Hunt Const. Group, Inc. v. National Wrecking Corp.

Decision Date08 April 2008
Docket NumberCivil Action No. 05-165(RMC).
Citation542 F.Supp.2d 87
PartiesHUNT CONSTRUCTION GROUP, INC., Plaintiff and Counter-Defendant, v. NATIONAL WRECKING CORPORATION, et al., Defendants.
CourtU.S. District Court — District of Columbia

David Titus Dekker, Laura Ann Kamas, Michael S. McNamara, Thelen Reid Brown Raysman & Steiner LLP, Washington, DC, for Plaintiff and Counter-Defendant.

Michael C. Zisa, Stephen M. Seeger, Quagliano & Seeger, PC, Washington, DC, Leonard Arthur Sacks, Leonard A. Sacks & Associates, P.C., Rockville, MD, for Defendants.

MEMORANDUM OPINION

ROSEMARY M. COLLYER, District Judge.

Hunt Construction Group, Inc. ("Hunt") and National Wrecking Corporation ("NWC") entered into a construction subcontract whereby NWC agreed to provide certain excavation services at a project located in downtown Washington, D.C. The United States Surety Company ("USSC") and XL Reinsurance America, Inc. ("XL") (collectively the "Sureties") provided a performance bond with Hunt as the obligee and NWC as the principal/obligor. NWC allegedly caused delays in the project, so that, months after it had completed its work, Hunt "terminated" its subcontract with NWC and then sought to hold the Sureties liable under the performance bond for costs and expenses allegedly caused by NWC's tardy performance. This litigation ensued and the Sureties now ask for summary judgment.

I. BACKGROUND PACTS

NWC agreed to a subcontract ("Subcontract") with Hunt on or about October 6, 2003, to perform excavation and certain other work on the construction of an Embassy Suites Hotel in D.C. (the "Project"). NWC began the work in the same month and completed the mass excavation on April 6, 2004. Hunt alleges that NWC was required to complete the mass excavation no later than February 12, 2004. Hunt contends that NWC never properly staffed the Project and, from the beginning, failed to keep pace with the construction schedule. In an effort to keep on schedule, Hunt accelerated the performance of Rapid Response Construction, Inc. ("Rapid") when it first started concrete work on the footings on January 22, 2004, and kept the accelerated pace in place all the way through to the top of the building. According to Hunt, it incurred costs of $803,264 due to late mass excavation work by NWC.

Although the Subcontract called for NWC to give Hunt a "detailed plan and schedule for performing and coordinating its Work" within five days of signing the subcontract, Sureties' Mem. Ex. 1 § 9.3, NWC did not actually submit a schedule until sometime in December 2003. That schedule indicated that NWC would complete the mass excavation by February 25, 2004. Hunt says that it did not realize that there would be a substantial delay until early February 2004, when it confronted NWC. On February 5 and 6, 2004, Mr. Page, Hunt's Project Manager, sent letters to NWC complaining about the delay and warning that NWC might be liable for Hunt's increased costs.

On July 13, 2004, more than three months after NWC completed the mass excavation work for the Project and was no longer on site, Hunt sent NWC a letter captioned "Default Notice," indicating that it constituted "formal notice that National Wrecking Corporation is in default of its subcontract with Hunt Construction Group" ("the NWC Default Notice"). See Sureties' Mem. Ex. 6. The NWC Default Notice stated, in part:

National Wrecking's refusal to perform its subcontract obligation to perform the Work promptly and diligently, its failure to meet the Project Schedule, and its causing of delay to Hunt constitute material breach of the subcontract terms. During the Project, National Wrecking consistently failed to supply sufficient labor and supervision. National Wrecking also failed to perform its Work promptly and diligently, and to meet the Project Schedule. This resulted — and continues to result — in delay and interference with the work of other trades. Therefore, Hunt declares National Wrecking in default pursuant to Section 30.1 of the subcontract. This letter is to provide National Wrecking with three days notice that it intends to exercise the remedies for default provided in subcontract sections 30.[1](2), 30.1(3), 30.1(4), 30.1(5) and the other Subcontract provisions providing rights and remedies to Hunt.

Id. On that same day, Hunt also wrote to the sureties to give "formal notice" that NWC was declared to be in default ("USSC Notice of Default"). In part the USSC Notice of Default informed the Sureties:

Among other breaches, National Wrecking Corporation has refused to perform its work and has delayed the project. Hunt hereby demands that United States Surety Company and XL Reinsurance America, Inc. arrange for performance of National Wrecking's obligations under the subcontract. Hunt looks to United States Surety Company and XL Reinsurance America, Inc. to remedy National Wrecking's failures to perform.

Sureties' Mem. Ex. 7. Of course, as Hunt acknowledges, the Sureties could not arrange for the performance of NWC's mass excavation work because the USSC Notice of Default was sent after NWC had completed the excavation. Sureties' Mem. Ex. 3, Deposition of Robert Decker ("Decker Dep.") at 145-147.1

The Sureties immediately engaged Robert Beers of Beers Construction Consultants, Inc., to investigate Hunt's claim. However, Mr. Beers had a very hard time getting Tom Page, Hunt's project manager and the ostensible author of the default notices, to respond to his calls and messages. When they finally did talk, on July 21, 2004, Mr. Page refused to speak to Mr. Beers without advice of Hunt's lawyers. The Sureties wrote to Mr. Page on August 10, 2004, seeking information but Mr. Page did not respond. On August 17, 2004, the Sureties sent a Status Inquiry to Mr. Page, asking about the progress of NWC's work. Mr. Page did not respond.

After months of silence, Hunt sent a "Notice of Termination" to NWC and copied the Sureties on October 14, 2004. The Sureties again asked Mr. Beers to investigate, Mr. Beers again attempted to contact Mr. Page (who had signed the Notice of Termination), and Hunt again failed to respond. The Sureties wrote to Hunt on November 30, 2004, asking that Hunt and Mr. Page cooperate with Mr. Beers's investigation and provide requested information immediately. Hunt did not respond.

However, Hunt did initiate this suit against NWC on January 25, 2005. Hunt added the Sureties as defendants on October 5, 2006, when it filed its Second Amended Complaint. Hunt alleges that the Sureties breached their bond obligations and owe it more than $800,000.

II. LEGAL STANDARDS
A. Jurisdiction and Venue

Plaintiff rests jurisdiction on the diversity of the parties and the amount in dispute. See 28 U.S.C. § 1332(a)(2). Am. Compl. ¶ 9. Jurisdiction is determined based on the facts as they existed at the time the case was filed. Grupo Dataflux v. Atlas Global Group, L.P., 541 U.S. 567, 570-71, 124 S.Ct. 1920, 158 L.Ed.2d 866 (2004). A court lacks diversity jurisdiction if there are litigants from the same state on opposing sides of the controversy. 28 U.S.C. § 1332(a)(1); see Prakash v. Am. Univ., 727 F.2d 1174, 1178 n. 25 (D.C.Cir. 1984). A corporation is deemed to be a citizen of the state in which it is incorporated and the state where it maintains its principal place of business. 28 U.S.C. § 1332(c)(1). The principal place of business for a corporation is usually its headquarters, where day-to-day business is conducted. Mastersorb-Cook v. Criss Bros. Iron Works, Inc., 722 F.Supp. 810, 812 (D.D.C.1989). The Court has jurisdiction over this matter, because the matter in controversy exceeds the sum or value of $75,000, exclusive of interests and costs, and is between citizens of different States. Further, the Court has personal jurisdiction over each of the parties because they are U.S. corporations doing business in the District of Columbia. Venue is also proper in this Court. A plaintiff can bring an action in (1) a judicial district where any defendant resides, if all defendants reside in the same State, (2) a judicial district in which a substantial part of the events or omissions giving rise to the claim occurred, or a substantial part of property that is the subject of the action is situated, or (3) a judicial district in which any defendant may be found, if there is no district in which the action may otherwise be brought. 28 U.S.C. § 1391(b). Venue is properly placed in the District of Columbia because the Defendants do business in the District of Columbia and the Project is located in the District of Columbia.

B. Summary Judgment

Under Rule 56 of the Federal Rules of Civil Procedure, summary judgment must be granted when "the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." Fed.R.Civ.P. 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); see also Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Diamond v. Atwood, 43 F.3d 1538, 1540 (D.C.Cir.1995). Moreover, summary judgment is properly granted against a party that "after adequate time for discovery and upon motion ... fails to make a showing sufficient to establish the existence of an element essential to that party's case, and on which that party will bear the burden of proof at trial." Celotex, 477 U.S. at 322, 106 S.Ct. 2548. To determine which facts are "material," a court must look to the substantive law on which each claim rests. Anderson, 477 U.S. at 248, 106 S.Ct. 2505 (1986). A "genuine issue" is one whose resolution could establish an element of a claim or defense and, therefore, affect the outcome of the action. Celotex, 477 U.S. at 322, 106 S.Ct. 2548; Anderson, 477 U.S. at 248, 106 S.Ct. 2505.

In ruling on a motion for summary judgment, the...

To continue reading

Request your trial
13 cases
  • United States v. Leebcor Servs.
    • United States
    • U.S. District Court — Eastern District of Virginia
    • August 18, 2022
    ...for loss suffered." Am. Sur. Co. v. Plank & Whitsett, Inc., 159 Va. 1, 165 S.E. 660, 663 (1932); see Hunt Constr. Group, Inc. v. Nat'l Wrecking Corp., 542 F. Supp. 2d 87, 95 (D.D.C. 2008). The relevant language from the Performance Bond contract is as Whenever [McKenney's] shall be, and be ......
  • LDT KELLER FARMS LLC. v. BRIGITTE HOLMES LIVESTOCK CO. INC.
    • United States
    • U.S. District Court — Northern District of Indiana
    • March 30, 2011
    ... ... See Wheeler v. Pilgrim's Pride Corp., 591 F.3d 355, 362 (5th Cir. 2009) (collecting ... ...
  • Sonoma Springs Ltd. P'ship v. Fid. & Deposit Co. of Md.
    • United States
    • U.S. District Court — District of Nevada
    • August 14, 2019
    ...and that the surety must immediately commence performing under the terms of the its bond."); Hunt Constr. Grp., Inc. v. Nat'l Wrecking Corp. , 542 F. Supp.2d 87, 95 (D.D.C. 2008) ("When an obligee fails to provide timely notice to a surety so it can exercise its options ..., the obligee has......
  • Sheet Metal Workers' Local Union No. 100 Wash., D.C. Area Pension Fund v. W. Sur. Co.
    • United States
    • U.S. District Court — District of Maryland
    • May 17, 2016
    ...payment plan. ECF No. 31 at 35-36. In support of this argument, Western Surety principally relies on Hunt Construction Group, Inc. v. National Wrecking Corp. , 542 F.Supp.2d 87 (D.D.C.2008). aff'd on other grounds , 587 F.3d 1119 (D.C.Cir.2009). In that case, the bond at issue secured perfo......
  • Request a trial to view additional results
2 books & journal articles
  • Chapter 10
    • United States
    • Full Court Press Business Insurance
    • Invalid date
    ...731 F. Supp.2d 1298 (M.D. Fla. 2010) District of Columbia Circuit: Hunt Construction Group, Inc. v. National Wrecking Corp., 542 F. Supp.2d 87 (D.D.C. 2008). State Courts: California: First National Insurance Co. v. Cam Painting, Inc., 173 Cal. App.4th 1355, 93 Cal. Rptr.3d 808 (2009); Amwe......
  • CHAPTER 11 Surety Bonds
    • United States
    • Full Court Press Insurance for Real Estate-Related Entities
    • Invalid date
    ...731 F. Supp.2d 1298 (M.D. Fla. 2010) District of Columbia Circuit: Hunt Construction Group, Inc. v. National Wrecking Corp., 542 F. Supp.2d 87 (D.D.C. 2008). State Courts: California: First National Insurance Co. v. Cam Painting, Inc., 173 Cal. App.4th 1355, 93 Cal. Rptr.3d 808 (2009); Amwe......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT