Heidbrink v. Schaffner
Decision Date | 05 April 1910 |
Citation | 147 Mo. App. 632,127 S.W. 418 |
Parties | HEIDBRINK v. SCHAFFNER et al. |
Court | Missouri Court of Appeals |
A contractor, in a building contract which stipulated that the owner on obtaining a certificate of the architect might terminate the contract and complete the work, and that the expense incurred by the owner should be audited by the architect, whose certificate should be conclusive, gave a bond conditioned on his performance of the contract. He abandoned the work, and the owner completed it and sued on the bond for the cost of completing the work. Held, that the owner need not allege and prove that the certificate had been given as to the expense of completing the work.
4. CONTRACTS (§ 346)—BUILDING CONTRACTS —ACTION FOR BREACH—ISSUES AND PROOF.
Where, in an action on the bond of a building contractor, who had abandoned the work, which was completed by the owner, the issue raised by the pleadings involved only the reasonable cost of the completion of the work, that the contract provided that the expense incurred by the owner in completing the work should be certified by the architect, whose certificate should be conclusive, was not available as a defense because not pleaded.
Appeal from St. Louis Circuit Court; Hugo Muench, Judge.
Action by William Heidbrink against L. S. Schaffner and others. From a judgment for plaintiff, defendants appeal. Affirmed.
Jno. S. Leahy and Block & Sullivan, for appellants. Kurt Von Reppert, for respondent.
Defendant Schaffner contracted to erect a house for plaintiff for $5,800 by December 1, 1906. The work on the house progressed to a certain stage until December 1st, when Schaffner quit work, he testified, because he had no money to pay for labor or material, and claiming plaintiff had not paid him the installments of the price as agreed. Schaffner notified plaintiff he would not complete the house and abandoned the contract, so the jury must have found under the instruction about what facts would authorize a verdict for plaintiff. Plaintiff then took charge of the job and completed it, he alleges, at a cost above the agreed price of $1,841.22, for which sum he sued Schaffner and the other defendants who were his bondsmen. This notice was sent by Schaffner to plaintiff December 1st: At the date of said notice the building was not nearly finished, though it was to have been finished by said date. The contract for building the house was in writing and contained this article, which is material to the appeal:
The bond on which the present action was filed reads: ...
To continue reading
Request your trial- State ex rel. Donnell v. Searcy
- State ex rel. Massman Const. Co. v. Buzard
-
Myers v. Union Elec. Light & Power Co.
... ... 241; Hunt v. Owen Bldg. & Inv. Co., 219 S.W. 138; Berger Mfg. Co. v ... Crites, 178 Mo.App. 218, 165 S.W. 1163; Heidbrink v ... Schaffner, 147 Mo.App. 632, 127 S.W. 418; St. Joseph ... Iron Co. v. Halverson & Co., 48 Mo.App. 383. (2) The ... written contract ... ...
-
Myers v. Union Electric L. & P. Co.
...60 Mo. 241; Hunt v. Owen Bldg. & Inv. Co., 219 S.W. 138; Berger Mfg. Co. v. Crites, 178 Mo. App. 218, 165 S.W. 1163; Heidbrink v. Schaffner, 147 Mo. App. 632, 127 S.W. 418; St. Joseph Iron Co. v. Halverson & Co., 48 Mo. App. 383. (2) The written contract provided for settlement for the area......