Hoffman v. Toll

Decision Date17 September 1891
Docket Number268
Citation28 N.E. 557,2 Ind.App. 287
PartiesHOFFMAN ET AL. v. TOLL
CourtIndiana Appellate Court

From the Hamilton Circuit Court.

Judgment affirmed.

T. J Kane and T. P. Davis, for appellants.

J Stafford and T. E. Boyd, for appellee.

OPINION

CRUMPACKER, J.

Hoffman & Barrett, as special partners for that purpose only, took a contract from the school trustees of the city of Noblesville to furnish materials and construct a public school building in said city, according to certain plans and specifications.

They employed Toll to do the plastering upon the building, and when the structure was almost completed the school trustees contracted with the firm of Smead & Co. to put in machinery and apparatus for heating and ventilating, and a dry-closet system. Smead & Co. contracted with Barrett, who assumed to act for the firm of Hoffman & Barrett, to do the work about the building in connection with such heating and ventilating apparatus, and Barrett, so assuming to act for his firm, employed Toll to do the additional plastering made necessary by such improvements. Toll did the work in the belief that it was a partnership undertaking, and then brought this suit against Hoffman & Barrett to recover a general balance alleged to be due from them as partners on account of the plastering.

Barrett was duly served with process and suffered default, but Hoffman appeared to the action and filed an answer in four paragraphs. The first was the general denial, the second and third were pleas of payment, and the fourth was a combination of answer and counter-claim, in which it was alleged that Hoffman & Barrett undertook the construction of the building according to certain plans and specifications, as special partners, and as such they employed Toll to do the plastering, but that he had failed to complete the work according to his contract, and that Hoffman & Barrett had settled with the school trustees for the work and agreed with them that it would require $ 73.17 to complete Toll's contract, and the trustees retained that amount from the contract-price of the building, to be paid to Toll when he should finish his work; that Toll had knowledge of and assented to such arrangement, and that he had never completed the work.

It was also alleged that Hoffman had no part in the contract to put in the heating and ventilating apparatus, but that Barrett undertook said work on behalf of the firm without Hoffman's knowledge or consent, and that he employed Toll to do the additional plastering on behalf of the firm, without Hoffman's consent and without authority, and that such additional work amounted to $ 39.10.

No demurrer was filed to the answer, and a reply in general denial joined the issues. The cause was tried by a jury and a verdict returned in favor of Toll for $ 197.09, the full amount of his claim. The jury returned answers to a series of interrogatories submitted to them by the court at the defendant's request.

The defendant moved for judgment upon the interrogatories and for a new trial, both of which motions were overruled, and judgment was rendered upon the general verdict.

Motions were made by the defendant to modify the judgment, and overruled by the court.

This appeal was taken by Hoffman alone, and the alleged errors which he relies upon for the reversal of the judgment are:

1. In awarding judgment for the full amount of the verdict.

2. Overruling the motion for a new trial.

The first of these assignments is based upon the interrogatories, which, with the answers, are as follows:

"1. Did the defendants, Hoffman & Barrett, enter into a special partnership in June, 1888, to build a school-house in the city of Noblesville for the board of school trustees? Ans. Yes. C. J. McCole, foreman.

"2. As such partners did said defendants enter into a contract with said board of school trustees on 19th of June, 1888, to build said school-house according to the plans and specifications of the architect? Ans. Yes. C. J. McCole foreman.

"3. Was said plaintiff employed to do the plastering required to be done in building said house, under said contract of June 19th, according to said plans and specifications? Ans. Yes. C. J. McCole, foreman.

"4. If the plaintiff had completed the work he so undertook, what would have been due him therefor? Ans. $ 687.78. C. J. McCole, foreman.

"5. Is it true that the plaintiff had failed at the time of the commencement of this suit to complete the said work so undertaken by him according to the plans and specifications? Ans. Yes. C. J. McCole, foreman.

"6. Did the plaintiff, after the commencement of this suit, undertake to complete said work that he had left unfinished as aforesaid? Ans. Yes. C. J. McCole, foreman.

"7. Did the defendant Hoffman, in behalf of said Hoffman & Barrett and said board of school trustees, on January 19th, 1889, settle the matters between them, growing out of said contract, entered into between them in June, 1888? Ans. Yes. C. J. McCole, foreman.

"8. Did said defendant Hoffman, on said 19th of January, 1889, leave in the hands of said board of school trustees the amount of $ 73.17 to be paid to plaintiff when he should complete said work undertaken by him for Hoffman & Barrett, which they were required to do pursuant to said contract of June 19th? Ans. Yes. C. J. McCole, foreman.

"9. Did said board of school trustees notify said plaintiff that said sum of $ 73.17 was in their hands for him when he completed said work? Ans. Yes. C. J. McCole, foreman.

"10. Did the board of school trustees, on October 2d, 1888, enter into a contract with Isaac D. Smead & Co. to place in said school building a warning and heating apparatus and dry-closet system? Ans. Yes. C. J. McCole, foreman.

"11. Did the defendant Barrett enter into a contract with said Smead & Co. to do work relating to placing said warming and ventilating apparatus and dry-closet system in said building? Ans. Yes. C. J. McCole, foreman.

"12. Did the defendant refuse to have anything to do with said agreement and work? Ans. Yes. C. J. McCole, foreman.

"13. Did the defendant Hoffman authorize the execution of said...

To continue reading

Request your trial
1 cases

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT