Henry Ripley v. United States No 498 United States v. Henry Ripley No 499, Nos. 498 and 499

CourtUnited States Supreme Court
Writing for the CourtLamar
Citation223 U.S. 750,32 S.Ct. 352,56 L.Ed. 614,223 U.S. 695
Decision Date11 March 1912
Docket NumberNos. 498 and 499
PartiesHENRY C. RIPLEY, Appt., v. UNITED STATES. NO 498. UNITED STATES, Appt., v. HENRY C. RIPLEY. NO 499

223 U.S. 695
32 S.Ct. 352
223 U.S. 750
56 L.Ed. 614
HENRY C. RIPLEY, Appt.,

v.

UNITED STATES. NO 498. UNITED STATES, Appt., v. HENRY C. RIPLEY. NO 499.

Nos. 498 and 499.
Submitted March 10, 1911.
Decided March 11, 1912.

Messrs. William H. Robeson, Benjamin Carter, and F. Carter Pope for ripley.

Assistant Attorney General Thompson and Mr. Philip M. Ashford for the United States.

Statement by Mr. Justice Lamar:

Appeal and cross appeal from a judgment by the court of claims for $14,732.05 in favor of Henry C. Ripley against the United States, in a suit for the recovery of damages in connection with the construction of a public work, consequent upon the action of the agent in charge.

By the act of June 13, 1902 (32 Stat. at L. 340, chap. 1079), Congress appropriated $250,000 for the completion of the work of improving the harbor of Aransas Pass, Texas. The contract was awarded to Henry C. Ripley. It provided for

Page 696

the completion of a jetty, having a brush foundation, to be covered with a layer of stone, on which was to be built a superstructure, with sloping sides and a top width of 10 feet. This superstructure was to be formed of a core or mound of riprap, 'and when, in the judgment of the United States agent in charge, this mound has become sufficiently consolidated, its gaps shall be filled and its crest leveled; . . . large blocks shall then be bedded in the crest of the mound.'

It was provided that——

'Where the contract contemplates the placing of the materials in the work, the material shall be placed securely and carefully where directed by the U. S. agent in charge. . . .

'All material furnished and work done under this contract shall, before being accepted, be subject to a rigid inspection by an inspector appointed on the part of the government, and such as does not conform to the specifications set forth in this contract shall be rejected. The decision of the engineer officer in charge as to quality and quantity shall be final.'

The contract also provided that the work should be executed under the supervision of the engineer officer in charge or his duly authorized agent. The United States was to employ one or more inspectors, and the contractor, without additional compensation, was bound to furnish facilities for the inspection of work and material. The contractor was to furnish extra labor at cost prices, as determined by the engineer, and should furnish board and lodging to government employees at reasonable rates satisfactory to the engineer. If the work was not diligently prosecuted, the contract might be annulled, or the engineer in charge, 'with the prior sanction of the Chief of Engineers, may waive for a reasonable period the limit originally set for the completion of the work, and remit the charges for the expenses of superintendence and inspec-

Page 697

tion for so much time as, in the judgment of the engineer officer in charge, may actually have been lost on account of . . . violence of the elements, or by epidemic, or local or state quarantine restrictions, or other unforeseeable causes of delay arising from no fault of the contractor, and which actually prevented him from commencing or completing the work within the period required by the contract.

Claimant entered upon the performance of the contract August 18, 1903, and completed 2,100 feet of jetty when operations ceased about September 17, 1904, owing to the exhaustion of the appropriation.

About the time work began, without fault on the part of the contractor or of the United States, there was a delay of about thirty days, due to the fact that the contractor's tug, while in charge of a licensed pilot, was grounded on a sand bar. The government apparently incurred expenses for inspection during this period and deducted that amount from Ripley's account.

Owing to an epidemic of yellow fever the force of the contractor was disorganized, and work was necessarily suspended for thirty days. The government did not charge him with inspection expenses during the fifteen days the quarantine was in force, in a city through which the cars hauling the material were prevented from passing. And the court held also that Ripley was not chargeable with the inspection expenses for the other fifteen days, during which his force was scattered as a result of the epidemic.

During the progress of the work, a large number of blocks were rejected by the inspector as not conforming to specifications. 'Many of those so rejected were afterwards accepted, but ninety of the stones offered as crest blocks were rejected as such, and were accepted and used as riprap and paid for as such. The difference in the amount paid claimant for said stones used as riprap and

Page 698

the amount he would have received if they had been used as crest blocks' was allowed him by the court of claims. It found that 'he was compelled to furnish other crest blocks to take the place of those rejected, which caused a delay of ten days to claimant in the completion of the work.'

It appears that the rejection of these blocks was due to a difference in the method of measurement, the inspector insisting that the blocks should be measured at the narrowest, thinnest, and shortest points. The contractor contended that mean or average measurements should be taken, claiming that this was the understanding of himself and the officer who drew the specifications. The engineer at Galveston thereupon suggested that the matter should be referred to the Chief of Engineers in Washington; and later a supplementary agreement was drawn, which permitted the use of blocks 'which would make the work as stable, or more stable, than if the dimensions conformed strictly to the letter of the specifications. In consideration of which change the contractor agrees to accept $5 per ton for all blocks received under the supplementary agreement which would have been rejected under the original specification.'

The plaintiff's claim for additional compensation for extra labor furnished the government and for board and lodging furnished its employees was rejected by the court, as also his claim for damages for double handling caused by the inspector's refusal to permit him to unload certain material on the jetty.

The contractor's principal claim, however, was for damage caused by the delay resulting from the refusal of the inspector in charge to permit crest blocks to be laid after the core had fully consolidated. As long as the jetty was uncovered by these blocks it was subject to the rough action of...

To continue reading

Request your trial
68 practice notes
  • Tobin Quarries v. Central Nebraska Public P. & I. Dist., Civil Action No. 57.
    • United States
    • United States District Courts. 8th Circuit. United States District Court of Nebraska
    • January 8, 1946
    ...and specifications" and otherwise expressly committed to him the determination of the very questions at issue. In Ripley v. United States, 223 U.S. 695, 750, 32 S.Ct. 352, 56 L.Ed. 614, the engineer's decision was held final upon matters of detail that in the contract were explicitly commit......
  • McCullough v. Clinch-Mitchell Const. Co., No. 9810.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (8th Circuit)
    • May 22, 1934
    ..."the contract did not contemplate that the opinion of the court should be substituted for that of the engineer" (Ripley v. United States, 223 U. S. 695, 704, 32 S. Ct. 352, 356, 56 L. Ed. 614); and, concerning a similar matter, "his action cannot, therefore, be subjected to the revisory pow......
  • In re Carozza, Bankruptcy No. 891-83188-20. Adv. No. 891-8450-20.
    • United States
    • United States Bankruptcy Courts. Second Circuit. U.S. Bankruptcy Court — Eastern District of New York
    • May 10, 1994
    ...an intention to cheat or be dishonest.\' U.S. v. Wunderlich, 342 U.S. 98, 72 S.Ct. 154, 96 L.Ed. 113 (1951); Ripley v. United States, 223 U.S. 695, 750, 32 S.Ct. 352, 56 L.Ed. 614 (1912). . . . `The courts almost uniformly hold that an action for false representations, 167 BR 335 called als......
  • 31 658 Contractors, Inc v. United States 8212 88, No. 70
    • United States
    • U.S. Supreme Court
    • October 21, 1971
    ...S.F. & C.R. Co. v. Price (supra).' Id., at 602, 20 S.Ct., at 233. The Court also followed the Kihlberg rule in Ripley v. United States, 223 U.S. 695, 701—702, 704, 32 S.Ct. 352, 355—356, 56 L.Ed. 614 (1912), and Merrill-Ruckgaber Co. v. United States, 241 U.S. 387, 36 S.Ct. 662, 60 L.Ed. 10......
  • Request a trial to view additional results
68 cases
  • Tobin Quarries v. Central Nebraska Public P. & I. Dist., Civil Action No. 57.
    • United States
    • United States District Courts. 8th Circuit. United States District Court of Nebraska
    • January 8, 1946
    ...and specifications" and otherwise expressly committed to him the determination of the very questions at issue. In Ripley v. United States, 223 U.S. 695, 750, 32 S.Ct. 352, 56 L.Ed. 614, the engineer's decision was held final upon matters of detail that in the contract were explicitly commit......
  • McCullough v. Clinch-Mitchell Const. Co., No. 9810.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (8th Circuit)
    • May 22, 1934
    ..."the contract did not contemplate that the opinion of the court should be substituted for that of the engineer" (Ripley v. United States, 223 U. S. 695, 704, 32 S. Ct. 352, 356, 56 L. Ed. 614); and, concerning a similar matter, "his action cannot, therefore, be subjected to the revisory pow......
  • In re Carozza, Bankruptcy No. 891-83188-20. Adv. No. 891-8450-20.
    • United States
    • United States Bankruptcy Courts. Second Circuit. U.S. Bankruptcy Court — Eastern District of New York
    • May 10, 1994
    ...an intention to cheat or be dishonest.\' U.S. v. Wunderlich, 342 U.S. 98, 72 S.Ct. 154, 96 L.Ed. 113 (1951); Ripley v. United States, 223 U.S. 695, 750, 32 S.Ct. 352, 56 L.Ed. 614 (1912). . . . `The courts almost uniformly hold that an action for false representations, 167 BR 335 called als......
  • 31 658 Contractors, Inc v. United States 8212 88, No. 70
    • United States
    • U.S. Supreme Court
    • October 21, 1971
    ...S.F. & C.R. Co. v. Price (supra).' Id., at 602, 20 S.Ct., at 233. The Court also followed the Kihlberg rule in Ripley v. United States, 223 U.S. 695, 701—702, 704, 32 S.Ct. 352, 355—356, 56 L.Ed. 614 (1912), and Merrill-Ruckgaber Co. v. United States, 241 U.S. 387, 36 S.Ct. 662, 60 L.Ed. 10......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT