Hadeed v. Willamette Hi-Grade Concrete Co.

Decision Date30 September 1964
Docket NumberHI-GRADE
Citation395 P.2d 553,238 Or. 513
PartiesElias HADEED, Appellant, v. WILLAMETTECONCRETE CO., an Oregon Corporation, Respondent.
CourtOregon Supreme Court

Donald B. Bowerman, Portland, argued the cause for appellant. On the brief were Rask, Hefferin & Bowerman, Portland.

R. E. Kriesien, Portland, argued the cause for respondent. On the brief were Mize, Kriesien, Fewless & Douglass, Portland.

Before McALLISTER, C. J., and ROSSMAN, SLOAN, GOODWIN and LUSK, JJ.

LUSK, Justice.

This is another case involving the interpretation of the so-called 'pickup or delivery' provision of ORS 656.154(3). 1

Plaintiff was an employee of Contractors Incorporated, hereinafter called Contractors, which was engaged in the construction of a shopping center. Defendant Willamette Hi-Grade Concrete Co. had a contract to supply Contractors with ready-mixconcrete. Both employers were under the Workmen's Compensation Act.

Plaintiff brought this action to recover damages for personal injuries alleged to have been caused by the negligence of the defendant.

Defendant filed a supplemental answer pursuant to ORS 656.324(3), alleging that plaintiff's injury was sustained while he was on premises over which the two employers had joint supervision and control within the meaning of ORS 656.154(1) and (2). The trial court so held, and entered judgment barring the action, from which plaintiff has appealed. He contends that the case falls within the 'pickup or delivery' clause of the statute.

The facts are free from dispute. Defendant commenced supplying ready-mix concrete to Contractors on June 28, 1961. Plaintiff was a hod carrier and it was his duty to receive concrete in a 'buggy', or small wheelbarrow, as it came through a moveable chute attached to the rear of the delivery truck, and dump the concrete inside the forms on a wall in the process of construction. There were days when as many as a hundred trucks brought concrete to the job site. By July 12, 1961, the day of the accident, the wall had risen to a height of 12 or 15 feet, and to facilitate the work, a ramp was constructed by Contractors for the use of the defendant's trucks, which would be backed up far enough on the ramp to enable the concrete to be poured into the buggies at the top of the ramp.

The ramp was only wide enough to leave a distance of about a foot on either side of the wheels of a truck occupying it.

On the arrival of a truck a hod carrier at the top of the ramp would guide the driver as he backed up, and after the truck was halted on a signal from a hod carrier, the latter would swing the chute so as to bring the end of it close to his buggy, and the truck driver would get out of the truck and operate a mechanism at the rear which controlled the flow of concrete. When a buggy was filled, the hod carrier then would wheel it away. Sometimes there were several hod carriers waiting to receive their loads, and the chute would be swung from one buggy to another.

On the day of plaintiff's injury, however, he was the only hod carrier at the ramp. For present purposes, we may adopt the account in plaintiff's brief of what then occurred.

'* * * As the plaintiff was attempting to give the defendant's driver directions in backing his vehicle the chute swung to the driver's side of the truck thereby blocking the view that the driver had of the plaintiff. The plaintiff then walked a few feet down the ramp toward the truck, motioning for it to stop, and after the truck stopped and before plaintiff could push...

To continue reading

Request your trial
7 cases
  • Carter v. Sims Crane Service, Inc., 35136
    • United States
    • Florida Supreme Court
    • April 12, 1967
    ...J. Halloran & Co., 338 Mass. 189, 154 N.E.2d 582 (1958); Claussen v. Ireland, 216 Or. 289, 338 P.2d 676 (1959); Hadeed v. Wilamette Hi-Grade Concrete Co., 238 Or. 513, 395 P.5d 553 (1964) and Shoemaker v. Johnson, 241 Or. 511, 407 P.2d 257 ...
  • Cody v. Disco, Inc.
    • United States
    • Oregon Court of Appeals
    • May 26, 1981
    ...256 Or. 582, 475 P.2d 67 (1970) (unloading 16 to 24 foot lengths of culvert pipe weighing about 600 pounds). Hadeed v. Wil. Hi-Grade Concrete Co., 238 Or. 513, 395 P.2d 553 (1964), involved a defendant whose employers delivered as many as 100 truckloads of concrete per day to plaintiff's em......
  • Shoemaker v. Johnson
    • United States
    • Oregon Supreme Court
    • November 3, 1965
    ...where the workmen of both employers are jointly involved in the work out of which the accident arises. * * *' Hadeed v. Wil. Hi-Grade Concrete Co., 238 Or. 513, 395 P.2d 553 (1964), concerned facts legally identical to Pruett v. Lininger, supra (224 Or. 614, 356 P.2d 547). We '* * * As in t......
  • Green v. Market Supply Co.
    • United States
    • Oregon Supreme Court
    • January 27, 1971
    ...v. Nork was applied in Childers v. Schaecher Lbr. Co., 234 Or. 200, 380 P.2d 993 (1963) (unloading logs); Hadeed v. Wil. HiGrade Concrete Co., 238 Or. 513, 395 P.2d 553 (1964) (unloading ready mix concrete); Gorham v. Swanson, 253 Or. 133, 453 P.2d 670 (1969) (loading bundles of lumber); Pa......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT