Husky Lumber Co., Inc. v. D. R. Johnson Lumber Co.

Decision Date06 June 1978
PartiesHUSKY LUMBER CO., INC., a corporation, Respondent, v. D. R. JOHNSON LUMBER COMPANY, a corporation, Appellant.
CourtOregon Supreme Court

Donald A. Dole, Roseburg, argued the cause and filed a brief for appellant. With him on the brief were Long, Neuner, Dole, Caley & Kolberg and Jeffrey Pugh, Roseburg.

Paul E. Geddes, Roseburg, argued the cause and filed a brief for respondent. With him on the brief were Geddes, Walton, Richmond, Nilsen & Smith, Roseburg.

Before HOLMAN, P. J., HOWELL and LENT, JJ., and JOSEPH, J. Pro Tem.

LENT, Justice.

Plaintiff brought this action at law to recover damages for defective lumber sold to it by the defendant. The case was tried to the court and resulted in a judgment in favor of the plaintiff for $4,662.15 in compensatory damages. The defendant on appeal challenges the amount of damages. We affirm.

Two issues are raised on appeal. The first is whether there is sufficient evidence to support the trial court's findings on the issue of damages. The second is whether the plaintiff was precluded from recovering the incidental damages claimed for failure to plead them specially.

The following facts are undisputed. Plaintiff, a lumber brokerage firm, purchased 103,092 board feet of mixed ponderosa and sugar pine lumber from defendant, a manufacturer of lumber, and resold the lumber to Klamath Molding Mill, Inc. (Klamath), a molding remanufacturing company. Representatives of Klamath, who picked up the shipment at the defendant's plant, inspected the lumber for grade and moisture content and found it to be within the appropriate standards. The lumber was then ripsawed into various widths and sent through a cutoff saw, where knots and other apparent and naturally occurring defects were cut out. The short pieces were then put through a "finger-jointer" to make boards of uniform length. These boards were then stored until they were needed for reprocessing to fill a particular order.

When the first order requiring this particular type of lumber was run, the quantity needed to fill the order was pulled from storage, resawed center, fed through a planer or molder, then inspected for defects. After approximately ten percent of the finger-jointed lumber was run through the molding process, it was discovered that a significant percentage of the lumber evidenced cracks or checking along the resawed surface. Interior checking of this type cannot be discovered at the initial inspection of the lumber or at any point prior to completion of the planing process. Only after the surface has been finished by the molder are these cracks detectable.

When Klamath discovered the defects, it called the plaintiff's representative, who in turn called the defendant to send representatives to the Klamath plant to inspect the lumber. The defendant's general manager, Donald Johnson, went with his mill manager and salesman to Klamath's plant and met there with Jay Robbins, Klamath's president. Robbins showed Johnson and his associates the defective lumber, and all agreed that the cracking was caused by improper kiln drying by the defendant. When lumber is kiln dried too rapidly, as this lumber was, the moisture on the inside cannot escape and, in effect, explodes, causing internal cracks.

Robbins first asked Johnson to take the lumber back, but the two men finally agreed to an arrangement more satisfactory to the defendant. Klamath would process the lumber in a manner which would yield maximum recovery, would tally the unsalvageable lumber, and would withhold payment accordingly.

At trial, additional terms of this agreement were in dispute. Defendant contended that Klamath agreed to store all the defective lumber at its plant, so that defendant could inspect and tally the amount before settlement. The trial court found that while Klamath did agree to salvage as much of the nondefective lumber as possible, it did not agree to set aside and store all the defective lumber for the defendant's inspection.

For the purposes of this appeal, the defendant accepts the trial court's finding as to the terms of the agreement, but contends that the award of damages was not supported by the evidence. The trial court found that the plaintiff had proved damages of $4,662.15, the exact amount prayed for in plaintiff's complaint.

Findings of fact of a law court are just as binding on us as a jury verdict. ORS 17.435; Hendrix v. McKee, 281 Or. 123, 126, 575 P.2d 134, 136 (1978). The scope of our review is limited by Article VII (Amended), § 3, of the Oregon Constitution, which states that " * * * no fact tried by a jury shall be otherwise re-examined in any court of this state, unless the court can affirmatively say that there is no evidence to support the verdict." See Shepler v. Weyerhaeuser Company, 279 Or. 477, 484, 569 P.2d 1040 (1977), cert. den. 434 U.S. 1051, 98 S.Ct. 903, 54 L.Ed.2d 805 (1978). Thus, if there is any evidence to support the trial court's award, we must affirm it.

Defendant's argument of insufficient evidence is based on the manner in which plaintiff attempted to establish a foundation for the amount of damages prayed for in the complaint at trial. The factual background appears to be as follows:

After approximately 65 to 70 percent of the lumber had been processed through the molder, because one of plaintiff's key employees was leaving the company, plaintiff asked to settle the account with Klamath, since Klamath had estimated it could take up to two years to completely process all of the shipment in question by filling orders as required. Robbins, Klamath's president, testified that Klamath had kept a running inventory of the unsalvageable lumber up to this point and applied the average percentage of unsalvageable material to the yet unprocessed material to come up with the figure of 11,008 board feet of total unsalvageable lumber. Klamath then took the average cost of all the material, increased by $10 per thousand board feet for shipping costs, and applied it to the total amount of defective lumber. To this product Klamath added $60 per 1,000 board feet for the cost of manufacturing through the molding process of the defective lumber and withheld the total amount, $4,662.15, from its payment to the plaintiff.

At trial, Robbins was cross-examined as to the manner and result of the tallies of the unsalvageable defective lumber. There appear to have been seven or eight separate tallies. Robbins discovered that he had inadvertently left three or four of the "tally slips" at his plant, but testified that he could recall what the final tally was. At the close of defendant's cross-examination of Robbins, defense counsel moved to strike the testimony of Robbins relating to damages in excess of that represented by records produced at trial on the basis that such testimony was either hearsay or not based on the witness' firsthand knowledge. The court denied the motion. Defendant has not assigned as error the trial court's denial of his motion. 1 Instead, defendant appears to contend that the testimony of this witness to facts represented by the missing tally sheets must be excluded upon this court's appellate review because it is not the best evidence of those facts. Having failed to make this "best evidence" objection at trial, however, defendant is precluded from raising it on appeal. 2 McEwen v. Ortho Pharmaceutical, 270 Or. 375, 421, 528 P.2d 522 (1974); Cox v. Ohio National Life Insurance Company, 250 Or. 7, 12, 438 P.2d 998 (1968); McCormick on Evidence, § 52 at 117 (2d ed 1972).

Even if we were to disregard the complained-of testimony, there was competent evidence, independent of any defects in that testimony, of the amount of damages. Defendant's exhibits 1 and 2, which were memos from Klamath to plaintiff and from plaintiff to defendant, indicated the total amount of defective lumber and the method used to arrive at the total amount of damages claimed (and awarded). Defendant offered these documents for substantive purposes without qualification. Now it attempts to limit their contents. The attempt is unavailing. 3 The contents of these two documents provide sufficient evidence of damages to sustain the trial court's award.

Defendant argues further that the judgment must be reversed for plaintiff's failure to prove its damages with "reasonable certainty." 4 In Cont. Plants v. Measured Mkt., 274 Or. 621, 624,...

To continue reading

Request your trial
7 cases
  • GPL Treatment, Ltd. v. Louisiana-Pacific Corp.
    • United States
    • Oregon Court of Appeals
    • July 18, 1995
    ...As the Supreme Court said in Cont. Plants v. Measured Mkt., 274 Or. 621, 624, 547 P.2d 1368 (1976), and Husky Lbr. v. D.R. Johnson Lbr. Co., 282 Or. 481, 579 P.2d 235 (1978), "reasonable certainty" signifies nothing more than "probability" and is found to refer to the kind of evidence requi......
  • Steele v. Mayoral
    • United States
    • Oregon Court of Appeals
    • November 4, 2009
    ...judgment record. The failure to assign error precludes our review of that ruling. ORAP 5.45(1); Husky Lbr. Co. v. D.R. Johnson Lbr. Co., 282 Or. 481, 487 n. 2, 579 P.2d 235 (1978); Olsen v. Deschutes County, 204 Or.App. 7, 21-22, 127 P.3d 655, rev. den., 341 Or. 80, 136 P.3d 1123 (2006). Ac......
  • Zehr v. Haugen
    • United States
    • Oregon Supreme Court
    • April 21, 1994
    ... ... See Feist v. Sears, Roebuck & Co., 267 Or. 402, 412, 517 P.2d 675 (1973) (stating ... See Yamaha Store of Bend, Inc. v. Yamaha Motor Corp., 310 Or. 333, 344, 798 ... See also Husky Lbr. Co. v. D.R. Johnson Lbr. Co., 282 Or. 481, ... ...
  • Bruer's Contract Cutting v. National Council on Compensation Ins.
    • United States
    • Oregon Court of Appeals
    • November 18, 1992
    ...and that that was error because they offered some evidence that net profits would have been earned. See Husky Lbr. Co. v. D.R. Johnson Lbr. Co., 282 Or. 481, 487-88, 579 P.2d 235 (1978); see also VonRavensberg v. Houck-Carrow Corp., 60 Or.App. 412, 416-17, 653 P.2d 1297 (1982). We agree wit......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT