500, but on the trial to the court without jury it was held that Republic had been prevented from the performance of its contract without its fault and that Great Lakes had breached it and the judgment for recovery on the bond was on the quantum meruit. A counterclaim for damages asserted by Great Lakes for alleged breach of the contract by Republic was dismissed.
On this appeal Great Lakes does not question that Republic furnished work and materials in the construction of the flooring in the building, nor that the fair value was as adjudicated, but it contends (1) that Republic's action against the bond was barred by the applicable time limitation of the Heard Act; and if it was not, (2) that the court erred in ascribing the breach of the sub-contract to Great Lakes instead of to Republic.
(1) The original Heard Act provisions as to the time for bringing action on public building contractors' bonds, 40 U.S.C.A. § 270, were repealed and amended by the Act of August 24, 1935, but the terms of the amendment continued them in force in respect to the contract here involved, 40 U.S.C.A. (1942) § 270, and the parties rightly agree that Republic's intervention here had to be filed within one year from "completion and final settlement" of the contract of the Great Lakes company. The question decided by the trial court and presented to this court by the appeal, is whether the "final settlement" was on August 24, 1940, or whether it was on November 13, 1940. The Republic's intervention was filed September 8, 1941, and was too late if the final settlement date was August 24, 1940, but it was within the year from November 13, 1940.
The contract of the Great Lakes Company for the construction of the building for $3,636,163 was entered into with the Procurement Division of the United States Treasury Department, but the functions of that division in respect to it were subsequently transferred to the Federal Works Agency. The administrative action of August 24, 1940, relied on by the Great Lakes company to establish "final settlement" on that date, was by the Federal Works Agency. Republic denies the finality of that action and contends that the "final settlement" is evidenced by certificate of the Comptroller General on November 13, 1940, as decided by the triel court.
It appears that: The contract between Great Lakes and the United States provided: "The compensation hereinbefore stipulated to be paid shall be reduced by the amount that the contracting officer, subject to the approval of the Comptroller General, shall find the cost of performing this contract is reduced solely by reason of the contractor not complying with the provisions of any code or codes of fair competition, or any related requirements (as provided in Executive Order Numbered 6646 of March 14, 1934); and such compensation shall be increased by the amount that the contracting officer, subject to the approval of the Comptroller General, shall find the cost of performing this contract has been increased solely by reason of compliance with any acts of Congress enacted after August 29, 1935, requiring the observance of minimum wages, maximum hours, or limitations as to age of employees in the performance of contracts with agencies of the United States."
The amount to be added or subtracted was a question for determination between Great Lakes and the United States. In addition, in August of 1939 there had been a flood in the post office which caused damage to certain electrical installations. A dispute arose between the United States and Great Lakes as to whether the building had been accepted at the time of the flood so that the loss was that of the United States or whether it had not been accepted so that the loss was that of Great Lakes. The amount involved was $11,911.38. There was also the question of the Government's right to damages for the delay in performance from February 28, 1938, to August, 1940.
On August 24, 1940, Neal A. Melick, Acting Commissioner of Public Buildings, addressed the following communication to the Federal Works Administrator:
To continue reading
Request your trial-
Allen v. Kraus
... ... Philadelphia, 326 Pa. 302, 192 A. 133; Great Lakes ... Const. Co. v. Creosoting Co., 139 F.2d 456; ... ...
-
Edwin J. Dobson, Jr., Inc. v. Rutgers, State University
...rights under the arrangements worked out for doing the work, except as provided in G4-F.1 et seq. In Great Lakes Constr. Co. v. Republic Creosoting Co., 139 F.2d 456 (8 Cir. 1943), plaintiff contracted with the United States for construction of a postoffice and subcontracted with defendant ......
-
Statler Mfg., Inc. v. Brown
...279 F.2d 200, 201 (6th Cir.1960); F.J. Lewis Mfg. Co. v. Snyder, 37 F.2d 299, 300 (6th Cir.1930); Great Lakes Const. Co. v. Republic Creosoting Co., 139 F.2d 456, 464 (8th Cir.1943); Hensler v. City of Los Angeles, 124 Cal.App.2d 71, 268 P.2d 12, 21 (1954); Walter Kidde Constructors, Inc. v......
-
Autrey v. Williams and Dunlap
...Co. v. Schaefer, 9 Cir. 1949, 173 F.2d 5, 7; Merando v. Mathy, 1945, 80 U.S.App.D.C. 281, 152 F.2d 21; Great Lakes Constr. Co. v. Republic Creosoting Co., 8 Cir. 1943, 139 F.2d 456, 464. 20 Later certain extras were authorized, bringing the total amount to $404,006. See 210 F.Supp. at 21 Ar......