Henderson & Russell Associates, Inc. v. Warwick Shopping Center, Inc., No. 751306
Docket Nº | No. 751306 |
Citation | 217 Va. 486, 229 S.E.2d 878 |
Case Date | November 24, 1976 |
Court | Supreme Court of Virginia |
Page 878
v.
WARWICK SHOPPING CENTER, INCORPORATED.
J. Davis Reed, III, Norfolk, for appellant.
Raymond H. Suttle, Newport News (Richard S. Gordon, Jones, Blechman, Woltz & Kelly, P.C., Newport News, on brief), for appellee.
Before I'ANSON, C.J., and CARRICO, HARRISON, COCHRAN, HARMAN, POFF and COMPTON, JJ.
COCHRAN, Justice.
Building & Design, Inc., the general contractor, entered into a contract in 1973 to complete a partially constructed theater building in the City of Newport News for the owner, Warwick Shopping Center, Incorporated (Warwick), for $105,700. After payments in the aggregate amount of $72,626.83 had been made to the general contractor by Warwick, the general contractor defaulted in February, 1974, when the project was approximately 25% Unfinished. Thereafter, a subcontractor, Henderson & Russell Associates, Inc. (Henderson), timely filed a memorandum of mechanic's lien for the balance due it by the general contractor, had copies of the memorandum served on the general contractor and on Warwick,
Page 879
and instituted this chancery cause to enforce its lien against the property.[217 Va. 487] The facts were stipulated. The balance payable by the general contractor to Henderson for work completed on the building, after allowing credit for unfinished work and certain materials recovered from the job site pursuant to a separate law action in detinue, was the sum of $25,534.56, with interest from February 27, 1974. The balance payable by Warwick to the general contractor under the contract if the contract had been satisfactorily completed was $33,073.17. Warwick, which had neither completed the building nor contracted to have it completed at the time of trial some eighteen months after the general contractor defauled, had received from another contractor an estimate of $75,000 for the cost of completion.
On these facts the trial court ruled, without giving reasons for the ruling, that Henderson's lien was not inforceable. Henderson has appealed from the final decree entered on August 21, 1975, which dismissed its bill of complaint and awarded judgment to Warwick.
Under the provisions of Code § 43--7, 1 the lien of a subcontractor is limited to the amount in which the owner is indebted to the general contractor, at or after the time the owner is given notice of the subcontractor's claim. Mills v....
To continue reading
Request your trial-
Bauer v. Harn, No. 791213
...definitive of issues. McLaughlin v. Gholson, 210 Va. 498, 500, 171 S.E.2d 816, 818 (1970). See also Henderson & Russell v. Warwick, 217 Va. 486, 488, 229 S.E.2d 878, 880 (1976). In the present case, the parties by stipulation carefully and clearly framed not only the dispositive issue b......
-
Bauer v. Harn, No. 791213
...definitive of issues. McLaughlin v. Gholson, 210 Va. 498, 500, 171 S.E.2d 816, 818 (1970). See also Henderson & Russell v. Warwick, 217 Va. 486, 488, 229 S.E.2d 878, 880 (1976). In the present case, the parties by stipulation carefully and clearly framed not only the dispositive issue b......