Hartford Elec. Applicators of Thermalux, Inc. v. Alden

Decision Date22 July 1975
Citation169 Conn. 177,363 A.2d 135
CourtConnecticut Supreme Court
PartiesHARTFORD ELECTRIC APPLICATORS OF THERMALUX, INC. v. Arthur H. ALDEN et al.

Ivar A. Jozus, Middletown, for appellants-appellees (defendants).

Lester Katz, Hartford, for appellee-appellant (plaintiff).

Before HOUSE, C.J., and LOISELLE, MacDONALD, BOGDANSKI and LONGO, JJ.

LONGO, Associate Justice.

The plaintiff, a dry wall subcontractor, sued the defendant owner-contractors, claiming $5347 due under a contract. The defendants denied that the plaintiff performed under the contract and, in their special defense and counterclaim, alleged that the plaintiff failed to complete the work in a thorough and workmanlike manner as required by the contract. The defendants further counterclaimed for liquidated damages under the terms of the agreement, claiming that the work was completed 114 days late. The court rendered judgment for the plaintiff in the sum of $5347 and for the defendants under their counterclaim in the sum of $1350, from which both parties appealed.

The defendants claim that the plaintiff failed to satisfy the terms of the contract, which provided that the work of the plaintiff was to be performed 'in a good, substantial, thorough and workmanlike manner . . . and in every respect complete . . . to the full satisfaction of . . . (the) Architect'; the plaintiff, therefore, should not recover the amount due. '(W)here the court can see from the contract that it was the intent of the parties that the performance on the one side was not to be conditioned on the performance on the other, the promises will be construed as independent.' Finlay v. Swirsky, 103 Conn. 624, 635, 131 A. 420, 424; Williston, Contracts (3d Ed.) §§ 665, 669. Consequently, the parties can recover damages consistent with the losses suffered and they are left free to prove their damages by the requisite degree of persuasion. Thus, the terms of the contract requiring performance in a workmanlike manner to the satisfaction of the architect constitute a promise by the plaintiff. Strimiska v. Yates,158 Conn. 179, 185, 257 A.2d 814; Lach v. Cahill, 138 Conn. 418, 421, 85 A.2d 481. The finding, supported by the evidence printed in the appendix to the plaintiff's brief, supports the conclusion that the work was performed in a workmanlike manner. Consequently, the court correctly refused to award damages to the defendants on that counterclaim.

Another clause of the contract, however, unmistakably provides that payment by the defendants is conditioned upon approval by the architect, 1 who is also an owner-contractor and a codefendant. See Haugen v. Raupach,43 Wash.2d 147, 260 P.2d 340; Silverstone, 'Satisfaction in the Performance of Contracts,' 2 Conn.B.J. 10. The finding, as supported by the evidence printed in the appendices to the briefs, indicates that the plaintiff, in response to the architect's expression of dissatisfaction with certain portions of the work, effected some repairs. The architect, however, never returned to inspect the new work; he did not specify which work items remained outstanding and stood in the way of approval. Under these circumstances, where payment is conditioned on approval by the architect who is also a party to the contract, the architect owes the subcontractor, within reason, the duty to inspect the work and to specify those items which must be corrected in order to secure his approval. Clover Mfg. Co. v. Austin Co., 101 Conn. 208, 213-14, 125 A. 646; Frankfort Distilleries, Inc. v. Burns Bottling Machine Works, Inc., 174 Md. 12, 197 A. 599; Hood v. Meininger, 377 Pa. 342, 105 A.2d 126; Restatement, Contracts § 265. If it were otherwise, the contractor's promise to pay would be illusory; there would be no mutuality of consideration, thereby rendering suspect a standard contract provision widely used in the construction industry. Therefore, the failure of the defendant architect to fulfill his duty to inspect the work following the plaintiff's repairs, and to specify additional corrections required, constitutes a waiver by the defendants of the condition requiring satisfaction of the architect precedent to payment. Haugen v. Raupach, supra; Restatement, 1 Contracts § 303(d). Consequently, the defendants are estopped from raising any defense based upon that provision. Ravitch v. Stollman Poultry Farms, Inc., 165 Conn. 135, 149, 328 A.2d 711.

In its cross appeal, the plaintiff assigns error with respect to the granting of liquidated damages to the defendants. Substantial performance was completed twenty-five calendar days after the contract completion date. The plaintiff claims that the defendants breached the contract by delaying notification, for forty days past the agreed upon final date for such notification, that it might commence performance. 2 It argues that the defendants' breach entirely excuses it from the liquidated damages clause in the contract. In the alternative, the plaintiff argues that for purposes of computing liquidated damages, it should be credited with the forty-day delay of the defendants.

The trial court concluded that the date mentioned in the contract, April 20, was not a guaranteed commencement date, but merely an approximation of the earliest possible date that the plaintiff could start working. The plaintiff attacks this finding, claiming that the defendants' delay in notification until approximately June 1 that the work could begin constituted a breach of contract. The conclusion of the trial court is tested by the finding and must stand unless it is legally or logically inconsistent with the facts found or unless it involves the application of some erroneous rule of law material to the case. New Haven v. United Illuminating Co., Inc., Conn.,362 A.2d 785.

The plaintiff has also attacked the underlying finding of fact that '(t)he plaintiff and defendants agreed that the earliest possible date on which work by the plaintiff might begin was April 20, 1970.' 'A finding of fact is tested by the evidence printed in the appendices to the briefs.' State ex rel. Golembeske v. White, Conn., 362 A.2d 1354. The defendants have not filed an appendix to their reply brief and there is no other evidence in any other appendix which could support the finding of fact. It is their duty to print all material evidence in the appendices to the briefs; the court will not look beyond the appendices to examine the transcript unless justified by extraordinary circumstances. Practice Book §§ 645, 721; Barnini v. Sun Oil Co., 161 Conn. 59, 62, 283 A.2d 217; State v. Grimes, 154 Conn. 314, 326, 228 A.2d 141 and cases cited therein; Maltbie, Conn.App.Proc. §§ 330-331. Hence, we cannot rely on the unsupported finding of fact and must rely on the terms of the contract itself. At the outset, we note that the contract was prepared by the defendants. When there is ambiguity, we must construe contractual terms against the drafter. Ravitch v. Stollman Poultry Farms, Inc., supra. Clause fourteen of the contract provides that '(t)he Subcontractor knows that the Contractor must have his contract performed on or before the 20th day of April.' The contract and the finding show that the parties clearly intended time to be of the essence. Under these circumstances, the contract must be construed to mean that the defendants promised the plaintiff that the performance could commence on or before the 20th day of April. Since the defendants notified the plaintiff that it should commence construction a day or two before June 1, the defendants were forty days in breach of their promise to notify the plaintiff.

Even in the absence of an express covenant, 'there is an implied one that the contractor shall be permitted to proceed with his construction in accordance with the contract and that he shall be given possession of the premises to enable him to do so. Gray v. Bekins, 186 Cal. 389, 395, 199 P. 767; Rockwell v. New Departure Mfg. Co., . . . (102 Conn 255, 289, 128 A. 302). A delay caused by the owner may constitute a breach excusing performance as required by the contract. Stehlin-Miller-Henes Co. v. Bridgeport, 97 Conn. 657, 663, 117 A. 811; Guerini Stone Co. v. Carlin Construction Co., 248 U.S. 334, 340, 39 S.Ct. 102 (63 L.Ed. 275).' LiVolsi Construction Co. v. Shepard, 133 Conn. 133, 136, 48 A.2d 263, 265.

The defendants argue that due to the failure of the plaintiff to comply with a provision in the contract requiring the subcontractor to inform the contractor in writing of delays, the plaintiff should be estopped from complaining that the defendants delayed the contract. The contract provides that where the subcontractor is 'detained by other...

To continue reading

Request your trial
28 cases
  • Humphrey Place Condominium Association v. Snipes, No. 476794 (CT 3/17/2005)
    • United States
    • Connecticut Supreme Court
    • 17 d4 Março d4 2005
    ...is frequently invoked in the context of actions for breach of building contracts. See, e.g., Hartford Electrical Applicators of Thermalux, Inc. v. Alden, 169 Conn. 177, 363 A.2d 135 (1975). Moreover, in this and at least two other jurisdictions, courts have cited to the rule in the context ......
  • Old Colony Constr., LLC v. Town of Southington
    • United States
    • Connecticut Supreme Court
    • 21 d2 Abril d2 2015
    ...town's contribution to the delay rendered the liquidated damages provision unenforceable under Hartford Electric Applicators of Thermalux, Inc. v. Alden, 169 Conn. 177, 184, 363 A.2d 135 (1975). Old Colony further contends that, in light of change orders approved by the town acknowledging O......
  • S. H. V. C., Inc. v. Roy, 977
    • United States
    • Connecticut Superior Court
    • 20 d5 Fevereiro d5 1981
    ...the implied obligation of one party to a contract not to obstruct the performance of the other. Hartford Electric Applicators of Thermalux, Inc. v. Alden, 169 Conn. 177, 182, 363 A.2d 135 (1975); LiVolsi Construction Co. v. Shepard, 133 Conn. 133, 136, 48 A.2d 263 (1946). Where the breach o......
  • New Haven Water Co. v. Town of North Branford
    • United States
    • Connecticut Supreme Court
    • 10 d1 Abril d1 1978
    ... ... 126, 130, 374 A.2d 137; Hartford Electric Applicators of Thermalux, Inc. v ... Alden, 169 Conn. 177, 185n, 363 A.2d 135; Anonymous v ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT