Hector Martinez and Co. v. Southern Pac. Transp. Co.

Decision Date08 November 1979
Docket NumberNo. 77-2793,77-2793
PartiesHECTOR MARTINEZ AND COMPANY, Plaintiff-Appellant, v. SOUTHERN PACIFIC TRANSPORTATION CO., Defendant-Appellee.
CourtU.S. Court of Appeals — Fifth Circuit

Paul J. Chitwood, Dallas, Tex., for plaintiff-appellant.

Howard P. Newton, San Antonio, Tex., for defendant-appellee.

Appeal from the United States District Court for the Western District of Texas.

Before WISDOM, HILL and VANCE, Circuit Judges.

VANCE, Circuit Judge:

Martinez appeals the trial court's dismissal of his claim under 49 U.S.C. § 20(11) (Carmack Amendment to the Interstate Commerce Act) for losses resulting from delay and damage in transportation by carrier Southern Pacific. The district court granted Southern Pacific's motion under Rule 12(b)(6) to dismiss the claim for delay damages. It held that such damages are special and Martinez failed to allege that the carrier had any notice of the possibility that such damages would accrue upon a breach of the contract between the parties. We reverse and remand for trial on the claim for some but not all of the damages sought.

Martinez's agent delivered a 2400 Lima Dragline, Model 66, to the Penn Central Railroad, the origin carrier, on February 11, 1974, for shipment from New Philadelphia, Ohio to Eagle Pass, Texas. The dragline was loaded onto five separate railroad cars. A single uniform bill of lading, which described the dragline as "used strip mining machinery and parts," was issued by Penn Central, listing Martinez's agent in Eagle Pass as the consignee.

The last of the five cars, which were shipped separately, arrived in Eagle Pass on April 2, 1974. Martinez had to make reasonable repairs in the amount of $14,467.00 because the dragline was damaged in transit. These repairs were not completed until June 20, 1974. Martinez also alleges delay damages in the amount of $117,600.00 because the dragline could not be used from March 1, when he contends that the last of the cars should have arrived, until June 20. The claimed sum represents the dragline's fair rental value during this period.

After filing a claim as prescribed by the bill of lading, Martinez sued Southern Pacific, which as delivering carrier is liable for all recoverable damages. Martinez framed his original complaint to allege three separate claims under the Carmack Amendment. First, Martinez sought recovery of the cost of repairing the damage to the dragline. Second, he sought the refund of certain demurrage or storage charges assessed by Southern Pacific and paid at the time of delivery. Third, Martinez sought compensation for wrongful deprivation of the dragline's use during the periods of delay in transit and of repair.

Martinez and Southern Pacific had already settled the first two of these claims, when Southern Pacific filed its Rule 12(b)(6) motion to dismiss the third claim for loss of use. Southern Pacific argues that, because such damages are special, they are not recoverable under the Carmack Amendment absent notice of the possibility of such damages. The trial court denied this motion upon condition that Martinez amend his complaint to allege such notice. When Martinez refused, the district court granted Southern Pacific's motion under Rule 12(b)(6). This ruling, which had the effect of dismissing all that remained of Martinez's suit, is the basis of this appeal.

Martinez's delay claim involves two very different items. Lost use during the period of March 1 until April 2 resulted from a delay in transit. Lost use from April 2 until June 20 resulted from repair of the damaged goods. Neither the parties nor the district court have focused on the full import of this distinction. Martinez's claimed loss during repair is not severable from the physical damage to the dragline but is a part of the same legal claim. Thus Martinez necessarily settled his claim regarding damages for the repair period when he settled his first claim for damages to the dragline. The surviving issue is the appropriate measure of damages for the claimed loss resulting from Southern Pacific's unreasonable delay in transportation.

The Carmack Amendment 1 governs Martinez's claim for damages resulting from the delay in transit. That amendment incorporates common law principles for damages. F. J. McCarty Co. v. Southern Pacific Co., 428 F.2d 690, 693 (9th Cir. 1970); L. E. Whitlock Truck Service, Inc. v. Regal Drilling Co., 333 F.2d 488, 491 (10th Cir. 1964); J & H Flyer Inc. v. Pennsylvania Rr., 316 F.2d 203, 205 (2d Cir. 1963). In applying that statute, we first examine the extent to which the innocent party actually has been injured by the alleged breach. This inquiry assists in determining how the innocent party can be restored to the position in which he would have been had the contract been fully performed. See Liberty Navigation & Trading Co. v. Kinoshita & Co., 285 F.2d 343, 350 (2d Cir. 1960) (Lumbard, C. J., concurring in relevant part), Cert. denied, 366 U.S. 949, 81 S.Ct. 1904, 6 L.Ed.2d 1242 (1961); 11 Williston on Contracts § 1338, at 198 (3d ed. W. Jaeger 1968).

Normally, the remedy is an award of money damages to the aggrieved party as compensation for his economic injury. 2 This rule in effect protects the innocent party's expectation interest, giving him the " benefit of the bargain." 3 Martinez's alleged injury in this case was deprivation of the dragline's use between March 1, when it should have been delivered, and April 2. Besides compensating the injured plaintiff, the common law also seeks to protect the defendant from unforeseeable large losses to the plaintiff. 4 This limitation makes good sense. An award of full compensation for all of the plaintiff's losses due to the breach, no matter how unforeseeable or bizarre these losses are, would simply be unfair to the defendant as well as possibly paralyzing to commerce.

We next assess the reasonable foreseeability of the plaintiff's actual injury at the time of entry into the contract here the bill of lading. Globe Refining Co. v. Landa Cotton Oil Co., 190 U.S. 540, 544, 23 S.Ct. 754, 47 L.Ed. 1171 (1903); De Fore v. United States, 145 F.Supp. 484, 491 (M.D.Ga. 1956), Aff'd sub nom. Georgia Kaolin Co. v. United States, 249 F.2d 148 (5th Cir. 1957). Our analysis on this point begins with Hadley v. Baxendale, 9 Ex. 341, 156 Eng.Rep. 145 (1854). There, mill operators were forced to close operations to ship a broken shaft for repairs, and the carrier negligently delayed shipment. The carrier, however, had not been informed of the situation at the mill. The court refused to award profits lost during the period of delay because such damages were not in the contemplation of the parties. The court articulated the rules, still almost universally followed, 5 that general damages are awarded only if injury were foreseeable to a reasonable man and that special damages are awarded only if actual notice were given the carrier of the possibility of injury. 6 Damage is foreseeable by the carrier if it is the proximate and usual consequence of the carrier's action. 11 Williston on Contracts, supra § 1344, at 226.

Martinez asserts that his loss resulting from the delay in shipment was reasonably foreseeable when he entered the contract to transport his dragline. Hadley held that the damages arising from an inoperative mill were not foreseeable results of delayed shipment of a shaft, without specific notice. It was not obvious that the shaft in Hadley was an indispensable element of a mill. In the instant case, however, it was obvious that the dragline is a machine which of itself has a use value. Some cases after Hadley have suggested that the injury resulting from loss of a machine's use are not foreseeable results of delayed transport, because it is not a usual consequence although it is a proximate consequence. See 11 Williston on Contracts, supra § 1344, at 226-27. These decisions are unwarranted extensions of Hadley and employ arbitrary and inflexible definitions of foreseeability. Capital goods such as machinery have a use value, which may equal the rental value of the equipment or may be an interest value. The latter is ordinarily interest at the market rate on the value of the machine. It might be quite foreseeable that deprivation of the machine's use because of a carriage delay will cause a loss of rental value or interest value during the delay period. 7 See generally F. Kessler & G. Gilmore, Contracts 1042 (2d ed. 1970). We must not lose sight of the basic common law rule, enunciated in Hadley, of damages for foreseeable loss. The amount of damages that was reasonably foreseeable involves a fact question that Martinez is entitled to present to a jury.

Southern Pacific replies that it was as foreseeable that the goods were to be sold as that they were to be used. This contention proves too much because Hadley allows recovery for harms that should have been foreseen. The general rule does not require the plaintiff to show that the actual harm suffered was the Most foreseeable of possible harms. He need only demonstrate that his harm was not so remote as to make it unforeseeable to a reasonable man at the time of contracting. Even if the dragline were being shipped for sale it does not follow that delay in shipment would cause no recoverable loss.

Southern Pacific argues that, because only market value damages are foreseeable under common law, damages for lost rental value must be special and therefore require notice by Martinez. This argument confuses one common law method for computing damages with the underlying common law rule of awarding reasonable compensation for foreseeable injury from a contract's breach.

The common law employs a number of methods for computing damages recoverable for unreasonable delay in shipment. One of these is the market value test that measures damages by the diminution in the goods' value between the time of dispatch and the time of actual delivery. See 11 Williston on Contracts, supra...

To continue reading

Request your trial
46 cases
  • Mach Mold Inc. v. Clover Associates, Inc.
    • United States
    • U.S. District Court — Northern District of Illinois
    • 17 Agosto 2005
    ...reasonably foresee as the ordinary consequence of a breach at the time the contract was made. See id.; Hector Martinez & Co. v. S. Pac. Transp. Co., 606 F.2d 106, 108-11 (5th Cir.1989), cert. denied, 446 U.S. 982, 100 S.Ct. 2962, 64 L.Ed.2d 838 (1980). In order to recover special damages, t......
  • Dictor v. David & Simon, Inc.
    • United States
    • California Court of Appeals Court of Appeals
    • 14 Febrero 2003
    ...in the Carmack Amendment. (E.g., Project Hope v. M/V IBN SINA, supra, 250 F.3d at pp. 75-76 citing Hector Martinez & Co. v. Southern Pacific Transp. Co. (5th Cir.1979) 606 F.2d 106, 108 ["[The Carmack Amendment] incorporates common law principles for damages"]; Rafaella Gallery v. UPS 1993)......
  • Glass v. Crimmins Transfer Co.
    • United States
    • U.S. District Court — Central District of Illinois
    • 13 Enero 2004
    ...natural consequences of a breach when the contract was made. See Reed, 637 F.2d at 1305; Hector Martinez & Co. v. Southern Pacific Transportation Co., 606 F.2d 106, 108-11 (5th Cir.1979), cert. denied, 446 U.S. 982, 100 S.Ct. 2962, 64 L.Ed.2d 838 (1980). To recover special damages, the plai......
  • Rose v. Aaron (In re Rose)
    • United States
    • U.S. District Court — Eastern District of Texas
    • 25 Agosto 2021
    ... ... Worth 2017, pet. denied); see also Hector Martinez & ... Co. v. S. Pac. Transp. Co. , 606 F.2d ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT