Hereford v. D.R. Horton, Inc.

Citation13 So.3d 375
Decision Date09 January 2009
Docket Number1070396.
PartiesSherry Gay HEREFORD, individually and as mother and next friend of Alyssa Hereford, her minor daughter v. D.R. HORTON, INC.
CourtSupreme Court of Alabama

William Eugene Rutledge of Rutledge & Yaghmai, Birmingham, for appellant.

D. Christopher Carson and Jason R. Bushby of Burr & Forman, LLP, Birmingham, for appellee.

On Application for Rehearing

SEE, Justice.

The opinion of September 5, 2008, is withdrawn, and the following opinion is substituted therefor.

Sherry Gay Hereford, individually and as mother and next friend of Alyssa Hereford, her minor daughter, appeals from a judgment of the Shelby Circuit Court, affirming a summary judgment entered by the arbitrator in favor of D.R. Horton, Inc. (hereinafter "Horton"). We affirm.

Facts and Procedural History

On January 6, 2003, Sherry Gay Hereford entered into a real-estate contract with Horton for the purchase of a newly constructed house that Horton had built. The contract included a one-year limited warranty that provided that Horton was responsible for repairing any latent defects in the house. The limited warranty expressly disclaimed all other warranties, whether express or implied, and provided that the limited warranty excluded recovery for "[i]ncidental, consequential, or secondary damages caused by a breach of this warranty." The limited warranty also contained an arbitration clause that provided that any dispute arising under the limited warranty shall be submitted to arbitration in accordance with the Federal Arbitration Act, 9 U.S.C. § 1 et seq.

Several months after the Herefords moved into the house, they discovered water damage in the third bedroom of the house. Hereford notified Horton of the damage, and a representative of Horton went to the house to investigate the cause of the water damage. Horton learned that the water damage was being caused by leakage from a condensation drain pipe for the heating, ventilation, and air-conditioning ("HVAC") system, which had become separated at one of its joints. Horton repaired the separation in the pipe joint, removed and replaced the damaged carpet, baseboards, insulation, and sheet rock in the bedroom, and sprayed the affected areas with a bleach-detergent solution. Horton planned to make further repairs to the bedroom; however, a dispute arose between Hereford and Horton regarding the extent of the repairs, and Hereford refused to allow Horton to make any further repairs to the house unless Horton agreed to meet Hereford's specific demands regarding the repairs.

Hereford hired Michael Ridge, a certified industrial hygienist, to inspect the house and to determine what measures were necessary to repair the damage caused by the leak in the HVAC pipe. The report prepared by Ridge recommended treating the entire house for mold. Specifically, Ridge's report recommended that the third bedroom should be enclosed with a barrier maintained with a high-efficiency particulate-air filtration system to prevent the spread of mold while the third bedroom was being treated. The report further advised that all the carpet and padding should be removed from the house, that the entire house should be cleaned, and that the contents of the house should be removed and stored during the repairs and treatment for mold. Concerned about the possible health hazards caused by exposure to mold, the Herefords moved out of the house and into a furnished apartment.

Hereford filed a claim under her homeowner's insurance policy with Alfa Insurance Company ("Alfa"), requesting that Alfa pay for the remediation of the Herefords' house and for the rental of the apartment. Alfa agreed to Hereford's requests and hired Pro-Care Complete Restoration Services, Inc., a professional remediation firm, to treat and repair the Herefords' house. Alfa paid over $20,000 for the services performed by Pro-Care. The Herefords moved back into their house after Pro-Care finished treating the house for mold and made the necessary repairs.

On February 27, 2004, Hereford sued Horton, claiming that Horton had breached the limited warranty by failing to repair the damage caused by the leak in the unattached HVAC pipe. Horton moved the trial court to dismiss Hereford's action or, in the alternative, to stay the proceedings and compel arbitration under 9 U.S.C § 1 et seq., the Federal Arbitration Act. Before the trial court ruled on Horton's motion, counsel for Horton notified the trial court that both sides had agreed to enter into settlement negotiations and, in the event that settlement negotiations were unsuccessful, to submit the dispute to a mutually agreeable form of binding arbitration. Thereafter, the trial court placed this case on the administrative docket pending a settlement or resolution of the dispute by an arbitrator.

The settlement negotiations between Hereford and Horton were unsuccessful, and the dispute was submitted to arbitration. On August 18, 2006, Horton moved the arbitrator for a summary judgment, arguing that it had not breached the limited warranty or, alternatively, that even if it had breached the limited warranty, it was not liable for that breach because, it argued, the damages sought by Hereford were only consequential damages, the recovery of which was barred by the limited warranty. Hereford responded to Horton's summary-judgment motion, arguing that the provision in the limited warranty excluding the recovery of consequential damages was not enforceable because, she argued, the limited warranty had failed to meet its essential purpose. The arbitrator entered a summary judgment in favor of Horton and dismissed Hereford's complaint, finding that Hereford could not prevail on her breach-of-warranty claim because Hereford's damages either were covered by her homeowner's insurance policy or were excluded under the limited warranty as consequential damages.

Hereford appealed the arbitrator's decision to the Shelby Circuit Court, and Horton moved that court to confirm the arbitrator's decision. The trial court determined that the arbitrator's decision was due to be confirmed, and it entered an order in accordance with that finding. Hereford now appeals.

Standard of Review

In R.P. Industries, Inc. v. S & M Equipment Co., 896 So.2d 460 (2004), this Court reviewed the trial court's order granting a motion to confirm an arbitration award and denying the opposing party's motion to vacate that award. We stated:

"`Where parties, as in this case, have agreed that disputes should go to arbitration, the role of the courts in reviewing the arbitration award is limited. Transit Casualty Co. v. Trenwick Reinsurance Co., 659 F.Supp. 1346 (S.D.N.Y. 1987), affirmed, 841 F.2d 1117 (2d Cir. 1988); Saxis Steamship Co. v. Multifacs International Traders, Inc., 375 F.2d 577 (2d Cir.1967). On motions to confirm or to vacate an award, it is not the function of courts to agree or disagree with the reasoning of the arbitrators. Application of States Marine Corp. of Delaware, 127 F.Supp. 943 (S.D.N.Y. 1954). Courts are only to ascertain whether there exists one of the specific grounds for vacation of an award. Saxis Steamship Co. A court cannot set aside the arbitration award just because it disagrees with it; a policy allowing it to do so would undermine the federal policy of encouraging the settlement of disputes by arbitration. United Steelworkers of America v. Enterprise Wheel & Car Corp., 363 U.S. 593, 80 S.Ct. 1358, 4 L.Ed.2d 1424 (1960); Virgin Islands Nursing Association's Bargaining Unit v. Schneider, 668 F.2d 221 (3d Cir.1981). An award should be vacated only where the party attacking the award clearly establishes one of the grounds specified [in 9 U.S.C. § 10]. Catz American Co. v. Pearl Grange Fruit Exchange, Inc., 292 F.Supp. 549 (S.D.N.Y.1968).'"

896 So.2d at 464 (quoting Maxus, Inc. v. Sciacca, 598 So.2d 1376, 1380-81 (Ala. 1992)). The standard by which an appellate court reviews a trial court's order confirming an arbitration award under the Federal Arbitration Act is that questions of law are reviewed de novo and findings of fact are reviewed only for clear error. See Riccard v. Prudential Ins. Co., 307 F.3d 1277, 1289 (11th Cir.2002).

Analysis

Hereford asks this Court to reverse the trial court's judgment affirming the arbitrator's decision and to vacate the arbitrator's decision because, she argues, the arbitrator manifestly disregarded the law in entering a summary judgment in favor of Horton. Before we can reach that question, however, we must determine whether in light of the United States Supreme Court's recent decision in Hall Street Associates, L.L.C. v. Mattel, Inc., ___ U.S. ___, 128 S.Ct. 1396, 170 L.Ed.2d 254 (2008), manifest disregard of the law remains a basis for obtaining relief from an arbitrator's award under the Federal Arbitration Act.

The Federal Arbitration Act, 9 U.S.C. § 2, provides, in pertinent part: "A written provision in ... a contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction ... shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract." "Section 2 has the effect of preempting conflicting Alabama law, in particular § 8-1-41(3), Ala.Code 1975, which makes predispute agreements to arbitrate unenforceable." Title Max of Birmingham, Inc. v. Edwards, 973 So.2d 1050, 1053 (Ala.2007) (citing Garikes, Wilson, & Atkinson, Inc. v. Episcopal Found. of Jefferson County, Inc., 614 So.2d 447, 448 (Ala.1993)). Therefore, in Alabama, predispute arbitration provisions are enforceable so long as the party moving to compel arbitration proves "the existence of a contract calling for arbitration and ... that that contract evidences a transaction involving interstate commerce." Title Max of Birmingham, 973 So.2d at 1052 (citing Polaris Sales, Inc. v. Heritage Imports, Inc., 879 So.2d 1129, 1132 (Ala. 2003))....

To continue reading

Request your trial
27 cases
  • Tucker v. Ernst & Young, LLP
    • United States
    • Alabama Supreme Court
    • 13 June 2014
    ...fact are reviewed only for clear error. See Riccard v. Prudential Ins. Co., 307 F.3d 1277, 1289 (11th Cir.2002).”Hereford v. D.R. Horton, Inc., 13 So.3d 375, 378 (Ala.2009).III. AnalysisCourts must enforce awards entered in arbitration proceedings conducted pursuant to the FAA unless the ch......
  • Honea v. Raymond James Fin. Servs., Inc.
    • United States
    • Alabama Supreme Court
    • 30 June 2017
    ...1975, § 6–6–15, a "manifest disregard of the law" was a ground available for reviewing the award), overruled by Hereford v. D.R. Horton, Inc., 13 So.3d 375, 381 (Ala. 2009) ("[W]e hereby overrule our earlier statement in Birmingham News that manifest disregard of the law is a ground for vac......
  • Stage Stores, Inc. v. Gunnerson
    • United States
    • Texas Court of Appeals
    • 8 October 2015
    ...Horn, 901 So.2d 27, 53 (Ala.2004), overruled by Horton Homes, Inc. v. Shaner, 999 So.2d 462 (Ala.2008), overruled by Hereford v. D.R. Horton, Inc., 13 So.3d 375 (Ala.2009).8 Cat Charter, 646 F.3d at 844.9 Id.10 Id. at 844–45.11 Rain CII Carbon, 674 F.3d at 471.12 Id. at 471, 474.13 Id. at 4......
  • Custom Performance Inc. v. Dawson
    • United States
    • Alabama Supreme Court
    • 27 August 2010
    ...U.S. 52, 123 S.Ct. 2037 (2003).”Birmingham News Co. v. Horn, 901 So.2d 27, 44 (Ala.2004), overruled on other grounds, Hereford v. D.R. Horton, Inc., 13 So.3d 375 (Ala.2009), and Horton Homes, Inc. v. Shaner, 999 So.2d 462 (Ala.2008). Instead, the Federal Arbitration Act (“the FAA”), 9 U.S.C......
  • Request a trial to view additional results
1 books & journal articles

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT