Great Lakes Excavating, Inc. v. Dollar Tree Stores, Inc.

Citation959 N.W.2d 351,2021 WI App 23,397 Wis.2d 210
Decision Date30 March 2021
Docket NumberAppeal No. 2019AP2095
Parties GREAT LAKES EXCAVATING, INC., Plaintiff-Appellant, v. DOLLAR TREE STORES, INC., Defendant-Respondent, AMCON Design and Construction Co., LLC, Riverworks Development Corporation and John H. Burkemper, Defendants, Riverworks City Center, LLC, Intervenor-Respondent.
CourtCourt of Appeals of Wisconsin

On behalf of the plaintiff-appellant, the cause was submitted on the briefs of John E. Machulak of Machulak, Robertson & Sodos, S.C., Milwaukee.

On behalf of the intervenor-respondent, the cause was submitted on the brief of Jessica Haskell and Paul W. Zimmer of O'Neil, Cannon, Hollman, DeJong & Laing S.C., Milwaukee.

Before Dugan, Graham and Donald, JJ.

DONALD, J.

¶1 Great Lakes Excavating, Inc. (Great Lakes) appeals an order granting partial summary judgment to Riverworks City Center, LLC (Riverworks) and Dollar Tree Stores, Inc. (Dollar Tree) and an order dismissing Dollar Tree. Great Lakes contends that the circuit court erred in finding that its construction lien was waived, pursuant to WIS. STAT. § 779.05(1) (2019-20).1 We disagree and affirm.

BACKGROUND

¶2 According to Great Lakes, Riverworks contracted with AMCON Design and Construction Co., LLC, to build a commercial building with a parking lot. Before the start of construction, Dollar Tree agreed to lease a store at the site.

¶3 Great Lakes asserts that AMCON then subcontracted with Great Lakes for work relating to the parking lot. The total price of the original subcontract was $37,165. Soon after, Great Lakes discovered poor soil conditions, which required the removal of the bad soil, importation of stone, and installation of engineered fabric. AMCON signed a change order for Great Lakes to perform additional work for an undetermined price. As the work progressed, AMCON also asked Great Lakes to remove a concrete pad and furnish additional stone. Great Lakes provided two additional change orders for this work to AMCON, but did not receive signed copies back. After the work was completed, Great Lakes invoiced AMCON for a total of $222,238.

¶4 After failing to receive payment, the owner of Great Lakes, Duwayne L. Bruckner (Bruckner), went to AMCON's office. Great Lakes asserts that AMCON stated that all it could pay was $33,448, and provided Bruckner with a lien waiver document, titled "Waiver of Lien to Date." Great Lakes further asserts that Bruckner agreed to a partial waiver of the lien and crossed out the words "to date" and handwrote in the word "Partial." AMCON provided Great Lakes a check in the amount of $33,448.

¶5 The lien waiver appears in pertinent part as follows:

¶6 No additional payments were made and Great Lakes filed a Subcontractor Claim for Lien on Riverworks in the amount of $188,790, which represented the $222,238 bill minus the $33,448 paid.

¶7 Subsequently, Great Lakes filed a summons and complaint naming AMCON, Riverworks, and Dollar Tree as defendants. Great Lakes sought a money judgment for AMCON's breach of contract and to foreclose its lien against Riverworks. Both Riverworks and Dollar Tree filed an answer to the original complaint; AMCON did not appear or file an answer.2

¶8 Riverworks moved for partial summary judgment on the grounds that Great Lakes had waived all its lien rights because it did not expressly limit the waiver to a particular portion of work pursuant to the procedure set forth in WIS. STAT. § 779.05(1). Dollar Tree joined in Riverworks’ motion.

¶9 In response, Great Lakes argued that Riverworks’ argument "improperly render[ed] the handwritten word [P]artial’ [on the lien waiver] as surplusage" and that the word "Partial" was not ambiguous. In addition, Great Lakes argued that Riverworks was equitably estopped from asserting that the lien waiver was a full waiver. Great Lakes also separately filed an amended summons and complaint to add a third cause of action, unjust enrichment.3

¶10 In reply, Riverworks argued that the language in WIS. STAT. § 779.05(1) was dispositive and that estoppel was inapplicable as Riverworks was neither present nor involved with Great Lakes’ signing of the lien waiver.

¶11 A hearing was held on Riverworks’ summary judgment motion. The circuit court agreed with Riverworks and Dollar Tree that Great Lakes had not complied with the procedure set forth in WIS. STAT. § 779.05(1) for limiting the waiver to a particular portion of the work. The court stated that "[m]erely changing the title of the lien waiver, without additional explanation, does not specifically and expressly limit the waiver to apply to a particular portion of such labor, services, materials, plans, or specifications." Thus, the circuit court concluded that Great Lakes had waived its lien claim and granted the motion for partial summary judgment on Great Lakes’ lien foreclosure cause of action.

¶12 At the hearing, Great Lakes did not raise, and the circuit court did not address, Great Lakes’ equitable estoppel argument. Additionally, the unjust enrichment cause of action in the amended summons and complaint was not addressed.

¶13 Great Lakes then petitioned this court requesting interlocutory review, which we denied.

¶14 After the petition was denied, Great Lakes stipulated with Dollar Tree for the entry of a final order dismissing Dollar Tree from this case, which the circuit court granted. Great Lakes now appeals this order and the order granting partial summary judgment on Great Lakes’ lien foreclosure cause of action.4

All other causes of action, including the unjust enrichment claim, remain pending in the circuit court.

DISCUSSION

¶15 We review a grant of summary judgment de novo , applying the same methodology as the circuit court. Palisades Collection LLC v. Kalal , 2010 WI App 38, ¶9, 324 Wis. 2d 180, 781 N.W.2d 503. Summary judgment should be granted only "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." WIS. STAT. § 802.08(2).

¶16 In this case, whether summary judgment was appropriate turns on a question of statutory interpretation, which we also review de novo. Town of Wilson v. City of Sheboygan , 2020 WI 16, ¶12, 390 Wis. 2d 266, 938 N.W.2d 493.

¶17 When interpreting a statute, we start with the language of the statute. State ex rel. Kalal v. Circuit Ct. for Dane Cnty. , 2004 WI 58, ¶45, 271 Wis. 2d 633, 681 N.W.2d 110. If the meaning of the words of a statute are plain, we stop our inquiry and apply the words chosen by the legislature. Id. "Statutory language is given its common, ordinary, and accepted meaning, except that technical or specially-defined words or phrases are given their technical or special definitional meaning." Id. ¶18 Lien waivers are governed by WIS. STAT. § 779.05. Subsection (1) provides that a lien waiver document "shall be deemed to waive all lien rights of the signer" unless "the document specifically and expressly limits the waiver to apply to a particular portion of such labor, services, materials, plans, or specifications." Additionally, subsection (1) states that "[a]ny ambiguity ... shall be construed against the person signing it."

¶19 Great Lakes argues that the circuit court erred by finding that Great Lakes waived its construction lien in full. Great Lakes argues that by crossing out the phrase "to Date" and inserting the word "Partial," the parties intended that the waiver would not be a full waiver of the lien claim. In addition, Great Lakes asserts that the reference to "$33,448 Dollars" in the lien waiver document defined a "particular portion" of the work completed.

¶20 We disagree with Great Lakes. For the purposes of this opinion, we assume that the parties intended to limit the waiver to a portion of the work. However, to accomplish this purpose, Great Lakes was required to comply with the plain language of WIS. STAT. § 779.05(1), which it failed to do.

¶21 As noted above, under the plain language of the statute, in order to limit a lien...

To continue reading

Request your trial
1 cases
  • Great Lakes Excavating, Inc. v. Dollar Tree Stores, Inc.
    • United States
    • Wisconsin Supreme Court
    • June 22, 2022
    ...to a particular portion of the work," "such as the labor in the original contract, which totaled $37,165." Great Lakes Excavating, Inc. v. Dollar Tree Stores, Inc., 2021 WI App 23, ¶¶21–22, 397 Wis. 2d 210, 959 N.W.2d 351. The court emphasized the waiver's "broad[ ]" statement that Great La......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT