Hetherington Letter Co. v. O. F. Paulson Const. Co.

Citation171 N.W.2d 264
Decision Date14 October 1969
Docket NumberNo. 52815,52815
PartiesHETHERINGTON LETTER COMPANY, Appellant Cross-Appellee, v. O. F. PAULSON CONSTRUCTION COMPANY, Appellee Cross-Appellant, v. MERCHANT'S NATIONAL BANK OF CEDAR RAPIDS, Iowa, Cross-Appellee.
CourtUnited States State Supreme Court of Iowa

J. D. Randall and D. G. Bleakley, Cedar Rapids, for appellant, cross-appellee, Hetherington Letter Co., and cross-appellee Merchant's Nat. Bank of Cedar Rapids, Iowa.

Remley & Heiserman, Anamosa, for appellee, cross-appellant.

RAWLINGS, Justice.

By action in equity plaintiff sought specific performance of a construction contract. Defendant cross-petitioned seeking foreclosure of its mechanic's lien. Trial to the court resulted in a decree which denied the specific performance sought by plaintiff and granted foreclosure of the lien subject to a deduction. Both parties appeal. We affirm in part, modify in part.

Hetherington Letter Company, plaintiff-appellant, cross-appellee, and O. F. Paulson Construction Company, defendant-appellee, cross-appellant, are separate corporate entities.

In the interest of brevity we shall, for purpose of this review, disregard Merchant's National Bank of Cedar Rapids, Iowa, mortgagee-intervenor, treating Hetherington Letter Company, plaintiff, and O. F. Paulson Construction Company, defendant, as the parties hereto.

Early in 1958 John D. Randall, an officer of Hetherington Company, and T. F. Paulson, vice-president of Paulson Company, entered into preliminary negotiations regarding partial reconstruction of a building owned by Hetherington Company in Cedar Rapids.

Contemporaneously Mr. Randall and T. F. Paulson discussed plaintiff's need for the services of an architect. The latter suggested, he being properly licensed and qualified, could so serve for a charge of $5 an hour, plus social security and pay roll taxes. Plaintiff corporation and T. F. Paulson, individually, thereafter proceeded under that oral arrangement.

September 22, 1958, plaintiff and defendant entered into a written contract (Exhibit 3), supplemented by 'General Conditions' (Exhibit 4), under which defendant agreed to provide all labor and materials necessary for 'repair and replacement' of the westerly 60 feet of the Hetherington structure.

Two letters were also submitted by defendant to plaintiff in accord with its request. The first (Exhibit 5), dated September 1, 1958, set forth in some detail the estimated prices for specified portions of the project. The other communication (Exhibit 6), bearing date September 15, 1958, designated the specific work to be performed. Exhibits 5 and 6 disclose the final total estimated cost was $55,600. Other relevant facts will be later considered.

Plaintiff here claims defendant failed to make the basement floodproof or to complete installation of a door leading to the second floor and finish a stairway wall.

Defendant takes the position it substantially performed pursuant to the contract, supplied extra labor and material, and should have benefit of the relief it requests.

Trial court found the balance owing to Paulson Company, on the contract, was $5,331.60, plus $16,025.33 for extras, or a total of $21,356.93, less $7,455.84 for failure to floodproof the basement, leaving a net of $13,901.09, as to which defendant's mechanic's lien was ordered established and enforced.

Eight 'errors' are assigned by plaintiff, deemed by us to be propositions (rule 344(a)(3), Rules of Civil Procedure) in support of a reversal. Its argument, however, is limited to alleged error by trial court in these four respects: (1) holding plaintiff liable to defendant for more than plaintiff balance due on contract price, by reason of fraud on the part of T. F. Paulson, the architect; (2) application of an erroneous standard for measurement of damages to which plaintiff is entitled because of defendant's failure to floodproof the basement; (3) finding plaintiff liable to defendant for extra labor and material based upon waiver of written contract terms; and (4) holding plaintiff not entitled to specific performance.

On the other hand defendant urges a reversal upon the premise trial court erroneously held, defendant agreed to construct a floodproof basement, and resultantly deducted $7,455.84 from the amount found owing it from plaintiff.

To some degree these propositions unavoidably overlap. To that extent they will be by us accordingly considered.

I. Regarding plaintiff's demand for specific performance, this court said in McCarty v. Jeffers, Iowa, 154 N.W.2d 718, 721: 'The general rules governing consideration of this case with ample citation of authority are found in Incorporated Town of Wahpeton, etc. v. Rocklin, 254 Iowa 948, 953, 119 N.W.2d 880, 883. 'A suit for specific performance is not a matter of absolute right but is always addressed to the sound judicial discretion of the court. * * * The court will not decree specific performance when the circumstances of the case show it would be inequitable to do so. * * * And, while the chancellor who tries the case has a considerable discretion in granting or withholding the remedy, such discretion is not absolute. We have on occasion found that it should not have been exercised, and have reversed decrees granting performance. * * *"

II. Also, in Peterman v. Hardenbergh, 250 Iowa 931, 933, 97 N.W.2d 152, 153, is found this apt statement relative to mechanic's lien foreclosures: '* * * as we pointed out in Huffman v. Hill, (245 Iowa 935, 65 N.W.2d 205) a technical, exact and perfect performance is not required nor necessary. If the terms of the contract are established by a preponderance of the credible evidence, and there is shown a substantial performance of its terms, the builder is entitled to the contract price plus extras, less reasonable sums for small items not furnished and reasonable damages on account of slight defects in performance. Lautenbach v. Meredith, 240 Iowa 166, 172, 173, 35 N.W.2d 870, 874. This is particularly true in equity suits, which are somewhat more liberal than actions at law. Littell v. Webster County, 152 Iowa 206, 215, 131 N.W. 691, 132 N.W. 426; Hayes v. Ramsey, 205 Iowa 167, 169, 217 N.W. 808, 809.' See also Sitzler v. Peck, Iowa, 162 N.W.2d 449, 451.

III. Plaintiff bases its right to specific performance largely, if not entirely, upon the testimony of Mr. Randall.

He testified, in part, to the effect defendant orally agreed to floodproof the basement but failed to do so.

At the outset we find nothing in the contract (Exhibits 3 and 4), or the letters (Exhibits 5 and 6), which refers to the matter of floodproofing. In course of trial Mr. Randall was permitted, over timeley and proper objection, to give testimony regarding conversations on that subject between him and T. F. Paulson. This was apparently permitted by trial court because of the fraud alleged by plaintiff in connection with execution of the contract. See in this regard Lamasters v. Springer, 251 Iowa 69, 73, 99 N.W.2d 300, and Bales v. Massey, 241 Iowa 1084, 1090, 43 N.W.2d 671.

It is to us evident T. F. Paulson, individually, was the architect for plaintiff corporation. In fact we find in the record no evidence disclosing Paulson Company, a corporation, could legally serve in that capacity. See chapter 118, Code, 1966; 6 C.J.S. Architects § 5, page 296; 5 Am.Jur.2d, Architects, section 2, page 662; and Annos. 56 A.L.R.2d 726.

Finally on this matter, plaintiff's argument on appeal is directed not to fraudulent representations or conduct by Paulson Company, but entirely toward Paulson the architect. He is not a party to this action, and fraud, if any, on his part personally is not here involved.

Under these circumstances we accord no further consideration to the matter of fraud as an element in the case at bar. See in this regard rule 344(a)(4) (Third), R.C.P., and Quint-Cities Petroleum Co. v. Maas, 259 Iowa 122, 126, 143 N.W.2d 345.

IV. Article 2 of the contract [Exhibit 3] states: 'The Owner, through the Architect, may from time to time, By written instructions or drawings issued to the Contractor, make changes in the abovenamed Drawings and Specifications, issue additional instructions, require additional work or direct the omission of work previously ordered, and the provisions of this contract shall apply to all such changes, modifications and additions with the same effect as if they were embodied in the original Drawings and Specifications. Since the cost of all such changes is to merge in the final cost of the work, articles 15 and 16 of the General conditions of the Contract are annulled, unless elsewhere especially made applicable.' (Emphasis supplied).

Trial court found this clause served to nullify Articles 15 and 16 of the 'General Conditions' agreement (Exhibit 4). We find no basis upon which to hold otherwise.

Furthermore defendant, by its pleadings, alleged plaintiff waived the restrictive provisions of Article 2, supra, with respect to All extras supplied, and trial court agreed.

As stated in 13 Am.Jur.2d, Building and Construction Contracts, section 24, page 26: 'Although stipulations in building or construction contracts requiring written orders or agreements for extra work or alterations are valid and binding so long as they remain in effect, it is equally well settled that they may be avoided by the parties to the contract. The courts have adopted various theories of avoidance, which may be classified as those of independent contract, modification or rescision, waiver, and estoppel.

'A waiver of such stipulation by the owner is the theory on which it is most frequently avoided. Among the acts or conduct amounting to waiver are the owner's knowledge...

To continue reading

Request your trial
6 cases
  • National Equipment Rental, Ltd. v. Estherville Ford, Inc.
    • United States
    • Iowa Supreme Court
    • December 23, 1981
    ...Seley. The situation is analogous to clauses in contracts which are waived by subsequent conduct. Hetherington Letter Co. v. O. F. Paulson Construction Co., 171 N.W.2d 264, 267 (Iowa 1969), opinion supplemented, 173 N.W.2d 575 (Iowa 1970); Benson & Marxer v. Brown, 190 Iowa 848, 179 N.W. 81......
  • Eastline Corp. v. Marion Apartments, Ltd.
    • United States
    • Mississippi Supreme Court
    • May 4, 1988
    ...1284 (1977); Charles Burton Builders, Inc. v. L & S Constr. Co., Inc., 260 Md. 66, 271 A.2d 534 (1970); Hetherington Letter Co. v. O.F. Paulson Constr. Co., 171 N.W.2d 264 (Iowa 1969); Hi-Valley Constructors, Inc. v. Heyser, 163 Colo. 1, 428 P.2d 354 (1967); Honolulu Roofing Co., Ltd. v. Fe......
  • Armour and Company v. Nard, 71-1433
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • June 7, 1972
    ...v. Nutrena Mills, Inc., 294 F.2d 505, 512-516 (CA8 1961) affirming 187 F.Supp. 415 (N.D.Iowa 1960); Hetherington Letter Co. v. Paulson Construction Co., 171 N.W.2d 264 (Iowa 1969), supplemented 173 N.W.2d 575, 576 (Iowa 1970). We also note that a review of the record demonstrates that Nard ......
  • Hetherington Letter Co. v. O. F. Paulson Const. Co., 54641
    • United States
    • Iowa Supreme Court
    • December 15, 1971
    ...appellant. Remley, Heiserman & Story, Anamosa, for appellee. PER CURIAM: This is a sequel to our opinion in Hetherington Letter Co. v. O. F. Paulson Const. Co., Iowa, 171 N.W.2d 264 as supplemented in 173 N.W.2d 575. We there found against Hetherington on the appeal and on Paulson's cross-a......