Hewlett-Packard Co., Inc. v. Berg

Decision Date06 April 1993
Docket NumberHEWLETT-PACKARD,No. 94-2251,94-2251
Citation61 F.3d 101
PartiesCOMPANY, INC., Plaintiff, Appellant, v. Helge BERG, etc., et al., Defendants, Appellees. . Heard
CourtU.S. Court of Appeals — First Circuit

Richard Allan Horning with whom Horning, Janin & Harvey, Kevin P. Light, Choate, Hall & Stewart and Robert W. Sutis were on brief, for appellant.

David A. Burman, for appellees.

BOUDIN, Circuit Judge, BOWNES, Senior Circuit Judge, and STAHL, Circuit Judge.

BOUDIN, Circuit Judge.

Hewlett-Packard appeals from an order of the district court confirming an arbitration award rendered in a business dispute with appellees Helge Berg and Lars Skoog and rejecting Hewlett-Packard's requests for a stay of the confirmation proceeding or a declaration that it is entitled to a set-off for the award. The case presents several difficult legal issues which can be understood only after a brief description of the facts and prior proceedings.

I. BACKGROUND

In March 1982, Apollo Computer, now owned by Hewlett-Packard, entered into a two-year distributorship contract with a Swedish company called Dicoscan Distributed Computer Scandinavia to sell Hewlett-Packard products in several Nordic countries. The 1982 contract included an agreement to submit any dispute under the contract to binding arbitration. In March 1984, the parties executed a new distributorship contract, which also contained an arbitration clause.

In the meantime, during 1983 and 1984, Dicoscan experienced financial problems. In mid-1984, Apollo claimed that Dicoscan was far behind in its payments. In September, Apollo terminated the 1984 agreement. The following month, Dicoscan filed for bankruptcy. The bankruptcy court assigned to Berg and Skoog, directors and officers of Dicoscan, the right to bring claims against Apollo based on the contracts.

Berg and Skoog filed a request for arbitration with the International Chamber of Commerce Court of Arbitration, claiming millions of dollars of damages arising out of Apollo's unilateral termination of the 1984 agreement. Apollo counterclaimed in the arbitration by asserting that the Swedish company had failed to pay about $10,000 due on the 1984 contract and about $207,000 due under the 1982 contract. After a dispute about Berg and Skoog's right to invoke arbitration, see Apollo Computer, Inc. v. Berg, 886 F.2d 469, 473 (1st Cir.1989), an arbitration proceeding was begun.

The arbitrators were required by the parties' contracts to apply Massachusetts law. Ultimately, the arbitrators awarded around $700,000 plus interest to Berg and Skoog, but allowed a set-off for the $10,000 that Dicoscan still owed Apollo under the 1984 contract. To both parties' surprise, the tribunal held that it was without jurisdiction to decide Apollo's more substantial claim based on the 1982 contract, ruling that the 1982 contract was not within the Terms of Reference issued by the arbitrators at the beginning of the proceeding.

As a result, Apollo was left with a sizable obligation to Berg and Skoog on the 1984 contract without a determination of its claim for more than $207,000 on the 1982 contract. Apollo unilaterally decided to pay the arbitration award amount but subtracted the $207,000 plus interest (together, about $300,000) as a "setoff in recoupment," which, it said, is a time-honored common law doctrine embraced in Massachusetts courts. Apollo also filed a request with the tribunal for a second arbitration regarding the 1982 contract. That tribunal has indicated that it will hear the arbitration.

In January 1993, Apollo (later succeeded as the plaintiff by Hewlett-Packard) filed the complaint in this action with the Massachusetts district court. Hewlett-Packard requested that the district court (1) declare that Hewlett-Packard was entitled to the $207,000 set-off and that the arbitration award is fully satisfied, and (2) vacate the tribunal's award and correct it. Hewlett-Packard later withdrew its second claim for relief.

Berg and Skoog moved to dismiss the complaint, arguing that such declaratory relief is unavailable as to foreign arbitration awards. Later, Berg and Skoog moved for confirmation of the arbitration award. Hewlett-Packard opposed confirmation of the award on the ground that, by failing to include its 1982 set-off, the award was contrary to public policy. In the alternative, Hewlett-Packard moved to stay confirmation, pending the outcome of the second arbitration. Hewlett-Packard also asked the court to compel arbitration as to its 1982 claim.

On November 7, 1994, the district judge filed a memorandum, together with a separate order, disposing of all of these motions. The court's order compelled arbitration under the 1982 contract but it confirmed the award previously made by the tribunal on the 1984 contract. The court said that it was without power to stay the confirmation proceeding, as Hewlett-Packard had requested, and that the request for a set-off was an improper attempt to modify the tribunal's award.

Apparently ready to enforce the now-confirmed arbitration award, Berg and Skoog moved the court for entry of final judgment, and proffered a detailed judgment specifying the award, interest and attorney's fees. Four days later, Hewlett-Packard filed its notice of appeal and thereafter filed a response disputing certain aspects of the proposed judgment. The district court has not acted on the motion for entry of final judgment; and no such judgment has been entered.

II. DISCUSSION

Hewlett-Packard purports to appeal all three of the district court's adverse actions: the confirmation of the arbitration award, the refusal to stay that confirmation proceeding pending the outcome of the second arbitration; and the rejection of Hewlett-Packard's set-off claim declaration. Commendably, Hewlett-Packard has alerted us to a possible jurisdiction problem, which this court is obliged to consider. We do so but caution future panels that the jurisdictional problems have not been briefed in this case.

Nothing in the record in this case purports to be a "final judgment," set forth in a separate document as required by Fed.R.Civ.P. 58, disposing of all claims. Thus, in formal terms there is no basis for appeal of a "final decision" under 28 U.S.C. Sec. 1291, even if the court actually resolved all of the claims before it. Indeed, as already noted, the defendants have pending a motion that requests entry of a "final judgment."

Nevertheless, the November 7 order, insofar as it confirms the arbitration award, is appealable now because Congress directed in the statute governing arbitration-related appeals that such an "order" confirming an award should be immediately appealable. 9 U.S.C. Sec. 16(a)(1)(D). The reason is a pro-arbitration policy designed to expedite confirmation of arbitration awards. This is clear from precedent and scholarly commentary. See, e.g., 15B C. Wright, A. Miller & E. Cooper, Federal Practice and Procedure Sec. 3914.17, at 9-12, 32-34 (2d ed. 1992).

There is one technical hitch. Seemingly, the order confirming the award is not itself a judgment that can be collected through court processes until it is entered on the docket as a judgment. See 9 U.S.C. Sec. 13. This has nothing to do with the final judgment rule; rather, the statute that governs confirmations provides that after a confirmation is ordered, a separate "entry of judgment" must be made pursuant to that order, and it is only at that stage that "[t]he judgment so entered ... may be enforced as if it had been rendered in an action in the court in which it is entered." Id.

Nevertheless, the Federal Rules of Civil Procedure do not say that appeals can only be taken from judgments; on the contrary, they contemplate that, subject to the complex rules that determine what is immediately appealable, there may be such a thing as an "appealable order" that is not a judgment. Fed.R.Civ.P. 79(b). And, as already noted, Congress has designated as immediately appealable "an order ... confirming ... an [arbitration] award." 9 U.S.C. Sec. 16(a)(1)(D).

Our position is not at odds with Middleby Corp. v. Hussmann Corp., 962 F.2d 614 (7th Cir.1992). Middleby held that no immediate appeal could be taken where the district court issued an order of confirmation but declined to enter judgment after making a specific determination to delay giving effect to the confirmation order until further proceedings were concluded. Here, by contrast, the district court denied the requested stay, and the confirmation order is immediately effective, requiring only the filing of specified papers with the clerk to permit "the entry of judgment thereon." 9 U.S.C. Sec. 13.

Because the confirmation order is appealable, we think that there is also before us Hewlett-Packard's claim that the confirmation proceeding should have been stayed. The reason is simply that the underlying argument for a stay is also an objection to the confirmation order itself. To this extent, it is effectively an interlocutory ruling made in the process of approving the confirmation request and like any other such interlocutory ruling it is reviewable at the time that the confirmation order itself is brought up on appeal. Cf. Stringfellow v. Concerned Neighbors in Action, 480 U.S. 370, 375, 107 S.Ct. 1177, 1181, 94 L.Ed.2d 389 (1987); 15A Wright, Miller & Cooper, supra, Sec. 3905.1, at 249-63.

A similar argument might also be made to justify an appeal now based on the district court's refusal to declare Hewlett-Packard's right to the set-off it asserted. The problem is complicated, but we see no need to resolve the complexities. Whether or not the refusal to allow the set-off is an appealable issue, the refusal at this time turns out not to be a legal error, so the jurisdictional issue need not be decided. See Norton v. Mathews, 427 U.S. 524, 530-32, 96 S.Ct. 2771,...

To continue reading

Request your trial
40 cases
  • Gueyffier v. Ann Summers, Ltd.
    • United States
    • California Court of Appeals Court of Appeals
    • 26 d4 Outubro d4 2006
    ...disputes. (9 U.S.C. § 2; Industrial Risk Insurers v. M.AN. Gutehoffnungshutte GmbH, supra, 141 F.3d at p. 1440; Hewlett-Packard Co. v. Berg (1st Cir.1995) 61 F.3d 101, 106.) By contrast chapter 2 of the United States Arbitration Act involves foreign commerce. In a February 9, 1970 hearing b......
  • Lummus Global Amazonas v. Aguaytia Energy Del Peru
    • United States
    • U.S. District Court — Southern District of Texas
    • 27 d3 Março d3 2002
    ...how courts have addressed situations in which the form of the arbitration award presented similar problems. In Hewlett-Packard Co., Inc. v. Berg, 61 F.3d 101 (1st Cir. 1995), the plaintiffs, assignees in bankruptcy, filed a request for arbitration against a company that had unilaterally ter......
  • Hardy Exploration & Prod. (India), Inc. v. Gov't of India
    • United States
    • U.S. District Court — District of Columbia
    • 7 d4 Junho d4 2018
    ...Four Seasons Hotels & Resorts, B.V. v. Consorcio Barr S.A. , 377 F.3d 1164, 1172 n.7 (11th Cir. 2004) ; see also Hewlett–Packard Co. v. Berg , 61 F.3d 101, 106 (1st Cir. 1995) (concluding that a district court may consider staying a case in broader circumstances than those found in Article ......
  • Ministry of Def. & Support for the Armed Forces of the Islamic Republic of Iran v. Cubic Def. Sys., Inc.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • 15 d4 Dezembro d4 2011
    ...to enforce the judgment, there is good reason why execution should be postponed.” (footnote omitted)); cf. Hewlett–Packard Co., Inc. v. Berg, 61 F.3d 101, 105–06 (1st Cir.1995) (holding that a district court has discretion, in an action under the New York Convention, to stay confirmation of......
  • Request a trial to view additional results
3 books & journal articles
  • Chapter 2
    • United States
    • Full Court Press Alternative Dispute Resolution in the Work Place
    • Invalid date
    ...Shield of Massachusetts v. BCS Insurance Co., 671 F.3d 635, 638 (7th Cir. 2011).[114] . 28 U.S.C. § 1291. See Hewlett-Packard Co. v. Berg, 61 F.3d 101, 104 (1st Cir. 1995).[115] . Bull HN Information Systems v. Hutson, 229 F.3d 321 (1st Cir. 2000). The court pointed out both that its decisi......
  • Jarred Pinkston, Toward a Uniform Interpretation of the Federal Arbitration Act: the Role of 9 U.s.c. Sec. 208 in the Arbitral Statutory Scheme
    • United States
    • Emory University School of Law Emory International Law Reviews No. 22-2, December 2008
    • Invalid date
    ...power to stay confirmation proceedings that do not arise from either the text of the N.Y. Act or FAA. Hewlett-Packard Co., Inc. v. Berg, 61 F.3d 101, 105-06 (1st Cir. 1995) (stating that the power to stay a proceeding is incidental to the power inherent in every court to control the disposi......
  • Gaining Appellate Review by "manufacturing" a Final Judgment Through Voluntary Dismissal of Peripheral Claims - Rebecca A. Cochran
    • United States
    • Mercer University School of Law Mercer Law Reviews No. 48-3, March 1997
    • Invalid date
    ...end of a case: "Every judgment shall be set forth on a separate document." FED. R. Crv. P. 58. 93. See, e.g., Hewlett-Packard Co. v. Berg, 61 F.3d 101 (1st Cir. 1995) (without a final judgment set out in a separate document, there is no final decision for appellate review even if the trial ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT