Griffis v. State
Decision Date | 06 October 1943 |
Docket Number | 8401 |
Citation | 69 S.D. 439,11 N.W.2d 138 |
Court | South Dakota Supreme Court |
Parties | WILLIAM C. GRIFFIS, SR., dba William C. Griffis & Son, Plaintiffs, v. STATE OF SOUTH DAKOTA, Defendant |
#8401—Motion granted
Wilson & Blethen, Mankato, Minn.
Lewis W. Bicknell, Webster, SD
Attorneys for Plaintiffs
George T. Mickelson, Attorney General
Ray F. Dreary, Asst. Attorney General, Pierre, SD
Attorneys for Defendant.
Opinion filed Oct 6, 1943
This is an original action in this court brought against the State to recover an amount alleged to be due plaintiffs for riprapping of embankment on US Highway No. 12 in Day County. Plaintiffs sought recovery upon six items. The Attorney General moved to dismiss the complaint, and this court granted the motion as to the first four items and denied the motion as to the other items. Griffis v. State 68 SD 360, 2 NW2d 666. Plaintiffs pursuant to stipulation filed an amended complaint, and as to the third cause of action alleged therein the Attorney General has moved to dismiss on the grounds that this court is without jurisdiction to render judgment because the statute (SDC 33.0604) giving consent by the state to be sued on claims disallowed by the State Auditor does not authorize the bringing on actions on claims for which there is no available appropriation, and that plaintiffs for a third cause of action fail to state a claim upon which relief may be granted.
The item in controversy is for “increased labor expense caused by state highway commission of South Dakota forcing stone to be used on this riprapping project of much larger size than specified in the contract and specifications,” and is the third item referred to in the former opinion. Plaintiffs agreed to furnish materials and to perform all labor under a written contract awarded on bids received after public notice. They were to be paid a fixed price of $1.84 per cubic yard for approximately 2,620 cubic yards of riprap fill and 9,450 cubic yards of hand placed riprap. The contract provided that plaintiffs were to furnish materials and perform all labor in conformity with the terms of the contract, the notice to contractors, proposal, plans and the standard specifications for road and bridges, and such notice, proposal, plans and specifications were made a part of the agreement as fully and to the same effect as if the same had been set forth in full in the body of the contract. Under the caption Rip-Rap Fill, there appears the following instruction in the standard specifications: And under the caption Hand Placed Rip-Rap, reference to material is as follows:
Plaintiffs allege that they were required by the engineer in charge to use stones weighing from 700 to 1,000 pounds “on the most of the 12,070 cubic yards of rip-rapping,” which were larger than the stone specified in the contract; that a “two-man” stone weighs approximately 200 pounds and can be lifted onto a truck or other conveyance by two men; that it required power hoists and other expensive equipment to load the heavier stone onto trucks; and that the additional cost of furnishing the larger stones in place of the material specified in the contract was the sum of $3,300, the amount sued for. It is further alleged that
The inspector or engineer in charge had no authority to vary the terms of the contract or to issue instructions contrary to the plans and specifications. The contract so specifically stated. It too contained the usual stipulation providing that no extra work was to be performed by the contractor without a written order. Stipulations requiring a written order for any alterations or extra work are frequently inserted in contracts for public works and have been construed by this court to be binding on the parties and to prevent a recovery for extras by a contractor when there is no compliance with such provision. England v. State, 61 SD 132, 246 NW 628; Kansas City Bridge Co. v. State, 61 SD 580, 250 NW 343.
It is the settled law of this state that an action under the provisions of SDC 33.0604 cannot be maintained if there is no available appropriation to pay the claim for which recovery is sought. Sigwald v. State, 50 SD 37, 208 NW 162; Brams v. State, 63 SD 571, 262 NW 89; Barnsdall Ref. Corp. v. Welsh, 64 SD 647, 269 NW 853. Funds appropriated for highway construction and maintenance are not available for payment of damages for breach of contract. Griffis v. State, supra, and cases cited.
The statute...
To continue reading
Request your trial