Henry Ripley v. United States No 498 United States v. Henry Ripley No 499, s. 498 and 499
Court | United States Supreme Court |
Writing for the Court | Lamar |
Citation | 223 U.S. 750,32 S.Ct. 352,56 L.Ed. 614,223 U.S. 695 |
Parties | HENRY C. RIPLEY, Appt., v. UNITED STATES. NO 498. UNITED STATES, Appt., v. HENRY C. RIPLEY. NO 499 |
Docket Number | Nos. 498 and 499,s. 498 and 499 |
Decision Date | 11 March 1912 |
Messrs. William H. Robeson, Benjamin Carter, and F. Carter Pope for ripley.
Assistant Attorney General Thompson and Mr. Philip M. Ashford for the United States.
Statement by Mr. Justice Lamar:
Appeal and cross appeal from a judgment by the court of claims for $14,732.05 in favor of Henry C. Ripley against the United States, in a suit for the recovery of damages in connection with the construction of a public work, consequent upon the action of the agent in charge.
By the act of June 13, 1902 (32 Stat. at L. 340, chap. 1079), Congress appropriated $250,000 for the completion of the work of improving the harbor of Aransas Pass, Texas. The contract was awarded to Henry C. Ripley. It provided for the completion of a jetty, having a brush foundation, to be covered with a layer of stone, on which was to be built a superstructure, with sloping sides and a top width of 10 feet. This superstructure was to be formed of a core or mound of riprap, 'and when, in the judgment of the United States agent in charge, this mound has become sufficiently consolidated, its gaps shall be filled and its crest leveled; . . . large blocks shall then be bedded in the crest of the mound.'
It was provided that——
'Where the contract contemplates the placing of the materials in the work, the material shall be placed securely and carefully where directed by the U. S. agent in charge. . . .
The contract also provided that the work should be executed under the supervision of the engineer officer in charge or his duly authorized agent. The United States was to employ one or more inspectors, and the contractor, without additional compensation, was bound to furnish facilities for the inspection of work and material. The contractor was to furnish extra labor at cost prices, as determined by the engineer, and should furnish board and lodging to government employees at reasonable rates satisfactory to the engineer. If the work was not diligently prosecuted, the contract might be annulled, or the engineer in charge, 'with the prior sanction of the Chief of Engineers, may waive for a reasonable period the limit originally set for the completion of the work, and remit the charges for the expenses of superintendence and inspec- tion for so much time as, in the judgment of the engineer officer in charge, may actually have been lost on account of . . . violence of the elements, or by epidemic, or local or state quarantine restrictions, or other unforeseeable causes of delay arising from no fault of the contractor, and which actually prevented him from commencing or completing the work within the period required by the contract.
Claimant entered upon the performance of the contract August 18, 1903, and completed 2,100 feet of jetty when operations ceased about September 17, 1904, owing to the exhaustion of the appropriation.
About the time work began, without fault on the part of the contractor or of the United States, there was a delay of about thirty days, due to the fact that the contractor's tug, while in charge of a licensed pilot, was grounded on a sand bar. The government apparently incurred expenses for inspection during this period and deducted that amount from Ripley's account.
Owing to an epidemic of yellow fever the force of the contractor was disorganized, and work was necessarily suspended for thirty days. The government did not charge him with inspection expenses during the fifteen days the quarantine was in force, in a city through which the cars hauling the material were prevented from passing. And the court held also that Ripley was not chargeable with the inspection expenses for the other fifteen days, during which his force was scattered as a result of the epidemic.
During the progress of the work, a large number of blocks were rejected by the inspector as not conforming to specifications. was allowed him by the court of claims. It found that 'he was compelled to furnish other crest blocks to take the place of those rejected, which caused a delay of ten days to claimant in the completion of the work.'
It appears that the rejection of these blocks was due to a difference in the method of measurement, the inspector insisting that the blocks should be measured at the narrowest, thinnest, and shortest points. The contractor contended that mean or average measurements should be taken, claiming that this was the understanding of himself and the officer who drew the specifications. The engineer at Galveston thereupon suggested that the matter should be referred to the Chief of Engineers in Washington; and later a supplementary agreement was drawn, which permitted the use of blocks
The plaintiff's claim for additional compensation for extra labor furnished the government and for board and lodging furnished its employees was rejected by the court, as also his claim for damages for double handling caused by the inspector's refusal to permit him to unload certain material on the jetty.
The contractor's principal claim, however, was for damage caused by the delay resulting from the refusal of the inspector in charge to permit crest blocks to be laid after the core had fully consolidated. As long as the jetty was uncovered by these blocks it was subject to the rough action of the waves, and the plaintiff's employees were deprived of the advantage of working in still water on the lee side of the jetty. The work began August 18, 1903, and the court found as a fact
...
To continue reading
Request your trial-
Charles I. Hosmer, Inc. v. Commonwealth
...New England Railroad Corp., 230 Mass. 483, 495, 496, 120 N.E. 120;Hurley v. Boston, 244 Mass. 466, 138 N.E. 838;Ripley v. United States, 223 U.S. 695, 701, 750,32 S.Ct. 352, 56 L.Ed. 614;Montgomery v. New York, 151 N.Y. 249, 45 N.E. 550. There is nothing in the contention that the plea shou......
-
United States v. Lennox Metal Manufacturing Co.
...in United States v. Wunderlich, 342 U.S. 98, 72 S.Ct. 154, 96 L.Ed. 113, and to restore the views expressed in Ripley v. U. S., 223 U.S. 695, 701-702, 32 S.Ct. 352, 56 L.Ed. 614, i. e., that where the power of the government under a contract is complete and its agent's decision conclusive, ......
-
In re Carozza
...intention to cheat or be dishonest.\' U.S. v. Wunderlich, 342 U.S. 98, 72 S.Ct. 154, 96 L.Ed. 113 (1951); Ripley v. United States, 223 U.S. 695, 750, 32 S.Ct. 352, 56 L.Ed. 614 (1912). . . . `The courts almost uniformly hold that an action for false representations, called also an action of......
-
McCullough v. Clinch-Mitchell Const. Co.
...did not contemplate that the opinion of the court should be substituted for that of the engineer" (Ripley v. United States, 223 U. S. 695, 704, 32 S. Ct. 352, 356, 56 L. Ed. 614); and, concerning a similar matter, "his action cannot, therefore, be subjected to the revisory power of the cour......
-
The Construction Industry in the U.S. Supreme Court: Part 1, Contract Law
...v. Joseph A. Holpuch Co., 328 U.S. 234 (1946); United States v. Callahan Walker Constr. Co., 317 U.S. 56 (1942); Ripley v. United States, 223 U.S. 695 (1912); United States v. Gleason, 175 U.S. 588 (1900). 67. Gleason , 175 U.S. at 602. 68. United States v. Moorman, 338 U.S. 457 (1950). 69.......