Hollandsworth v. Nebraska Partners

Decision Date01 December 2000
Docket NumberNo. S-00-044.,S-00-044.
PartiesWilliam R. HOLLANDSWORTH, Appellee, v. NEBRASKA PARTNERS, doing business as Mead Cattle Company, Inc., Appellant.
CourtNebraska Supreme Court

Melvin C. Hansen and Matthew J. Buckley, of Hansen, Engles, Ketcham, Olson & Buckley, P.C., Omaha, for appellant.

Rolf Edward Shasteen, of Shasteen & Crawford, P.C., Lincoln, for appellee.

HENDRY, C.J., WRIGHT, CONNOLLY, GERRARD, STEPHAN, McCORMACK, and MILLER-LERMAN, JJ.

CONNOLLY, J.

In this appeal, we address whether the payment of a court-approved lump-sum settlement in a workers' compensation case is subject to a waiting-period penalty under Neb.Rev.Stat. § 48-125 (Reissue 1998). The appellee, William R. Hollandsworth, and the appellant, Nebraska Partners, doing business as Mead Cattle Company, Inc., entered into a settlement agreement, which was approved by a single judge of the Nebraska Workers' Compensation Court. Nebraska Partners did not deliver the settlement check to Hollandsworth within 30 days of the order approving the settlement, and the same judge awarded a waiting-period penalty. A review panel affirmed, and Nebraska Partners appeals. We conclude that a lump-sum settlement approved by the Workers' Compensation Court is subject to the waiting-period penalty provided for in § 48-125. Accordingly, we affirm.

BACKGROUND

In September 1997, Hollandsworth was involved in an accident while employed by Nebraska Partners. From April 29 to May 26, 1998, Hollandsworth received temporary total disability benefits. In June 1998, Hollandsworth filed a petition in the compensation court seeking further benefits, including benefits for permanent partial disability. The parties then reached a settlement agreement under which Hollandsworth would receive a lump-sum settlement of $21,500 in satisfaction of all claims he had against Nebraska Partners. The compensation court approved the settlement on April 9, 1999. On April 19, the insurance company for Nebraska Partners issued a check made out to Hollandsworth and his attorney in the amount of the settlement. However, Hollandsworth did not receive the check. On May 11, Hollandsworth filed a motion for penalty and attorney fees in the compensation court. On May 13, the law office representing Nebraska Partners hand delivered the check to the office of Hollandsworth's attorney. On May 15, Hollandsworth signed a "Receipt in Satisfaction" stating that he acknowledged receipt of the money and that "the settlement provided in the Lump Sum Settlement filed herein is as of this date fully paid and satisfied of record."

A hearing was held on the motion, during which Hollandsworth's attorney stated, "I waive any claim for an attorney's fee in these proceedings." Following the hearing, the single judge of the compensation court awarded a 50-percent waiting-period penalty pursuant to § 48-125 because the check was delivered after 30 days had passed from the approval of the lump-sum settlement. Nebraska Partners filed an application for review by a three-judge panel of the compensation court. The panel affirmed and awarded attorney fees because Nebraska Partners had appealed and had failed to obtain a reduction in the award. Nebraska Partners appeals.

ASSIGNMENTS OF ERROR

Nebraska Partners assigns, rephrased, that the compensation court erred in determining that payment on a court-approved lump-sum settlement is subject to a waiting-period penalty under § 48-125 and in calculating a penalty based on the entire amount of the lump-sum award. In addition, Nebraska Partners assigns that the review panel erred in affirming the decision of the compensation court and in awarding attorney fees.

STANDARD OF REVIEW

Pursuant to Neb.Rev.Stat. § 48-185 (Cum.Supp.2000), an appellate court may modify, reverse, or set aside a Workers' Compensation Court decision only when (1) the compensation court acted without or in excess of its powers; (2) the judgment, order, or award was procured by fraud; (3) there is not sufficient competent evidence in the record to warrant the making of the order, judgment, or award; or (4) the findings of fact by the compensation court do not support the order or award. Miller v. E.M.C. Ins. Cos., 259 Neb. 433, 610 N.W.2d 398 (2000); Torres v. Aulick Leasing, 258 Neb. 859, 606 N.W.2d 98 (2000).

Statutory interpretation presents a question of law, in connection with which an appellate court has an obligation to reach an independent conclusion irrespective of the decision made by the court below. Philpot v. Aguglia, 259 Neb. 573, 611 N.W.2d 93 (2000); Ferguson v. Union Pacific RR. Co., 258 Neb. 78, 601 N.W.2d 907 (1999). In the absence of anything to the contrary, statutory language is to be given its plain and ordinary meaning; an appellate court will not resort to interpretation to ascertain the meaning of statutory words which are plain, direct, and unambiguous. Id.

ANALYSIS

Nebraska Partners contends that the waiting-period penalty in § 48-125 applies only to delinquent periodic payments and that payment of a court-approved lump-sum settlement is not subject to the penalty.

Section 48-125 provides in part:
Except as hereinafter provided, all amounts of compensation payable under the Nebraska Workers' Compensation Act shall be payable periodically in accordance with the methods of payment of wages of the employee at the time of the injury or death; Provided, fifty percent shall be added for waiting time for all delinquent payments after thirty days' notice has been given of disability.

(Emphasis supplied).

Neb.Rev.Stat. § 48-138 (Reissue 1998) provides: "The amounts of compensation payable periodically under the law by agreement of the parties with the approval of the Nebraska Workers' Compensation Court may be commuted to one or more lump-sum payments...." Neb.Rev.Stat. § 48-139 (Reissue 1998) states that a lump-sum settlement or agreement approved by the court is final and conclusive.

We conclude that payment of a court-approved lump-sum settlement is subject to the provisions of § 48-125. Although § 48-125 speaks of periodic payments, it does not limit the application of a penalty to periodic payments only. Further, § 48-138 provides that periodic payments may be commuted to one or more lump-sum payments, thus bringing a lump-sum payment under the scope of § 48-125. In addition, § 48-139 provides that a court-approved lump-sum settlement is final and conclusive. We have previously held that as provided in § 48-125, waiting-period penalties apply to final adjudicated awards. Gaston v. Appleton Elec. Co., 253 Neb. 897, 573 N.W.2d 131 (1998); Roth v. Sarpy Cty. Highway Dept., 253 Neb. 703, 572 N.W.2d 786 (1998); Leitz v. Roberts Dairy, 239 Neb. 907, 479 N.W.2d 464 (1992). We further note that operative August 28, 1999, § 48-125 was amended to clearly state that the waiting-period penalty applies to payments made after 30 days from the entry of a final order, award, or judgment of the compensation court.

Nebraska Partners next contends that even if the lump-sum settlement is subject to a penalty, that penalty should be calculated only on the amount of those periodic payments which would have accrued as of April 9, 1999. We disagree.

Nothing in § 48-125 allows a penalty to be assessed on only a portion of a delinquent payment. We have said that the purpose of the 30 day waiting-period penalty and the provision for attorney fees as provided in § 48-125 are to encourage prompt payment by making delay costly if the award has been finally established. Roth v. Sarpy Cty. Highway Dept., supra.

We have also stated that the only legitimate excuse for delay in the payment of compensation benefits is the existence of a genuine dispute from a medical or legal standpoint. Id.; Grammer v. Endicott Clay Products, 252 Neb. 315, 562 N.W.2d 332 (1997); ...

To continue reading

Request your trial
12 cases
  • Dawes v. Wittrock Sandblasting & Painting
    • United States
    • Supreme Court of Nebraska
    • 1 Agosto 2003
    ...Inc., 259 Neb. 671, 611 N.W.2d 828 (2000). The penalty statute is to encourage prompt payment of benefits. Hollandsworth v. Nebraska Partners, 260 Neb. 756, 619 N.W.2d 579 (2000). In summary, the mandate for prompt payment of benefits requires that employees and insurers promptly handle and......
  • Tilt-Up Concrete, Inc. v. Star City/Federal, S-99-799.
    • United States
    • Supreme Court of Nebraska
    • 19 Enero 2001
    ...has an obligation to reach an independent conclusion irrespective of the decision made by the court below. Hollandsworth v. Nebraska Partners, 260 Neb. 756, 619 N.W.2d 579 (2000); Gage Cty. Bd. v. Nebraska Tax Equal. & Rev. Comm., 260 Neb. 750, 619 N.W.2d 451 ASSIGNMENTS OF ERROR Tilt-Up as......
  • Russell v. Stricker
    • United States
    • Supreme Court of Nebraska
    • 30 Noviembre 2001
    ...of justice or result in damage to the integrity, reputation, and fairness of the judicial process. Hollandsworth v. Nebraska Partners, 260 Neb. 756, 619 N.W.2d 579 (2000). We addressed the issue of plain error in the context of § 25-21,185.09 in Fiscel v. Beach, 254 Neb. 678, 578 N.W.2d 52 ......
  • Holdsworth v. Cooperative
    • United States
    • Supreme Court of Nebraska
    • 14 Junio 2013
    ...of a genuine dispute from a medical or legal standpoint that any liability exists. 16 To further encourage prompt payment, in Hollandsworth v. Nebraska Partners, 17 we held that the payment of a court–approved lump-sum settlement in a workers' compensation case is subject to a waiting-perio......